Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

J Civil Struct Health Monit

DOI 10.1007/s13349-017-0251-6

ORIGINAL PAPER

Existing metallic bridges in Egypt: current conditions


and problems
Maha M. Hassan1 • Sherif A. Elsawaf2 • Hussein H. Abbas2

Received: 21 June 2017 / Accepted: 7 October 2017


 Springer-Verlag GmbH Germany 2017

Abstract Several metallic bridges are present in Egypt and addition to reinforced concrete substructures. The study is
form an important part of the transportation network. Many meant to shed light upon the current conditions of vital
of these bridges exceeded the intended design life. Cur- structures and explore the available practical repair
rently, deterioration of bridge conditions is pronounced and techniques.
is leading to many problems. In addition, it is feared that
lack of corrective procedures may lead to failure within a Keywords Assessment  Bridges  Damage  Egypt 
few years. Periodic maintenance and major repair activities Inspection  Metal
during a structure service life are mandatory to sustain a
satisfactory performance that preserves public safety and
extends the service life. The current work is carried out to 1 Introduction
summarize the most frequent structural problems and
defects faced during inspection campaign of a group of One of the oldest railway networks across the world exists
metallic bridges in Egypt. Reported problems include but in Egypt. Large number of bridges was built during the
are not limited to corrosion, fatigue cracks, and permanent nineteenth and twentieth centuries. In addition, several
deformations in structural elements. Data are collected metallic bridges exist as part of the roadway network that
through an extensive investigation of several metallic has been built during the last two centuries. Hence, a
bridges in Egypt. The study included visual inspection, considerable number of bridges have been in service for
structural analysis under the action of loads imposed by more than 100 years. During their service life, steel bridges
latest design codes, fatigue assessment of different bridge are exposed to environmental changes, increased loads,
components, and field tests. Observations include problems corrosion, and poor maintenance applications which results
or defects related to steel superstructure, pedestrian side in overall deterioration and inability to achieve satisfactory
walkways, sleepers and rails system, bracing systems, in performance. Accordingly, structural assessment combined
with application of required remedies is a pressing issue in
order to avoid local or global failure. Existing bridges in
& Maha M. Hassan Egypt serve both railway and roadway traffic over the
mahamoddather@eng.cu.edu.eg entire country. They include a large variety of lengths,
Sherif A. Elsawaf load-carrying capacity, structural systems, geometric
sherif.elsawaf@ehafconsulting.org dimensions, and materials. The current work focuses on
Hussein H. Abbas metallic railway and roadway bridges. It is part of the
habbas@ehafconsulting.org performed effort to analyze current bridge conditions and
1 build a suitable database of the status of in-service bridges.
Department of Structural Engineering, Cairo University,
Gamaa Street, Orman, P.O. Box 268, Giza, Egypt Inspection and monitoring of existing bridges have been
2 investigated by several researchers. Hai [1] and Hai et al.
Department of Structural Engineering, Al Azhar University, 1
Al Mokhaym Al Daem, Gameat Al Azhar, Nasr City, Cairo, [2] explored the status of the railway bridges in Vietnam
Egypt and listed the main deficiencies. The most critical observed

