Professional Documents
Culture Documents
Method Statement For Working Bored Pile (IFA, Rev. C)
Method Statement For Working Bored Pile (IFA, Rev. C)
SEQ
26.MAY.2022
FOR APPROVAL 2
OWNER’S REPRESENTATIVE :
CONSULTANT :
CONTRACTOR :
SUB-CONTRACTOR :
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement
Rev.C
Revision History
REV. SEQ. REVISED
ISSUE DATE DESCRIPTION REMARK
NO. NO. PAGE
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement
Rev.C
TABLE OF CONTENTS:
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 1
Rev.C
Submit legal documents, records relating to the construction contract: organization chart,
decision of appointment…etc.;
Survey, make status quo record of neighboring structures;
Expected disposal site: Land mine Tan Son Dam, Quang Tien commune, Quang Trach
district, Quang Binh province, about 16 km from the project, with an area of 5,972 hectares;
The estimated dumped reserve is about 250,000 m3 managed and exploited by COSEVCO 1.5
Joint Stock Company (according to the mining license No. 767/GP-UBND issued by the
People's Committee of Quang Binh province on April 3, 2013). demand to make use of the
project's excess soil and rock to make construction materials and compensate for the
environment after mining.
(Or) The afforestation land of Dang Ngoc Thon household in Minh Son village, Quang Dong
commune, Quang Trach district, Quang Binh province has an area of 5.6 hectares, about 3 km
from the project; The estimated dumped reserve is about 150 thousand m3 (according to the
land allocation map of the 151st century, section 2, lot K2 1-1A/5.6 together with the land
allocation decision No. 174/QD-UB signed by the People's Committee of Quang Trach district
signed by the People's Committee of Quang Trach district. On March 1, 1997) there is a need
to make use of the excess soil and rock of the project to make roads to the site and enhance
nutrient silt to plant trees, to add soil to the eroded area.
5 - Machinery, equipment, supplies and materials preparation work:
a- Mobilization of machinery-equipment:
Machinery-equipment will be gathered to the site under the plan of equipment has been
mobilization submitted in bids or in registration documents to the Owner.
The Owner or its representative - Project Management Consultant will check, inspect all
machinery, equipment of Contractor before approving to use for the project. Standard for
check, inspection and acceptance will base on: specifications of the project approved by the
Owner and safety requirements as prescribed by the State.
Machinery - equipment gathered at the site shall have full necessary documents as prescribed:
accreditation document, insurance, operation license ... etc.
Machinery- equipment gathered at the site shall be arranged as the chart shown on the
construction organization method. In case of absence in the construction organization method,
Site Management Board shall prepare an additional equipment gathering document before
they are transported to the site.
List of main equipment:
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 2
Rev.C
Số Năm sản
Stt Tên máy thiết bị Công suất Xuất xứ
Lượng xuất
No. Name Capacity Origin
Quantity YOM
01- Máy khoan
Drilling Rig
Máy khoan BG42 hoặc
tương đương Hmax=105m Đức
1 1 2012
BG42 Rotary Drilling Dmax=2,8m Germany
Rig or epuivalent
Máy khoan BG36 hoặc
tương đương Hmax=68,8m Đức
2 1 2005
BG36 Rotary Drilling Dmax=2,0m Germany
Rig or epuivalent
Máy khoan Suny
SR285R hoặc tương
Hmax=94m Trung Quốc
3 đương 2 2021
Dmax=2,3m China
SR285R Rotary Drilling
Rig or epuivalent
02- Máy cẩu
Crane
Cẩu HITACHI KH500
hoặc tương đương Nhật Bản
1 1 Pmax=100T 1996
KH500 Crawler Crane Japan
or epuivalent
Cẩu HITACHI KH180
hoặc tương đương Nhật Bản
2 1 Pmax=50T 1988
KH180 Crawler Crane Japan
or epuivalent
Cẩu SCC550A hoặc
tương đương Trung Quốc
3 2 Pmax=55T 2020
SCC550A Crawler China
Crane or epuivalent
03- Máy đào
Excavator
Máy đào Sunward
SWE210 hoặc tương
Trung Quốc
1 đương 4 Vmax=0,95m3 2016
China
Sunward SWE210
Excavator or epuivalent
(Attach the device's profile)
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 3
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 4
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 5
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 6
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 7
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 8
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 9
Rev.C
Site Manager
Nguyen Nhu Hoan
Tel: +84. 904.649.868
Temporary Facility Site QA /QC Manager QS Manager HSE Manager Techinical Leader
manager Doan Ngoc Duc Le The Luan Nguyen Xuan Vu Nguyen Minh Giang
Le Dang Minh Tel: +84.975.843.317 Tel: +84.984.605.051 Tel: +84.988.579.100 Tel: +84.912.663.769
Tel: +84. 985.121.633
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 10
Rev.C
Project Manager
Han Quyet Thang
Tel: 0978826555
Site Manager
Cao Ngọc Thu
Tel: 0983262680
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 11
Rev.C
Surveying work
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 12
Rev.C
9 - Overall bored pile construction procedure:
PLACE CASING
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 13
Rev.C
- Use total station to take the pile - Drill holes which depth is shorter 0.5m - Supply drilling fluids and drill the holes to
coordinates. than Casing length (depending on geological 50% depth;
conditions)
- Take 4 marks in 2 mutually - Check slope and correct if necessary;
- Use crane to place Casing;
perpendicular directions. - Supply drilling fluids and drill to 100%
- Use total station to check pile axis;
- Backfilling to compact around Casing; depth;
- Install ditch (or coffa) to prevent drilling - Stop drilling when taking the design depth.
