Primary Sedimentation
Primary Sedimentation
com/homework-help/questions-and-answers/design-pyramid-shaped-primary-
sedimentation-tank-upwards-flow-received-w-w-area-10-000-pop-q29172109
Step 1
Given that :
Q max = 2.25M LD
V
t =
Q max
Explanation:
2.25
4 roof tanks are used then Qmax = = 0.5625M LD
4
V
t =
Q max
V V V ⋅ 24
t = = =
6 3 3
0.5625 ⋅ 10 Litres 3 m 0.5625 ⋅ 10
0.5625 ⋅ 10 ( )
d
V ⋅ 24
2 =
3
0.5625 ⋅ 10
3
V = 46.875m
Explanation:
Step 2
3
m
Surface loading rate = 35
2
m − d
Q 0.5625 ⋅ 1000
Surface area (S A) = = = 16.07m
2
S LR 35
2
S A = 16m
V 46.875
Depth of the tank d = = = 2.92 = 3m
SA 16
Explanation:
Step 3
Now Assuming L : B = 1.5 : 1
L ⋅ B = 16
1.5B ⋅ B = 16
B = 3.3m ≅ 3.5m
L = 4.8m ≅ 5m
Explanation:
3
m
Given production rate (S P R) = 0.014
P − d
3
m
Total sludge produced per day S = 0.014 ⋅ 10000 = 140
d
140
Sludge in each tank = = 35m
3
35 35
Additional depth to be provided = = = 2m
SA 5 ⋅ 3.5
Explanation: