Professional Documents
Culture Documents
PE S4HC PR DD2 R Ponse
PE S4HC PR DD2 R Ponse
Which of the following items would the IAE need to add to accommodate the
Customers requirements for this deal?"
Incorrect
Question 2
What are the possible options for partners to move an on-premise ECC on HANA
customer to SAP S/4HANA Cloud, private edition?
One step ECC on SAP HANA to SAP S/4HANA conversion together with on-
premise to PCE migration using the SUM DMO with System Move option
Migrate ECC on SAP HANA to ECC on SAP HANA in the PCE setup
followed by conversion to RISE with SAP S/4HANA Cloud, private edition
Convert ECC on SAP HANA to SAP S/4HANA in the on-premise setup
followed by migration to SAP S/4HANA Cloud, private edition
Correct
Question 3
What is the required duration for SAP ECS to perform the post processing
activities on production systems?
10 hours
14 hours
12 hours
16 hours
Correct
Question 4
Which is the most preferred option to move an on-premise ECC on any DB
customer to SAP S/4HANA Cloud, private edition?
Correct
Question 5
Additional Sandbox tier can be included in the BOM for 2 months.
() True
False
Correct
Question 6
How many dry runs are included as part of the migration process in the
production environment by ECS?
Correct
Question 7
What are the available DR SLA options for the customer Acme, Inc.?
Correct
Question 8
Which of the following is correct in terms of an additional Sandbox tier required
for this customer?
You will need to advise the IAE to add “SAP S/4HANA Cloud, additional
non-productive tier, private edition (S)” to the existing BoM in order to
accommodate the additional tier required by the customer
You will need to advise the IAE to adjust the FUE count for this customer to
above 135FUE’s to ensure that the QAS tier is accommodate as per the
customers requirement.
You will need to advise the IAE to add “SAP Cloud, memory extension for
productive tiers, private edition” to the existing BoM in order to
accommodate the additional Sandbox tier required by the customer
You will need to advise the IAE to add “SAP S/4HANA Cloud, additional
non-productive tier, private edition (L)” to the existing BoM in order to
accommodate the additional tier required by the customer
Correct
Question 9
What is the required duration for SAP ECS to perform the post processing
activities on non-production systems?
2 working days
3 working days
4 working days
5 working days
Correct
Question 10
SAP S/4HANA versions that have at least months of mainstream
maintenance left are allowed a “as-is" migration in PCE without upgrading to
latest S/AHANA version.
Correct
Question 11
How many additional Production application servers will be required when the
system is scaled up from the base tee shirt size for 512Gb HANA to the target
system size of 1TB HANA?
Correct
Question 12
How much block storage will be required on the HANA DB Server for backups
during the migration process if the source system DB is sized at 2TB HANA?
5TB
2TB
4TB
3TB
Correct
Question 13
What type of storage is included as part of the base cost in a Brownfield
Migration?
Correct
Question 14
How many external (customer invoked) DR tests are included with RISE with
SAP S/4HANA Cloud, private edition?
Correct
Question 15
How many full system refreshes is the customer entitled to in a contract year?
Correct
Question 16
Which of the following factors impact the build time?
Inclusion of a DR Environment
Incorrect
Question 17
Which additional and variable costs does the Partner Cloud Architect (PCA) need
to account for in a typical PCE Migration scenario?
Cost related to the Storage needed in the migration VM for copying the
Export dump for the S/4AHANA conversion
Cost related to temporarily increasing the bandwidth speed and the
Hyperscaler gateway port to speed up data transfer during the duration of
the Migration project
Cost of the block Storage to take any backup's during the conversion
process
Correct
Question 18
Best Practices can be implemented as part of the system or can be completed
after the systems have been handed over to the customer.
True
{0 False
Correct
Question 19
What are the available DR SLA options for the customer Acme, Inc.?
Incorrect
Question 20
Which of the below statements related to Migration VM are correct ?
For the PCE S/4HANA conversion and system copy opportunities, the
Migration VM method is provided to the partners by the SAP delivery team
to execute tasks which need OS / DB access like executing SUM / SWPM
etc. for Hyperscaler like AWS, Azure and GCP
Storage needed for Export dump for the S/AHANA conversion is already
assigned in the migration VM by default without the partner needing to add
the storage SKU in the BOM
Migration VM is available both as Linux as well as windows deployment
option
Migration VM method can be used for all SAP Products running on ABAP
as well as JAVA, running on all databases like HANA/ASE, for ex. SAP PO
running on ASE, SAP Business Objects etc.
Correct
Question 21
How many countries are included as part of the Best Practice activation service?
Correct
Question 22
How many additional application servers will be required when the system is
scaled up from the base tee shirt size for 512Gb HANA to the target system size
of 2TB HANA?
Correct
Question 23
What is maximum system size for the base option RISE with SAP S/4HANA
Cloud, private edition SKU deployed on SAP Data Center?
1TB
256GB
512GB
2TB
Correct
Question 24
The SAP Application System <SID> in the source system should match the SIDs
in the target system.
Correct