RISK REGISTER OF AYENSU STREET LIGHT INS

LIKELIHOO IMPACT IF
D OF RISK THE RISK
DATE RAISED RISK DESCRIPTION TO OCCUR OCCUR

ID
Workers may be expose to electrical
hazards during installation.
High High

1
Delay in procurement of necessary
materials could install the project. High Medium
2
Adverse weather condition such as
heavy rain or storm may impede Medium High
progress.
3
Unforseen expenses or cost
overruns ccould exceed the
allocated budget. High Medium

4
Local residents may be disturb by
the noise and activities associated
witth the street light installation. High low

5
Unexpected technical difficulties
may arise during the installation
process.
High High

6
Newly installed street lights may be
vulnerable to vandalism or theft.
Medium High

7
Disputes and disagreements with
contractors could lead to delays or
legal complication.
Medium High

8
STREET LIGHT INSTALLATION
SEVERITY OWNER MITIGATION ACTION
RATING BASE PERSON WHO ACTION TO MITIGATE THE RISK
ON IMPACT WILL MANGE
AND
LIKELIHOOD THE RISK

Ensure all worker are properly trained


in electrical safety procedures and
High Project Manager provide personal protective equipment.

Maintain close communication with


High Project Manager suppliers and have alternative sources
identified to mitigate delay.
Moniter weather forcast and plan work
Project accordingly. Have contigency plan in place
High
Supervisor for weather-related delays.

Conduct thorough cost estimation and


regualar review project finances. Have a
Financial contigency budget in place for
Medium
Manager unexpected costs.

Inform the residents inadvance about


the project timeline and protential
Project disruption.
Medium
Supervisor

Ensure the project team includes


experience technicians and engineers
Project capable of troubleshooting and
High resolving technical issuees promptly.
Supervisor

Implement security measures such as


surveillance camaras or vandalism
Project fixtures to deter criminal activities.
Medium
Supervisor

Clearly defind roles, responsibilities,


and expectations in contracts.
Maintain open communication and
Medium Project Manager address any issues promptly to prevent
escalation.