123
J Civil Struct Health Monit

deficiencies were corrosion and deterioration due to aging. main defects and problems found during the inspection
Spyrakos et al. [3] and Ermopoulos and Spyrakos [4] campaign of 76 railway steel bridges in addition to several
performed complete assessment of a nineteenth century roadway bridges in Cairo governorate which is the capital
railway bridge and suggested possible repair procedures. of Egypt. Findings of visual inspection of different bridge
Bancila et al. [5] presented the Romanian methodology in components are exhibited. In addition, investigation of the
assessment of failure and malfunction in steel bridges frequent structural problems and defects is listed. The study
accompanied with some case studies. Zhou [6] estimated targets rating the current condition of bridges in Egypt in
the remaining fatigue life of existing bridges based on order to preserve the current bridge inventory.
field-measured stress range histograms under actual traffic
loads for three major highway bridges. Accordingly, a
procedure was proposed for evaluating fatigue life of 2 Description of bridges
existing bridges. Frangopol et al. [7] studied the bridge
reliability including the monitored data in structural The current study focuses on several metallic railway and
assessment and prediction models of bridges. Morales and roadway bridges located in Egypt. Data regarding the dif-
Bauer [8] reviewed the accumulated fatigue and remaining ferent considered bridges were collected through checking
life of highway bridges with service life time over 50 years of the available as-built drawings, calculations, and
in Canada. Oliveira and Camacho [9] collected a large inspection reports. Many of the considered bridges have
database for in situ vibration frequencies of bridges in been subject to repair works and in some cases major
Portugal. The study was part of the efforts for using con- rehabilitation. Figure 1a–p shows general view of sample
tinuous vibration monitoring of bridges in damage detec- bridges investigated in the current study. Tables 1 and 2 list
tion [10]. Hassan and Abbas [11] exhibited results of field the inspected railway and roadway bridges. Railway
vibration measurements for major steel railway bridges in bridges are grouped based on the location and working
Egypt. line; meanwhile, roadway bridges are grouped based on the
Generally, structural failure of a bridge can be defined as structural type: group 1 incorporate riveted sections and
the condition when sudden collapse occurs or when signs group 2 incorporate welded sections. Generally, the studied
of local defects prevent the bridge from fulfilling its pur- bridges include: truss and plate girders, simple and con-
pose. The local defects include corrosion, deterioration, tinuous systems, and fixed and movable bays, riveted and
cracks, excessive vibration or deformation, in addition to welded sections. Figure 2a shows age distribution of
various aging signs. Causes of bridge failure can be cate- inspected bridges. A percentage of 42.1% of the considered
gorized as design deficiencies, corrosion, construction and bridges have been in service for more than 100 years.
supervision mistakes, accidental overload and impact, Figure 2b shows distribution of different spans. Most of
scour, lack of maintenance or inspection, and force majeure inspected bridges fall in the span length between 10 and
[12, 13]. In order to preserve the existing bridges at a 20 m. Figure 2c summarizes the used structural systems.
functional level, rehabilitation and repair methodologies Simple beams are the most observed system which presents
have to be applied. Ghosh and Ghoshal [14] discussed the the most suitable system for the majority of bridges based
possible rehabilitation procedures through assessment of on span lengths. Figure 3a–c shows sample elevation of
three case studies from Bangladesh, Malaysia and India. selected bridges showing the employed structural system.
The authors focused on the efficiency of innovative repair The inspected roadway bridges included four main
schemes for extending the service life of existing steel bridges as listed in Table 2. Kasr El Nil Bridge is a road-
bridges and improving their durability and serviceability way bridge constructed in 1933. It connects Tahrir Square
with minimum cost and time. Caglayan et al. [15] inves- in downtown Cairo to modern Cairo Opera complex toward
tigated the capability of old railway bridges to accommo- the southern end of Gezira Island. The total length of the
date heavier axle loads through a series of dynamic tests, bridge is 1932 m. The bridge consists of a number of bays
acceleration measurements, and finite element simulations. serving two traffic lanes in each direction. The construction
Abbas and Hassan [16] investigated the influence of system of the bridge is four continuous steel girders with
applied repair methodologies for a case study railway variable depth as shown in Fig. 1m. Two bays of the bridge
bridge in Egypt. are movable bridge. El Sanaie bridge is located on a road
The current study is part of an extensive assessment connecting the road of Faraj and Sebtia areas. The length of
practice for a group of steel bridges constituting part of the the bridge is about 497 m. Inspection showed that the
railway and roadway network in Egypt. The study con- width of the bridge is about 13.00 m divided into three
sisted of different phases including visual inspection, lanes, in addition to a side walkway of about 1.45 m in
modeling, static and dynamic load tests, material tests, and both directions. The construction system of the bridge is
repair recommendations. In this paper, focus is given to the three continuous steel girders over six bays with a length of

123
J Civil Struct Health Monit

Fig. 1 General view of sample bridges

123
J Civil Struct Health Monit

Fig. 1 continued

Table 1 Summary of inspected railway bridges


Group Inspected bridges

Group 1 Khott Bridge—Masraf Basandella (1)—Masraf Basandella (2)—Masraf Ammar (2)—Bahr Belqas—Masraf El Emmom (4)—
Ebshan—Bahr El Adma—El Malah—Abou Sha’asha’—Zawya—Tabarya—Masraf El Emmom (7)
Group 2 Sabal El Ganouby—Sabal El Shamaly—Nenaia—Sersaweya Canal—Shaab Shenwaan—Tanata Canal—El Malah—El
Rahebein—Berket El Sabe—Abou El Akhdar El Asloogy—Menouf—Masraf Tta—Masraf Sabal bel Eraqia—Meshla—Terat El
Kased
Group 3 Moheet El Khatatba—Kellin—Sahel Morkos—El Khandaq El Sharqy (Dmanhour)—El Shamasma—Masraf (10)—Masraf (11)—
Saeedi Mahalet Malek—Delta Meet Bara—Meadya—El Khandaq El Sharqy (Tawfekya)
Group 4-A Sawahelya—Diroot—Ibrahimya Assiut—Malah Assiut—Old and New Abou Shosha—Kasel Kom Ombo
Group 4-B Kantara Qebly—Raswa
Group 5 Harrery Tunnel—Delta Tunnel—Ganabeya El Qorasheya—Teraat El Kased—Kafr Saqr—El Nezaam—Juhayna
Group 6 Abo El Nomros—El Ayyat—Maktafia—Elwy El Demeerdash—Elwy EL Waziz—Teraat El Khaleeg El Masry—El Ibrahimya—
Abd Allah Wahby
Group 7 Imbaba—Banha—Dessouk and Rahmania—Edfina—Kafr El Zayat—Kanater—Mansoura—Marazek—Zefta—Old and New
Gerga—Noubarya—Shola Tunnel

123
J Civil Struct Health Monit

Table 2 Summary of inspected roadway bridges rest on transversal frames consisting of girder with double
Group Inspected bridges
cantilevers and two braced columns in the longitudinal
direction. The longitudinal beams are topped by a floor
Group 1 Kasr El Nil Bridge—Galaa—Sanaei consisting of a slab and a concrete slab. There is a metal
Group 2 Mohamed Naguib fence on either side of the bridge; however, there are no
sidewalks. Galaa Bridge was built in 1914 with a total
length of 145 and 19 m width. The bridge supporting
system is composed of two riveted trusses connected by
about 8.0 m each, in addition to four metal frames with
cross girders. The bridge has two fixed bays and two
span 18.5 m and two cantilever beams of length 8.5 m in
movable bays (swing type).
both directions. The road is a concrete slab loaded with
metal slabs based on secondary longitudinal beams, about
1.25 m long and secondary cross-beams, about 2.0 m
3 Assessment and inspection campaign
away. Mohamed Nagube bridge consists of two traffic
lanes. It transfers the traffic from the direction of ELMarge
The inspection campaign included the study of 76 steel
El Gadida as well as branching across the subway to the
bridges within the railway network in Egypt in addition to
direction of Mohamed Naguib Street. The bridge consists
several roadway bridges at Cairo province. The current
of a number of metal bays, starting and ending with con-
study focuses on the encountered problems and defects at
crete bays. Each of the three main girders is located in the
different members of bridge. The study was performed
longitudinal direction of the bridge, connecting them with
starting at the end of 2014 and till the end of 2017. Age of
secondary cross-girder in the main direction. Main girders
the inspected bridges ranges between 27 and 119 years at

25-50 11 0-10
6 0 10-20
50-75 8 11 20-30
75-100 5 30-40
14 2
32 100-125 40-50
50-60
10 60-70
70-80
80-90
44
24

(a) Distribution of Age of Bridges (b) Distribution of Span Length

1
Simple Beam
2
14 Continuous Beam
Simple and Continuous Beams
3 Simple Truss
43 Continuous Truss
13
Simple Arch with Ties

(c) Used Structural System


Fig. 2 Inspected railway bridges

123
J Civil Struct Health Monit

Fig. 3 Sample structural system of inspected bridges

the beginning of inspection campaign. It should be men- ladders were employed to access far zones of the bridge in
tioned that the last detailed inspection of most of these order to ensure investigation of all areas. The inspection
bridges was performed in 1985. In addition, Egyptian intensity depended upon the importance and criticality of
National Railways (ENR) performs periodic visual the structural element. Each steel member was viewed from
inspection of these bridges on a regular basis. Generally, all sides along its length. Dimensions of structural elements
each bridge has a person in charge who inspects different were measured and compared to the original as-built
bridge components and reports any defects to higher drawings in order to record any section losses. Increased
authorities. attention was given to the tension zones of fracture critical
Visual inspection phase presents a very important part of members. Similarly, compression members were checked
the assessment study. The different elements of the for buckling or deformations. Sections and connections
inspected bridge were extensively investigated to pinpoint were inspected for loose or missing rivets or bolts. Steel
defects for further investigation. Inspection focuses on bearings were checked for cracks or surface corrosion.
critical positions such as steel sections and connections, Substructure elements representing piers, side walkways, or
concrete slabs, piers, abutments, drainage system, lighting, roadway lanes were inspected for spalling, cracks, scaling,
and handrail guards. The visual inspection was performed reinforcement corrosion, or material deterioration. The
by means of several teams at the same time. At the begin- common observed defects include corrosion, fatigue cracks,
ning of the inspection phase, the existing structural draw- aging, missing rivets, poor condition of concrete, in addi-
ings and previous inspection reports (if available) were tion to inadequate lighting or drainage facilities. Moreover,
studied. Accordingly, the structural system of the bridge is some bridges suffer from problems related to vehicle col-
fully understood and any reported repair procedures are lision, or poor maintenance applications. In the following
recorded. Previously prepared inspection forms and sections, the frequently observed defects are listed and
checklists are employed to perform a close-up visual discussed for the different bridge components. Moreover,
examination of the different components [17]. Boats and practical repair procedures will be explored.

