PROJECT TITLE: CONCRETING OF ESPIRITU ROAD AT PUROK 6, BARANGAY BALDIOS

LOCATION: BARANGAY BALDIOS , SANTA. IGNACIA, TARLAC DATE:

WEATHER: AM:

PM:

MANPOWER: EQUIPMENT:
- Project Engineer - One Bagger - Jack Hammer
- Foreman - Elf Truck -
- Skilled Worker - Backhoe -
- Laborer - Water Truck -
- Safety Officer - Dumptruck -
- First Aider - Concrete Cutter -
- Operator - Bar Cutter
- - Tamping Machine
- - Cut Off Machine
- - Welding Machine

ACTIVITIES
VISITORS:

PREPARED BY: NOTED BY:

Arc. Albert Solas


Site Engineer Contractors Project Architect
PROJECT TITLE: CONSTRUCTION OF ONE (1) STOREY ONE(1) CLASSROOM BUILDING PROJECT TITLE: CONSTRUCTION OF ONE(1) STOREY ONE(1) CLASSROOM BUILDING
LOCATION: PADA-PADA NATIONAL HIGH SCHOOL DATE: LOCATION: PADA-PADA NATIONAL HIGH SCHOOL DATE:
WEATHER: AM: WEATHER: AM:
PM: PM:

MANPOWER: EQUIPMENT: MANPOWER: EQUIPMENT:


- Project Engineer - One Bagger - Jack Hammer - Project Engineer - One Bagger - Jack Hammer
- Foreman - Elf Truck - - Foreman - Elf Truck -
- Skilled Worker - Backhoe - - Skilled Worker - Backhoe -
- Laborer - Water Truck - - Laborer - Water Truck -
- Safety Officer - Dumptruck - - Safety Officer - Dumptruck -
- First Aider - Concrete Cutter - - First Aider - Concrete Cutter -
- Operator - Bar Cutter - Operator - Bar Cutter
- - Tamping Machine - - Tamping Machine
- - Cut Off Machine - - Cut Off Machine
- - Welding Machine - - Welding Machine
ACTIVITIES ACTIVITIES

VISITORS: VISITORS:

PREPARED BY: NOTED BY: PREPARED BY: NOTED BY:

Engr. Michael Jofred P. Doria Albert Solas Engr. Michael Jofred P. Doria Albert Solas
Site Engineer Contractors Project Engineer Site Engineer Contractors Project Engineer
PROJECT TITLE: Construction of New Mayor's Office and Executive Hall

LOCATION: Municipal Compound, Sta. Ignacia, Tarlac DATE:

WEATHER: AM:

PM:

MANPOWER: EQUIPMENT:
- Project Engineer - One Bagger - Jack Hammer
- Foreman - Elf Truck - Cut Off Machine
- Skilled Worker - Backhoe - Welding Machine
- Laborer - Water Truck -
- Safety Officer - Dumptruck -
- First Aider - Concrete Cutter -
- Operator - Bar Cutter
- - Tamping Machine

ACTIVITIES

VISITORS:

PREPARED BY:

SITE ENGINEER

PROJECT TITLE: CONSTRUCTION OF MULTI-PURPOSE HALL(PHASE 1)


LOCATION: MANAQUEM, CAMILING, TARLAC DATE:

WEATHER: AM:

PM:

MANPOWER: EQUIPMENT:
- Project Engineer - One Bagger - Jack Hammer
- Foreman - Elf Truck - Cut Off Machine
- Skilled Worker - Backhoe - Welding Machine
- Laborer - Water Truck -
- Safety Officer - Dumptruck -
- First Aider - Concrete Cutter -
- Operator - Bar Cutter
- - Tamping Machine

ACTIVITIES

VISITORS:

PREPARED BY:

MARIA AGNES D. JULIAN

Project Manager
FABRICATION AND
INSTALLATION OF 300
UNITS SOLAR STREET
LIGHTS WITH POST
Along Romulo Highway, Santa Ignacia, Tarlac

LOG BOOK
CONSTRUCTION AND
IMPROVEMENT OF
DRAINAGE SYSTEM ALONG
OLD SLAUGHTERHOUSE
ROAD AND ROAD #12,BRGY.
POB WEST
Old Slaughterhouse Road and Road #12, Brgy. Pob. West,
Santa Ignacia, Tarlac

LOG BOOK