Summary of Structure

S.No. Chainage CA Chainage P&P Span Type Status Remarks

1 0+034 0+034 1x2 Box Completed


2 0+310 0+310 10 MNB Completed
3 0+458 0+458 1x2 Box Completed
4 0+556 0+556 30 MNB Pending Due to Cos
5 0+868 0+868 1X12 VUP Completed
6 1+163 1+163 1x2 Box Completed
7 1+323 1+323 1x2 Box Completed
8 1+571 1+571 1X12 VUP Completed
9 1+703 1+703 1x2 Box RHS Completed
10 2+000 2+000 1x2 Box Completed

11 2+494 2+494 15 MNB WIP

12 2+964 2+964 1x2 Box Completed


13 3+212 3+212 1X12 VUP Completed
14 3+868 3+868 1X12 VUP Completed
15 4+229 4+229 10 MNB Completed

16 4+347 4+347 1x2 Box WIP

17 4+900 4+900 1x2 Box Completed


18 5+327 5+327 1x2 Box Alignment Issue
19 5+438 5+438 1X12 VUP Alignment Issue
20 5+900 5+900 1x2 Box Completed
21 6+247 6+247 1x2 Box Completed
22 6+403 6+403 1x40 Grade Seprater WIP
23 6+728 6+728 1x2 Box RHS Completed
24 7+200 7+200 1x2 Box Completed
25 7+250 7+250 1x80 Flyover WIP

ABSTRACT STATUS OF STRUCTURE WORKS


Particular Box MNB VUP Flyover GS Total
New Construction 14 4 5 1 1 25
Total = 14 4 5 1 1 25
Completed = 10 2 4 16
Under Progress = 3 1 - 1 1 6
Total Tackled = 13 3 4 1 1 22
Balance = 1 1 1 - - 3