123
J Civil Struct Health Monit

3.1 Steel superstructure: corrosion


Start
Corrosion and loss of protective coating are one of the most
observed defects in metallic structures. Bridges are usually
Check the available as-built drawings, calculations, previous
inspection reports…etc. exposed structures which are subjected to large tempera-
ture changes in addition to humidity. The above reasons
Perform visual inspection of the different bridge components combined with lack of maintenance and repair procedures
and pinpoint the defects. lead to corrosion. Lee [18] proposed a method for recog-
nizing bridge coating rust using color image processing as
Determine the material properties of the metallic and concrete an accurate, efficient, and fast method. The method was
components through material tests. developed by Shen et al. [19] by proposing a rust defect
recognition method based on colour and texture features of
Construct preliminary finite element models using the available coating.
as-built drawings.
For the group of inspected bridges, the severity of
corrosion ranged from surface light corrosion to serious
Perform static load tests and dynamic properties tests in order to
specify the bridge response under the applied loads. corrosion leading to decreasing the sectional area
(Fig. 5a–c). Corrosion is caused by an electro-chemical
Update finite element models using the static and dynamic test process that leads to the oxidation of iron. It is commonly
results. observed at the bottom levels of metallic bridges (floor
elements) subjected to water vapor arising from waterways
Check different members and connections using straining beneath the bridge. For some bridges, severe corrosion
actions from models under the effect of new loads. was observed leading to pitting or creating holes through
the steel plates (Fig. 5a–d). In other bridges, corrosion was
Determine the remaining fatigue life of fatigue-critical not serious and only observed throughout the protective
members based on axle load and occurrence data received from
coating layer (Fig. 5e). In some cases, corrosion was
observed at bottom of columns after removing poured
Specify the type and extent of defects based on the previous
steps. protective reinforced concrete pedestals (Fig. 5f). For the
inspected bridges, dimensions of sections were measured
Study available repair alternatives and prepare drawings and upon removing the rust area. It was found that in most
bill of quantities. cases the thickness of section elements decreased by about
1–2 mm. Based on the structural analysis study, it was
End decided that sections do not need strengthening. However,
in some special cases, the area of the section decreased
Fig. 4 Bridge assessment procedure greatly and steel plates were added to compensate for the
lost area as shown in Fig. 3h in Saida Eisha bridge. Fig-
The main observed defects for the inspected bridges ure 6 shows the distribution of corrosion severity for the
were surface to severe corrosion, permanent deformations inspected bridges. Classification is based on a subjective
in members, missing rivets, cracks, improper repair appli- criteria set by inspectors during visual inspection. Guide-
cations, loss of connecting rivets, spalling, cracks, scaling, lines, stipulated in Japan Bridge Association report [20],
reinforcement corrosion, material deterioration, poor con- classify corrosion based on type, thickness and color tone.
dition of concrete, in addition to inadequate lighting or Most of the inspected bridges were characterized by good
drainage facilities. to fair section condition with light rust at localized zones.
Observations from the visual inspection phase were Meanwhile, 17.8% of the inspected bridges were having
recorded and used to determine the suitable repair proce- severe to bad section conditions. The age of these bridges
dures. Consequently, FE models were developed based on ranged between 50 to 119 years with 62% exceeding
the as-built drawings and the visual inspection observa- 100 years. It was also observed that for this category
tions. Static and dynamic tests were performed to validate bridges are located on the Nile River with severe envi-
the built models. Hence, models are used to analyze the ronmental conditions.
bridge performance under the increased axle loads. In Repair procedure includes determining the extent of
addition, fatigue assessment study was performed consid- corrosion. If severe corrosion is observed, member could
ering the records provided by Egyptian National Railways be replaced or strengthened with additional plates to sub-
(ENR). A flow chart summarizing the principle steps for stitute the missing steel area. For the case of light corro-
the assessment procedure is shown in Fig. 4. sion, the corroded layer needs to be removed. Afterwards,

