Professional Documents
Culture Documents
Test Work Permit Procedure
Test Work Permit Procedure
Email *
kingz ack0332@gmail.com
Apprentice Name:
AhmadZohaib
P. #:
6867
There are ____________ types of work permit in FFC-GM 1/1
None Of These
Personnel
Plant Facility
Both
Production
Maintenance
Safety
Retention time for permit after job completion is 0/1
One Month
One Week
Fortnightly
42 Days
Other:
Correct answer
42 Days
True
False
Correct answer
True
Pneumatic Tools operation is covered in 0/1
Correct answer
0%
15%
5%
40%
If a vehicle is fitted with spark arrestor, explosivity test is not required 1/1
True
False
Project & Electrical Engineer Co-Signing is required at excavation of depth more 1/1
than
6 inch
12 inch
18 inch
1 meter
1.5 meter
2 ft
Dosimeter badge is not mandatory for the Inspection Technician carrying out 1/1
Radiography
True
False
During radioactive source transportation the extent of radiations outside container1/1
should not be more than
8 hrs.
9 hrs.
12 hrs.
Correct answer
8 hrs.
19 %
19.5 %
21 %
Oxygen meter low value buzzer shall sounds if oxygen drops to 1/1
19 %
19.5 %
20 %
True
False
75 Degree
60 Degree
45 Degree
15 cm
30 cm
60 cm
Scaffolding structure more than 26 ft high requires fixing to some other structure 1/1
True
False
True
False
If the tools arrangement takes more than two hours after permit exchange, the 1/1
permit becomes Invalid or Void
True
False
Executing's agency
Initiating agency
Safety
After completion of job, Housekeeping is the responsibility of 1/1
Area Operator
Executing Crew
Toe Plates should not be provided around working platforms at heights 1/1
True
False
Confined space entry work permit is required for entry in excavation more than 1/1
220 cm
100 cm
150 cm
True
False
The meter scale above 60% indicates that the concentration in this range is almost 1/1
explosive.
True
False
For plant site, confined space entry attendant shall be arranged by ____________ 0/1
agency
Executing Agency
Correct answer
72 Volt
48 Volt
220 Volt
Earth Leakage Circuit Breaker (ELCB) with Isolating Transformer is to be 0/1
provided and located as close as possible to the source of power and must be safely
supported outside the confined space. for voltage above in confined space.
72 Volt
48 Volt
220 Volt
Correct answer
48 Volt
During shut down it may be possible to combine certain items of equipment on 1/1
one cold work permit. This is known as
Project
Blanket Permit
Any lifting greater than 75 percent of the rated capacity of crane or hoist used for 1/1
the operations.
Blind Lifting
Complicated Lifting
Heavy Lifting
Radiography should not be done without proper shielding near flame detectors of 1/1
B-601/602/605, F-202 and gas turbine, control compartment of gas turbine,
capacitance type transmitters installed at urea plant proximeter J.B's of all
vibration equipments and control rooms during normal plant operation.
True
False
If higher voltage electrical equipment is to be used inside Urea reactor, then the 1/1
Requesting Section must obtain approval from
DM Electrical
Electrical Engineer
GM M&O
During the Job inside confined space, Job Conditions are changed, What to do 1/1
first?
Get Help
Block & Bleed arrangement for confined space entry permit 0/1
Acceptable
Not Acceptable
Correct answer
Not Acceptable
Closed Valves
Blind
Venting
Correct answer
Blind
Hot Jobs
Cold Jobs
No Job
Entry Only
Radiography area is cordoned off as per 1/1
Area Requirement
Isotope Strength
Equipment Service
Coordination Engineer
Instrument Engineer
DM
No Co Signing is required
Coordination Engineer
Instrument Engineer
DM
No Co Signing is required
Prior to Starting a job, Who will explains Safety Instructions to Area Engineer / 1/1
Designate
Area Operator
Maintenance Supervisor
Shift Incharge
Coordination Engineer
Piping
Vessel
Structure Beam
Welding Machine
Correct answer
Structure Beam
Additional protective equipment are not required, what to be mentioned on work 1/1
permit
Ear Plug
Safety Goggles
None
Cotton Gloves
1/1
Ear Plug
Safety Goggles
None
Cotton Gloves
The Condition in which the permit is to be __________ if permit is not extended 1/1
after 1 hour of next shift.