fluids from spilling out.
- Pile coordinates follow to the design - Follow to the coordinates of the total - Check standing position before drilling;
(X-Y) station: - Drilling speech follows to standard;
- Tolerance under X-Y directions: <5.0 cm; - Diameter: ± 2.0cm;
- Follow to determined axe coordinates on - Depth: + 10cm compared with the design.
the field using ruler measurements;
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 14
Rev.C
VERTICAL DIRECTION OF BOREHOLE FABRICATE STEEL CAGES 1ST CLEAN DRILLED HOLES
WALL
- Check the depth of piles; - Ensure quantity and quality; - Check the depth of piles;
- Prepare, install the Koden machine; - Store re-bars (raw material and finished - Replace all fluids.
- Check the vertical direction of products);
boreholes by Koden machine. - Fabricate steel cages in compliance with
shop drawings;
- make steel cage hooks.
- The vertical direction of piles is - Check detailed structure (on Specification); - Depth: measured at 2÷4 positions at drilled
≤1%; - Check cleanness; hole edges, equivalent the depth after
dredging
- Check stiffness and stability when loading
to install;
- Check steel cage hooks.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 15
Rev.C
- Place the cages into the drilled holes; - Change the drilling fluids (if necessary) - Install the pipes for casting the concrete;
- Position and reinforce the steel cages - Check the depth; - Cast the concrete and cut the pipes;
to fix to the drilled hole; - Check quality of drilling fluids. - Stop casting the concrete when achieving
- Pump the water and weld to seal the design level;
ultrasonic pipe ends; - Clean the concreting equipment.
- Position the steel cages to fixe to the
Casing.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 16
Rev.C
10 - Drilling fluids:
a- Drilling fluids:
Basic effect of drilling fluids is to create pressure column to borehole walls and against to soil
pressure on borehole wall and pressure of groundwater and causes leading to landslide the
boreholes.
Because the drilling fluids keep the borehole walls stability during the construction, they
should be constantly maintained in entire length of boreholes and during the bored pile
construction.
Drilling fluids can be used such as bentonite or polymer depending on geologic requirements
of each project. The use of bentonite or polymer can also be based on the local requirements
on environmental protection where the project is located.
b- Working principle of drilling fluids:
Density of drilling fluids is greater than or equal to water density (1> 1.15). Therefore, they
can create pressure equilibrium column and fight from infiltration of groundwater, landslide
due to pressure of groundwater.
Drilling fluids have high viscosity (18> 45 s), with a lower density to concrete. Therefore,
they bring the flexibility of fluids which help casting concrete by surge mortar method.
Coating member which is created from the drilling fluids will form a thin member to link the
surface of drilled hole walls and contribute to against the landslide of hole walls.
Gel degree of fluids brings the consistency throughout the construction process and prevent
from the groundwater infiltration causing the damage to link of fluid components and loss of
drilling fluid effects. Depending on the use of bentonite or polymer, the gel degree can change
leading to change of features appropriately to different construction conditions and methods.