123
J Civil Struct Health Monit

Fig. 5 Corrosion signs at different inspected bridges

123
J Civil Struct Health Monit

1.4% bridges. Most of the inspected bridges were constructed at


Severe to Bad a time when data concerning fatigue were not available.
8.2% Hence, the used details did not account for such effects. In
16.4% Bad to Fair addition, overload or collisions could lead to fatigue
damage [1]. Fatigue defects are critical and need immedi-
Fair to Good
ate repair as it may lead to immediate failure of the affected
element. The different investigated bridges were assessed
Good
considering records for axle loads and the remaining life
time was determined accordingly. After analyzing the floor
beams shown in Fig. 7a, b, it was found that stresses due to
74.0% standard train loads specified by the Egyptian Code [22]
exceed fatigue limit requirements for slotted detail cate-
gory. Hence, strengthening applications were recom-
mended including repair of existing cracks in addition to
Fig. 6 Distribution of corrosion severity for different inspected increasing the strength of floor beams through addition of
bridges
steel plates. For the inspected bridges, the remaining fati-
gue life for different members was estimated using the
epoxy fillers and appropriate painting systems are applied.
traditional S–N method [23]. However, this method might
Generally, actions should be taken to avoid circumstances
underestimate the actual remaining fatigue life of bridge
leading to corrosion. This includes ensuring the availability
[6]. Field measurements present an accurate alternative in
of a proper drainage system and periodic maintenance
estimating fatigue remaining life in addition to many
procedures.
innovative measurement methodologies [24–26]. Fatigue
cracks may not appear due to corrosion; hence, it is rec-
3.2 Steel superstructure: fatigue cracks
ommended to investigate the fatigue-critical members upon
removing rust by sand blasting.
Different structural elements in metallic bridges are sub-
jected to stress cycles due to varying applied loads.
3.3 Steel superstructure: connecting elements
Depending on the number of applied cycles and connection
(rivets and bolts)
details, fatigue cracks might initiate at fatigue-prone
members and connections [21]. Accordingly, for the
The common method of construction for most of the
inspected bridges, fatigue cracks were investigated at the
inspected bridges was the use of rivets in connecting dif-
fatigue-critical members, near weld lines, and around rivet
ferent parts. During the inspection campaign, it was
heads. Cracks were observed at the slotted stringer-to-cross
observed that the rivets were missing at some connections
girder joint (Fig. 7a, b) in two different bridges. These two
(Fig. 8a–d). Generally, such missing rivets are replaced by
bridges were the only ones employing the slotted connec-
high strength bolts. However, replacement bolts were also
tion detail. In addition, they were built using welded sec-
reported to be damaged at many locations (Fig. 8a, b). For
tions. Both bridges have been in service for less than
the different inspected bridges, it was found that less than
30 years; however, high stress values under applied live
5% had missing rivets for about 20% of the inspected
loads were observed in the cracked cross girder of both
connections. In addition, most of these bridges exceeded

Fig. 7 Fatigue cracks in different inspected bridges

123
J Civil Struct Health Monit

Fig. 8 Connecting element condition at sample bridges

100 years in service. Generally, connections were thor- 3.4 Steel superstructure: bearings
oughly investigated considering their location and the
affecting straining actions. It was generally observed that Bridge bearings convey forces due to different loading
the defects are common in the connections of the lower effects between the steel superstructure and the sub-
bracing system connections. This can be attributed for the structure. They also accommodate the expected move-
assumptions and simplifications made during the design ment in the bridge due to temperature changes, train
phase at the time of bridge construction. Bracing members loads, or lateral loads. Railway bridges are characterized
were only designed to support loads caused only by wind by expected heavy forces at the supports. Hence, all the
effects. Meanwhile, these members are affected by the studied bridges employ mechanical steel bearings except
passage of trains as the whole bridge transmits the applied for New Gerga bridge and Abo Shosha Bridge which
loads through interaction between their members. This was employed elastomeric pot bearings. Meanwhile, the
observed during load testing of the different studied inspected roadway bridges employed elastomeric bear-
bridges as measured strain values exceeded the calculated ings or simple steel bearing plates. During visual
values considering simplified 2-D models. This was also inspection, the common defects of the bridge bearings
confirmed upon building 3-D finite element models. Repair included light or heavy corrosion, misalignment, sheared
procedures include mainly replacement of rivets with high bolts, and loss of restraining blocks, and cracking of
strength bolts and in some cases increasing the number of concrete pad (Fig. 9a–d). Repair practices include refur-
bolts by introducing new holes or changing gusset plates. bishment, lubrication, replacement of damaged parts,
In some cases, strengthening of bracing members was jacking, and levelling. Generally, bearing conditions were
needed due to observed yielding, especially at gusset plate fair for all inspected bridges except for the defects shown
zone. in figures.

123
J Civil Struct Health Monit

Fig. 9 Defects in bearings at sample bridges

3.5 Steel superstructure: collision and impact bracing members. Such application may cause the forma-
tion of fatigue cracks at the welded floor beams.
Several bridges were damaged due to collision of trains or In 2016, replacement of wearing surface of Kasr El Nil
elements on board. Figure 10a shows a replaced vertical Roadway Bridge was performed. Bridge expansion joints
member in Marazek Bridge after a derailment accident in were closed as continuous asphaltic layer was laid above
2002. Train wagons crashed through several floor beams in bridge slab as shown in Fig. 11b. This resulted in imme-
addition to main truss members resulting in loss of parts of diate cracks at the wearing surface layer. In addition, ver-
these members. Figure 10b, c shows a common observed tical and horizontal deformations were observed at the
defect due to collision of items on board of train. Fig- movable bay of the bridge as shown in Figs. 9d and 11c.
ure 10d shows permanent deformation in bridge column In Mohamed Naguib Bridge, the structural system of the
due to vehicle collision. In these cases, straightening repair bridge consisted of simply supported successive bays. Due
procedures are applied in conjunction with adding steel to observed movements at the expansion joints, it was
plates to substitute the plastically deformed parts. decided to connect ends of main beams to the supporting
frames as shown in Fig. 11e. Hence, the structural system
3.6 Steel superstructure: inadequate repair of the main beams changed from simply supported beams
procedures to continuous beams. This led to constraining the bridge in
the longitudinal direction due to temperature deference
In some cases, inadequate or poor repair methods result in between hot and cold seasons. Consequently, diagonal
serious damage to bridge superstructure. Figure 11a shows buckling waves were observed in main beams as shown in
poor welding applications from one side only of the gusset Fig. 11f.
plate observed at the bracing level of New Gerga Bridge.
Site welding was employed to replace existing lower

123
J Civil Struct Health Monit

Fig. 10 Collision and impact defects at sample bridges

3.7 Traffic lane and sidewalks: reinforced concrete 3.8 Traffic lane and sidewalks: wearing surface
slab deck and expansion joints

Deck slab represents major part of roadway bridges. For Inspection of the roadway lanes included examination of
inspected railway bridges, deck slabs are employed for the used wearing surface layers and used expansion joints.
traffic lanes or pedestrian sidewalks. In Zefta Railway In addition, some bridges employed timber as part of the
Bridge, adjustments to the structural system of the bridge sidewalks. Figure 13a–f shows a sample of the observed
were made to accommodate a roadway lane instead of a defects for the different considered bridges. Defects can be
railway track. Generally, reinforced concrete slabs were categorized into cracking or settlement of the wearing
inspected for spalling, cracking, efflorescence, dampness, surface layer, misalignment, closing by dust or due to
potholing, delamination, or corroded reinforcement. In excessive movement, missing some elements or leakage of
some cases, the concrete cover was lost and the steel expansion joint and poor condition of timber. Repair works
reinforcement was exposed and corroded. Figure 12a–d include replacement of expansion joints according to the
shows observed defects for the different bridges. These expected movement, removal and replacement of the
defects were observed in approximately 10% of the wearing surface layer, and replacement of timber with
inspected bridges. Repair includes replacement of the more durable material.
corroded steel reinforcement, using epoxy-based materials
to connect the new reinforcement to the existing rein-
forcement, and pouring of concrete.

123
J Civil Struct Health Monit

Fig. 11 Samples of inadequate repair procedures

3.9 Traffic lane and sidewalks: guardrails and mesh Repair works include replacement of damaged or missing
parts, aligning works, removal of corroded layer, and
Guardrail and mesh represent an important part that repainting.
improves traffic safety. In the studied bridges, they are used
to separate the traffic lane from surroundings. Non-rigid 3.10 Rail and sleepers
rails are generally observed consisting of steel posts, steel
horizontal bars, and steel mesh. The observed defects, Rails and sleepers constitute an important part of the rail-
shown in Fig. 14a–d, include damage due to collision, way system. They have a direct impact upon the service-
missing parts of the rail, misalignment, and corrosion. ability of the passing trains. In addition, cracked sleepers or

