Highway Constitution Act
Highway Constitution Act
Highway Constitution Act
The present project consists of the improvement of the highway to the Florida - Hungará
town center for a length of 00+770.41 km. With which the socio-economic conditions
and the integration of rural spaces into a regional context would be improved, prioritizing
their organization and articulation based on their temporary needs for the extraction and
exploitation of natural resources, located in the district of Nuevo Imperial-Cañete -Lime.
For the proper functioning of the vehicular flow, the proposed section will need to be
constructed by widening curves and correcting maximum slopes to comply with the
provisions of the geometric design manual.
To achieve the main product, physical delivery of the “Florida-Hungará Highway”, the
following deliverables will be presented by the company N&M CONSULTING SAC:
First, the delivery of the Geometric Design of the highway will be carried out, with this
documentation they will begin and Improvement permits and authorizations will be
obtained. Having these documentations, the selection of the construction company will
be carried out through a competition, once this is completed, the improvement of the
road will begin, and its supervision will be carried out by N&M CONSULTING SAC and
finally with the approval of the improvement it will be carried out. the physical delivery of
the road.
2. PROJECT ALIGNMENT
STRATEGIC OBJECTIVES OF THE
PURPOSE OF THE PROJECT
ORGANIZATION
“Improvement of the Highway that connects the Integration of productive areas remote from
La Florida and Hungara population centers, with national trade.
an approximate extension of 770.41 m”
“The preparation of technical files at the tender Improve the passability conditions of the road
level for the execution of construction works in that will be developed through areas with
accordance with the Terms of Reference and better geological and topographic conditions.
other contractual documents.”
“The execution of this project is Recognition of the company at a national and
Page1 of 7
"aligned with the company's strategic plan that international level.
seeks to expand the sector, construct and improve
roads."
Page2 of 7
3. PROJECT OBJECTIVES
Scope:
Compliance with each of the phases established for the project.
Time:
The term for the execution of the project has been estimated at 01 month equivalent
to 30 calendar days.
Start date: 06/14/2018
End date: 07/14/2018
Cost:
Management of the design and improvement of the “La Florida-Hungará” Highway ",
with an estimated cost of S/. 99,481.30 Soles incl. VAT.
Quality:
Compliance with quality standards applicable to the type of project.
Page3 of 7
5. HIGH LEVEL REQUIREMENTS
Criterion of
Interested Requirements
acceptance
Physical Delivery of the Hotel within 21 months.
Owner The Normal
Physical delivery of the Hotel must not exceed
the amount of S/ 14,028,248.32.
Obtain Design Drawings in maximum time
Architect Normal
of 30 days.
Physical Delivery of the Hotel within 21 months.
The Physical delivery of the Hotel must not
General manager Normal
exceed the amount of S/ 14,028,248.32.Avoid
paying a penalty of
1% for each day of breach of contract.
Comply with work plans according to the
Project application and functionality in the project. The
Normal
manager communications plan should be clear and
simple, easy to
understanding for all personnel involved.
Head of Obtain the Design in a maximum time of 30 Normal
Engineering days.
On-site Quality Control will be carried out daily.
Head of
Physical Delivery of the Hotel within the period Normal
Supervisio
of
n
23 months.
Page5 of 7
7. KEY STAKEHOLDERS
Page6 of 7
9. MAIN MILESTONES OF THE PROJECT
Date
EDT Main Milestones Final date Approved
Start
No.
1.1.1 Beginning of Project Management 14/11/2016 28/11/2016 Project manager
1.1.2 Planning 29/11/2016 02/01/2017 Project manager
1.1.3 Execution 14/11/2016 13/08/2018 Project manager
1.1.4 Monitoring and Control 14/11/2016 13/08/2018 Project manager
1.1.5 Closing 13/08/2018 22/10/2018 Project manager
1.2.1.1 Preliminary studies 14/11/2016 21/11/2016 Project manager
1.2.1.3 Architecture 17/11/2016 23/11/2016 Project manager
1.2.1.2 Structures 22/11/2016 02/12/2016 Project manager
1.2.1.4 Electrical installations 24/11/2016 28/11/2016 Project manager
1.2.1.5 Sanitation 24/11/2016 28/11/2016 Project manager
1.2.1.6 Budget 03/12/2016 08/12/2016 Project manager
1.2.1.7 Works Programming 09/12/2016 17/12/2016 Project manager
Beginning of Procedures to Obtain
1.3.1 Supplies of Water Services, 19/12/2016 02/02/2017 Project manager
Drainage and Electricity
1.3.2 Building permit 24/12/2016 25/02/2017 Project manager
Preparation of Bases for the
1.4.1 27/02/2017 09/03/2017 Project manager
construction competition
Page7 of 7
10. PROJECT BUDGET
11. RESTRICTIONS
RESTRICTION TAXED BY
The project must be completed before 10/13/2018, because the General manager
hotel must come into operation.
The maximum budget available is S/. 14'028,248.32 without General manager
include VAT.
There will be no extension of deadlines. Sponsor
Penalties that the client imposes according to the contract. Sponsor
12. ASSUMPTIONS
SUPPOSED UNCERTAINTY
Disbursement of money according to Purchases of new equipment to improve
schedule, quality and meet scope.
by the company and the client.
Inadequate quality control causes problems The user of each department does not
of quality that affect to provide correct validation of the project.
the
planning are known late.
The appearance of a new norm, or law that Therefore, the scope of the project must be
changes the rules of business. reconsidered and request approval for a
change of
scope
Preliminary draft delivered by Possible critical points will have to be
he correctly reviewed and analyzed to avoid problems
prepared client. with the
project times and costs.
Secured financing from the client. The start of the project may be delayed.
The effective flow to the The project is expected to be completed in
project. time
My dear.
Legal cleanup of the lot, clean property titles. The start of construction and contractor
selection may be slowed.
Page8 of 7
Work hours during construction will be an 8- To deliver the project on time, human
hour shift. resources have been calculated based
on 8 hours a day.
Page9 of 7
13. PROJECT APPROVAL REQUIREMENTS
Success criteria Evaluator Sign the closure of the
project
The project must be delivered within the General Manager
deadline of
19 months. Custer Corporation
General Manager of
The project cost should not exceed 2%
Custer Corporation.
The project must be developed within the General Manager of
quality, safety and occupational health Custer Corporation
standards contemplated in the current
regulations of the Ministry of
Job.
Comply with approved deliverables and General Manager
100% agreed of
Custer Corporation
Formal approval of project completion will
be approved by the Project Sponsor and
client Custer Corporation
SAC
The approval criterion that will be used
will be the hotel's Certificate of
Conformity, review and approvals of the
specialists of the different areas
(disciplines) that
base the project.
SIGNATURE: SIGNATURE:
Page10 of 7