IMPLEMENTATION SCHEDULE OF ENVIRONMENTAL MANAGEMENT MEASURES

TIME (MONTHS)
ENVIRONMENTAL
MEASURES ACTIONS YEAR YEAR YEAR YEAR
ASPECT YEAR 1 YEAR 5
10 20 30 36

A. PREVENTION AND MITIGATION PROGRAM OF ENVIRONMENTAL IMPACTS

GENERATION OF Control and Acquisition of PPE


GASES, NOISE, prevention
VIBRATIONS, AND Acquisition of Materials and Tools
PARTICULATE
Social media containers and/or
MATERIAL
sanitary trench

Reinstallation of Camp and


Latrine

ORE DISPOSAL AND Prevention Verify the physical stability of the


DISPLAY dismounts

Installation of topographic
controls

Design and construction of


stability walls

Design and construction of


diversion channels

Control and Remediate disturbed areas


prevention
VEGETATION AND Train staff to protect biodiversity
SOIL REMOVAL
Control and recovery of flora and
fauna

B. CONTINGENCIES PROGRAM
Prepare contingency plan

Acquisition of equipment and first


WORK ACCIDENTS Contingency aid materials

Training and coaching by


specialized personnel

C. ENVIRONMENTAL TRAINING AND EDUCATION PROGRAM

Condition and establish a training


area
Prevention
1Worker training
and training Design of a training plan

Train mining personnel

D. OCCUPATIONAL HEALTH AND SAFETY PROGRAM

Preparation of the occupational


DS Occupational health and safety plan
Health Policy 024 - Prevention
Training of mining personnel
2016-EM
Signage of the activity area

E. SOLID AND LIQUID WASTE MANAGEMENT PROGRAM

Preparation of solid waste


management plan
Generation of non-
Enabling areas and installation of
hazardous solid Mitigation
containers
waste
Training on solid and liquid waste
management.
Installation of water discharge
points
Water consumption Prevention
Maintenance and control of water
flow

Training on domestic effluents


Generation of
Mitigation construction of latrines, septic
domestic effluents
tanks

F. FUELS, GREASES AND LUBRICANTS MANAGEMENT PROGRAM

Fuel and lubricant management


training
Generation of spills,
C ontrol and Construction of fuel storage area
fires and/or
Mitigation
explosion

G. CLOSURE AND POST CLOSURE PROGRAMS


Cleaning and Removal of the
area

Generation of Remediation Soil Remediation


environmental and
Leveling and Revegetation
liabilities compensation
Landslide and runoff control

Control and follow up