123
J Civil Struct Health Monit

Fig. 12 Samples of reinforced concrete slab deck defects

loose rails will increase the dynamic effects on the steel lubricates away from the steel superstructure. In addition,
structure and lead to unexpected stresses in its members. regular removal of debris and rubbish in the pipes is
Generally, poor conditions of the sleepers in addition to required.
many missing connecting elements were observed for the
different inspected bridges (Fig. 15a–b). Recommenda- 3.12 Lighting
tions for repair include replacement of the poor sleepers,
tightening of loose bolts, and substituting the missing Illumination of bridges helps to highlight their structural
connecting elements. and architectural features. In addition, it is required by
different guidelines and specifications for safety purposes.
3.11 Drainage systems Most of the inspected bridges have insufficient lighting
services or power supply systems (Fig. 17a, b). The rec-
Specifications and guidelines specify the minimum diam- ommendations include introducing new lighting schemes
eter and slope for drainage pipes, outlets, and drip grooves. that enhance the esthetics of bridges and show their his-
Great care is required such that the system does not dis- torical significance and ensuring the availability of the
charge on the concrete or steel surface leading to damage required power supply.
or corrosion. Generally, drainage problems are caused by
blockage of pipes with rubbish or debris. During visual 3.13 Substructure elements: piers and abutments
inspection, it was observed that most of the inspected
bridges did not include a clear drainage system (Fig. 16a, Piers and abutments represent an important part of the
b). Such improper drainage properties resulted in dis- bridge as they convey loads to the soil. In the inspected
charging on the superstructure and substructure as seen in bridges, the substructure elements were composed of
Fig. 16c, d. Recommendations include introducing a drai- reinforced concrete and covered with protective stony
nage system that ensures discharging of water, grease, or layer. They were checked for scour or erosion. Moreover,

123
J Civil Struct Health Monit

Fig. 13 Samples of wearing surface and expansion joints defects

measurements were made using surveying equipment to 3.14 Excessive vibrations and serviceability
check the vertical alignment of the piers and abutments and
to record any possible movements. In addition, bearing Traffic-induced vibrations can result in unsatisfactory
seats were checked for cracking or spalling especially near behavior of bridges and discomfort for the users. Generally,
the edges. Finally, the concrete surface was checked for this problem does not affect structural safety; however, it
any deterioration signs, especially in areas exposed to affects regular users’ confidence in the structure. In the
roadway drainage. Figure 18a, b shows a sample of the Kanater Bridge, excessive vibrations were reported during
observed defects including cracks, loss of the concrete previous assessments of the bridge. This was the only
cover and appearance of reinforcement steel. bridge to suffer from this problem. Additional rigid frames

123
J Civil Struct Health Monit

Fig. 14 Samples of guardrails and mesh defects

Fig. 15 Samples of rail and sleepers defects

were added near supports in order to increase the cross- 3.14.1 Conclusions
sectional rigidity as shown in Fig. 19 based on the study
performed by Zaki and Abu-Hamd [27]. Possible solutions This paper presents summary of common defects observed
include adding dampers, bracing members, or decreasing during an inspection campaign including 76 railway
the velocity of trains. bridges in Egypt in addition to several roadway bridges in
Cairo governorate. The study was composed of different
phases including visual inspection, tests, modeling, and

123
J Civil Struct Health Monit

Fig. 16 Poor and lack of drainage systems in inspected bridges

Fig. 17 Insufficient lighting in sample of inspected bridges

piloting possible repair or rehabilitation procedures. The • In most cases, existing sizes of members coincide with
current paper focuses on the observed defects in the steel the available design drawings and documents related to
superstructure and the concrete substructure during visual bridge. However, changes in member sizes were
inspection phase. The following main conclusions can be observed due to repair procedures applied throughout
drawn: the service life of the bridge.
• Service life of many bridges has exceeded 100 years.
• The study showed that the status of the inspected
Hence, continuous monitoring of these bridges is
bridges ranged between good to fair with poor signs in
crucial.
some cases.

123
J Civil Struct Health Monit

Fig. 18 Piers and abutment defects

Acknowledgements The authors wish to express their sincere


appreciation to the structural team at EHAF Consulting Office for the
technical support. The authors also would like to acknowledge the
support provided by the Egyptian National Railways (ENR).

