Professional Documents
Culture Documents
Activities Train
Activities Train
1. AIM
Find the optimal number of sectors and define them in the plane.
Define the Activity Train and fill it in the Lookahead.
Indicate the amount of concrete to be poured per day.
2. JOB MATERIAL
The work to be carried out is the construction of the shell of an 8-story building.
The scope of the work will be to carry out only the formwork and casting of all
the columns, plates, beams, lightened slabs and solid slabs . The steel items and
installations will be developed by subcontractors who will not influence the
progress of the hull (performance has already been considered with the
interaction of these activities).
*The perimeter wall is not part of the scope of the project.
7. All beams are 0.25mx 0.50m. The length of the beams in direction XX is
4.75m and in YY is 6.00m and 2.78m.
0.50
0.25
Peruvian Chapter of LEAN CONSTRUCTION INTITUTE
8. The entire plane is symmetrical in XX and YY and there will be only 3 sizes
of panels (2 lightened and 1 solid).
4. TASKS TO BE DONE
The optimal feasible number of sectors must be determined to carry out the work
in the shortest possible time according to the project considerations.
Graph and list the sectors in the typical plant of the project (in the case of
formwork and concrete pouring).
Indicate the amount of formwork and concrete metering for slabs, beams and
verticals (columns and plates) for each of the sectors.
Indicate the number of people that will be required in each item (vertical
formwork, beam formwork, slab formwork, horizontal concrete and vertical
concrete).
Fill out the Lookahead form with the Work Train.
Indicate the number of days it will take to complete the project and enter the total
amount of concrete to be poured each day.
PRODUCTIVITY
PROD
DEPARTURE UND
.
hh/
Vertical Formwork and Stripping (Columns and Plates) 1.53
m2
hh/
Emptying of Verticals (Columns and Plates) 0.72
m3
hh/
Beam Formwork and Stripping 2.48
m2
Formwork and Stripping of Slabs hh/
0.87
(Solid and Lightened) m2
hh/
Horizontal Emptying (Slabs and Beams) 0.96
m3
AREA ( m2 )
Slab 1 31.19
Peruvian Chapter of LEAN CONSTRUCTION INTITUTE
Slab 2 15.00
Slab 3 (solid) 64.06
METERS
Concrete 0.13 m3/m Beam length is multiplied by the
Beams
Formwork 0.85 m2/m given factors
Concrete 0.20 m3/m2 Slab area is multiplied by the
Solid Slabs
Formwork 1.00 m2/m2 given factors
Concrete 0.08 m3/m2 Slab area is multiplied by the
Lightened Slabs
Formwork 1.00 m2/m2 given factors
Concrete 0.32 m3
C1
Formwork 3.92 m2
Concrete 0.63 m3
C2
Columns and Formwork 5.32 m2
Final metering
Plates Concrete 1.05 m3
C3
Formwork 7.00 m2
Concrete 5.58 m3
P1
Formwork 42.14 m2
Exhibitors: