DETAILED ESTIMATE OF PLASTERING ON GROUND FLOOR OF BUILDING

Measurements
Quantity
Sl No. Details of Items No. Length Breadth Height (m2)
(m) (m) (m)
II Wall Plastering
1 Office 1 8.63 5 3.7 100.862
Column 1 1.23 3.7 4.551
Total 105.413
Deduction Openings
Door, D 1 1.2 2.7 3.24
Door, D1 1 1 2.7 2.7
Window, W 3 2 2 12
Window, W1 2 1.5 2 6
Total Deduction 23.94
Less Deduction 81.473
2 Room 1 6 5 3.7 81.4
Column 2 1.23 3.7 9.102
Total 90.502
Deduction Openings
Door, D 1 1.2 2.7 3.24
Door, D1 2 1 2.7 5.4
Window, W 1 2 2 4
Total Deduction 12.64
Less Deduction 77.862
3 Toilet 1 1 2.9 1.55 3.7 32.93
Deduction Openings
Door, D 1 1.2 2.7 3.24
Less Deduction 29.69
4 Library 1 6 11.9 3.7 132.46
Column 2 1.23 3.7 9.102
Total 141.562
Deduction Openings
Door, D 1 1.2 2.7 3.24
Window, W 7 2 2 28
Total Deduction 31.24
Less Deduction 110.322
5 Classroom 1 1 6 9 3.7 111
Column 2 1.23 3.7 9.102
Total 120.102
Deduction Openings
Door, D 1 1.2 2.7 3.24
Window, W 3 2 2 12
Total Deduction 15.24
Less Deduction 104.862
6 Toilet 2 1 20.17 3.7 74.629
Deduction Openings
Door, D 1 1.2 2.7 3.24
Door, D2 5 0.7 2.1 7.35
Total Deduction 10.59
Less Deduction 64.039
7 Passage 1 37.35 2.4 3.7 294.15
Deduction Openings
Door, D 7 1.2 2.7 22.68
Door, D1 1 1 2.7 2.7
Window, W 5 2 2 20
Opening 1 1.75 2 3.5
Lobby Opening 1 5.9 3.7 21.83
Stair Room Opening 1 1 2.8 3.7 10.36
Stair Room Opening 2 1 2.7 3.7 9.99
Total Deduction 91.06
Less Deduction 203.09
8 Lobby 1 6.25 5.9 3.7 89.91
Column 4 1.23 3.7 18.204
Total 108.114
Deduction Openings
Opening 1 1.5 2 3
Opening 1 1 2 2.1 4.2
Opening 2 1 5.9 3.7 21.83
Window, W1 2 1.5 2 6
Total Deduction 35.03
Less Deduction 73.084
9 Stair Room 1 1 6.25 2.8 3.7 56.61
10 Classroom 2 1 9 6 3.7 111
Column 2 1.23 3.7 9.102
Total 120.102
Deduction Openings
Door, D 1 1.2 2.7 3.24
Window, W 2 2 2 8
Window, W1 2 1.5 2 6
Total Deduction 17.24
Less Deduction 102.862
11 Classroom 3 1 6.3 9 3.7 113.22
Column 2 1.23 3.7 9.102
Total 122.322
Deduction Openings
Door, D 1 1.2 2.7 3.24
Window, W 3 2 2 12
Total Deduction 15.24
Less Deduction 107.082
12 Classroom 4 1 9 6 3.7 111
Column 2 1.23 3.7 9.102
Total 120.102
Deduction Openings
Door, D 1 1.2 2.7 3.24
Window, W 2 2 2 8
Window, W1 2 1.5 2 6
Total Deduction 17.24
Less Deduction 102.862
13 Stair Room 2 1 6.25 2.7 3.7 56.24
II Ceiling Plastering
1 Office 1 8.63 5 43.15
Beam 2 5 1.2 12
2 Room 1 1 6 5 30
Beam 1 5 1.2 6
3 Toilet 1 2.9 1.55 4.495
4 Library 1 6 11.9 71.4
Beam 1 1 6 1.2 7.2
Beam 2 1 11.9 1.2 14.28
5 Classroom 1 1 6 9 54
Beam 1 1 6 1.2 7.2
Beam 2 1 9 1.2 10.8
6 Toilet
Part 1 1 4.55 4.1 18.655
Part 2 1 1.42 1.9 2.698
7 Passage 1 2.4 37.35 89.64
Beam 7 2.4 1.2 20.16
8 Lobby 1 6.25 5.9 36.875
Beam 1 5.9 1.2 7.08
9 Classroom 2 1 9 6 54
Beam 2 6 1.2 14.4
10 Classroom 3 1 6.3 9 56.7
Beam 1 1 6.3 1.2 7.56
Beam 2 1 9 1.2 10.8
11 Classroom 4 1 9 6 54
Beam 2 6 1.2 14.4
Total 647.493
III Outside Plastering 1 162.77 3.7 602.249
Deduction Openings
Window, W 16 2 2 64
Window, W1 8 1.5 2 24
Front Opening 1 1 2 2.1 4.2
Front Opening 2 1 1.5 2 3
Front Opening 3 1 1.75 2 3.5
Total Deduction 98.7
Less Deduction 503.549