References

1. Hai DT (2006) Current status of existing railway bridges in


Vietnam: an overview of steel deficiencies. J Const Steel Res
62:987–994
2. Hai DT, Yamada H, Katsuchi H (2004) Existing bridge condi-
tions in Vietnam: current failures and their causes. Bridge
maintenance, safety, management and cost (IABMAS). Kyoto
2004:337–339
3. Spyrakos CC, Raftoyiannis IG, Ermopoulos JC (2004) Condition
assessment and retrofit of a historic steel-truss railway bridge.
J Constr Steel Res 60:1213–1225
Fig. 19 Rigid frames added near supports, Kanater Bridge
4. Ermopoulos J, Spyrakos CC (2006) Validated analysis and
strengthening of a 19th century railway bridge. J Eng Struct
28:783–792
• The explored defects included corrosion, fatigue initi- 5. Bancila R, Petzek E, Silvia R, Ionita O (2009) Assessment of
failure and malfunction in steel bridges. Joint workshop of COST
ation cracks, loss of connecting elements, collision action TU0601 and E55, Ljubljana
damage, concrete cracking, failure of expansion joints, 6. Zhou YE (2006) Assessment of bridge remaining fatigue life
poor conditions of sleepers, improper drainage or through field strain measurement. J Bridge Eng 11(6):737–744
illumination system, in addition to excessive vibrations. 7. Frangopol DM, Strauss A, Kim S (2008) Bridge reliability
assessment based on monitoring. ASCE J Bridge Eng
• In some cases, poor applied maintenance procedures 13(3):258–270
that affect the structural system of the bridge can lead 8. Morales M, Bauer D (2006) Fatigue and remaining life assess-
to severe consequences including partial or complete ment of steel bridges more than 50 years old. In: Proceedings of
failure. the 7th International conference of short and medium span
bridges
• Determination of fatigue life of different member 9. Oliveira CS, Camacho VT (2016) Data-base with in situ vibration
requires reasonable and detailed record of actual traffic frequencies of bridges in Portugal. J Civil Struct Health Monit
during service life of bridge. In Egypt, the given 6(5):851–862
records are usually larger than actual traffic which may 10. Das S, Saha P, Patro SKJ (2016) Vibration-based damage
detection techniques used for health monitoring of structures: a
lead to under-estimating the remaining fatigue life of review. J Civil Struct Health Monit 6(3):477–507
members. 11. Hassan MM, Abbas H (2017) Dynamic characteristics of old
• Corrective actions and suitable maintenance should be railway steel bridges in Egypt. In: Proceedings of the Interna-
performed for observed defects. In addition, periodic tional Conference on Advances in Sustainable Construction
Materials and Civil Engineering Systems (ASCMCES-17)
inspection plan and continuous monitoring should be 12. Biezma M, Schanack F (2007) Collapse of steel bridges. ASCE J
considered for the existing bridge inventory in Egypt. Perform Constr Facil 21(5):398–405

123
J Civil Struct Health Monit

13. Deng L, Wang W, Yu Y (2015) State-of-the-art review on the 21. Haghani R, Al-Emrani M, Heshmati M (2012) Fatigue-prone
causes and mechanisms of bridge collapse. ASCE J Perform details in steel bridges. J Build 2(4):456–476
Constr Facil 30:1–13 22. The Egyptian Code of Practice for Steel Construction—Allow-
14. Ghosh U, Ghoshal A (2002) Experiences in rehabilitation of steel able Stress Design (ECP 205-2007) Housing and Building
bridges. J Struct Eng Int 4:269–272 Research Center, Building and Physical Planning, Giza, Egypt
15. Caglayan O, Ozakgul K, Tezer O (2012) Assessment of existing 23. CEN, Eurocode 3 (1992) Design of steel structures, part 1–9:
steel railway bridges. J Constr Steel Res 69:54–63 fatigue. European Committee for Standardization, Brussels,
16. Abbas HH, Hassan MM (2016) Evaluation of strengthening Belgium
applications for old railway bridges in Egypt. In: Proceedings of 24. Faraz S, Helmi K, Algohi B, Bakht A, Mufti A (2017) Sources of
the 19th International Conference on IABSE Congress, errors in fatigue assessment of steel bridges using BWIM. J Civil
Stockholm Struct Health Monit 7(3):291–302
17. American Railway Engineering and Maintenance of Way Asso- 25. Raeisi F, Mufti A, Mustapha G, Thomson DG (2017) Crack
ciation (2010) Manual of Railway Engineering. AREMA, detection in steel girders of bridges using a broken wire electronic
Lanham binary sensor. J Civil Struct Health Monit 7(2):233–243
18. Lee S (2011) Color image-based defect detection method and 26. Fasl J, Helwig T, Wood SL (2013) Probabilistic method for
steel bridge coating. In: Proceedings of the 47th ASC Annual estimating remaining fatigue life in steel bridges using measured
International Conference Proceedings, TX strain data. J Civil Struct Health Monit 3(4):317–324
19. Shen HK, Chen PH, Chang LM (2013) Automated steel bridge 27. Zaki MA, Abu-Hamd MH (2007) Rehabilitation assessment of a
coating rust defect recognition method based on color and texture steel railway bridge by dynamic field testing. J Struct Infrastruct
feature. J Auto Const 31:338–356 Eng 3(4):343–353
20. The Public Works Research Institute (1992) Joint report on the
maintenance of weathering steel bridges. The Japan Iron and
Steel Federation and the Japan Bridge Association, p. 71

123

You might also like