Invalid
Re- issue
Valid
Stopped
Extend
The Condition in which the permit is to be __________ if the job scope extends. 0/1
Invalid
Re- issue
Valid
Stopped
Extend
Correct answer
Re- issue
The Condition in which the permit is to be __________ if workers are not using 1/1
PPEs mentioned on permit.
Invalid
Re- issue
Valid
Stopped
Extend
The Condition in which the permit is to be __________ if permit is extended for 0/1
next 9 hours during normal operation.
Invalid
Re- issue
Valid
Stopped
Extend
Correct answer
Invalid
The Condition in which the permit is to be __________ if any particular of the 1/1
permit is left unchecked or blank.
Invalid
Re- issue
Valid
Stopped
Extend
Invalid
Re- issue
Valid
Stopped
Extend
Correct answer
Stopped
The Condition in which the permit is to be __________ if SCABA placed for 0/1
confined space entry is without seal.
Invalid
Re- issue
Valid
Stopped
Extend
Correct answer
Stopped
Invalid
Re- issue
Valid
Stopped
Extend
Correct answer
Stopped
It is the responsibility of initiating agency to define work and ensure fulfillment of 0/1
all safety checks of work permit before handing it over.
True
False
Correct answer
True
Monthly Basis
Quarterly Basis
Annual Basis
Who will double checks, signs the permit & retains the hard copy. 1/1
Area Operator
True
False
Correct answer
False
Electrical
Cold
Hot
None
Red Tag
Scaffolding OK
Toe Boards
None
For offsite facilities Work permit is valid for 1/1
8 Hours
12 hrs.
One Day
None
Life Line
SCABA
None
If there is a risk of Suffocation then what PPE must be used in confined space 1/1
Breathing Appratus
Dust Mask
Face Shield
Which type of work permit is required for Transmitter Calibration. 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for Scaffolding Erection / Removal 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for Sandblasting 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for Opening & assembling of Piping 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for Removal of Valve Bonnet 0/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Correct answer
Cold
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for Entry inside a vessel 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Which type of work permit is required for working on electrical circuit 1/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Permit required for Flight Pump Operation in Trench 0/1
Cold
Hot
Electrical
Civil
Instrument
Confined
Correct answer
Hot
Offsite
Battery Limit
Offsite
Battery Limit
Correct answer
Battery Limit
11 KV line to APL is classified as 1/1
Offsite
Battery Limit
Offsite
Battery Limit
Trench & Lines containing Air Conditioning Circuits are responsibility of 1/1
Utilities.
True
False
Offsite
Battery Limits
Urea Bulk Storage is classified as 0/1
Offsite
Battery Limits
Correct answer
Battery Limits
Offsite
Battery Limits
Correct answer
Battery Limits
Control Room
Displayed in Area
Fire Water Network in Production units is the responsibility of 1/1
Respective Area
Safety
Security
Admin
Rest of Fire Water Network except in Production units is the responsibility of 1/1
Respective Area
Safety
Security
Admin
Rest of Fire Water Network except in Production units is the responsibility of 1/1
Respective Area
Safety
Security
Admin
Evaporation Ponds are classified as 1/1
Offsite
Battery Limits
Offsite
Battery Limits
Offsite
Battery Limits
HVAC system and window type ACs electrical job is classified as 1/1
Categoty A
Category B
Communication and fire alarm system electrical job is classified as 1/1
Categoty A
Category B
Categoty A
Category B
Medium voltage generators (Auxiliaries not included) electrical Job is classified as 1/1
Categoty A
Category B
Medium and low voltage bus bar in substation electrical Job is classified as 1/1
Categoty A
Category B
In Scaffolding All ties provided. Distance between two ties is 6ft. Lowest tie 1/1
point is 6" above ground
True
False
All planks are extended 9 ft - 10 10 ft (Minimum) outside the ties of Scaffolding. 1/1
True
False
Scaffolding of height to width ratio higher than 4:1 is secured with other fixed 0/1
structures
True
False
Correct answer
False
Scaffolding of height to width ratio higher than 4:1 is secured with other fixed 0/1
structures
True
False
Correct answer
False
True
False
Correct answer
False
Allowable load on scaffolding platform is two persons plus 50 kg weight (for tools 1/1
etc.) per square meter.
True
False
Maximum free span of wooden plank is 4 feet in Scaffolding. 1/1
True
False
Toe boards are provided where scaffolding platform height is more than 8 ft from 1/1
ground
True
False
Hot Work permit will be required for use of camera within plant battery limits. 1/1
True
False
This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy
Forms