PH of fluids in a range of 7> 12 will make sure the chemistry of fluids and does not affect to
the quality or concrete or rebar as well as nature of the fluids in the construction process .
c- Selection of bentonite and polymer:
Density and gel degree of bentonite is larger than polymer. Therefore, it can be used for
different geology types. Especially for some weak geology such as loose mud or crude sand
particles, the bentonite is necessary selection.
However, besides above mentioned advantages, the bentonite fluid has several limitations:
Due to big density and gel, it is more complex to treat in both the construction and discharge
to the environment and make unsanitary site.
Bentonite often causes sediment at pile bottom. Without treating carefully, sediment and solid
bentonite can affect the quality of concrete.
Due to above factors, construction phases also will be longer.
Polymer fluid has lighter density, not keep the sand and can be self-disintegrated in natural
environment, hence:
Sand and solids will immediately sink to the bottom of pile during drilling and just use
buckets to clean the pile bottom after drilling without blowing, washing the fluid. The
construction phase will be shorter.
Polymer is light and clean. So it does not affect to the quality of concrete when casting.
It does not affect to the environment.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 17
Rev.C
VẬT LIỆU
MATERIALS -Cung
- Supplycấpthe
nước vào into
water
-Bentonite
- Bentonite(dạng
(dried bột khô,package)
powder, đóng bao) DRILLING FLUIDS MIXING mixingtrộn;
container;
thùng
- CMC STATION
TRẠM TRỘN - Give a small Bentonite
-Phụ giaadditive
CMC (tùy(depend on vào
thuộc geology)
địa -Rắc lượng nhỏ vật liệu
DUNG DỊCH KHOAN into the water;
chất) Mix Bentonite into the water Bentonite
- Mixing vào nước;
time: 15-20
Stir well by the mixing machine -Thời
minutesgian trộn: 15 20
NƯỚC Trộn bột Bentonite vào nước; phút.
WATER
-Nước
- Water(nước
(testedđãimpurity
được thí nghiệm )
components Khuấy đều dung dịch bằng máy trộn
thành phần tạp chất)
Fail đạt
Không
--Dung
The drilling fluidsđược
dịch khoan will
SEDIMENTATION TANK SYSTEM DRILLING FLUIDS IN BOREHOLES be recoverd dutting the
DUNG DỊCH TRONG hồi về trong quá trình
HỆ THỐNG BỂ CHỜ LẮNG The drilling
cleaning the hole and
The used drilling fluids are transferred HỐ fluids
KHOAN are supplied làm sạch
casting đáy hố khoan
the concrete
to the sedimentation tank system will constantly into the boreholes during the và trong quá trình đổ
Dung dịch khoan
be transferred qua sử dụng
for deposition được
of coarse construction
Dung dịch khoan được cấp liên tục bê tông.
đưa qua
grained hệ thống bể chờ lắng để
components vào hố khoan trong suốt quá trình thi
lắng đọng thành phần cát hạt thộ
công.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 18
Rev.C
After mixing, the bentonite fluid is pumped into the tank or silo and incubated for 6 to 12
hours to ensure composition of bentonite to swell up.
Tests of bentonite quality are conducted after the swell and the fluid is used to achieve the
mechanical and physical indicators according to rules: (Bentonite shall be used and have to
satisfy the requirements in sub-clause 10.5.6.6 and table 1 in TCVN 9395-2012)
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 19
Rev.C
Polymer used as drilling fluid shall often be added Soda additive to increase the viscosity.
NGUYÊN LÝ HOẠT
OPERATION ĐỘNG CỦA
PRINCIPLE DÂY CHUYỀN
OF CHAIN USINGSỬ DỤNG DUNG
POLYMER DỊCH POLYMER
FLUID
VẬT LIỆU
MATERIALS DRILLING FLUIDS MIXING --Cung cấpthe
Supply nước vàointo
water
-Polymer(dạng
- Polymer (driedbột khô,package)
powder, đóng bao) TRẠM TRỘN
STATION thùng trộn;
mixing container;
- Soda
-Phụ giaadditive
Soda (depend on geology) --Trộn phụ into
Mix Soda gia Soda tan
the water
DUNG DỊCH KHOAN
Mix Soda and Polymer into the water -đều
Give a small
trong nước;Polymer
Stir well by the mixing machine into
-RắcSoda
lượngandnhỏ
water;
vật liệu
Trộn bột phụ gia Soda và Polymer - Mixing time: 15-20
NƯỚC
WATER trong nước; Polymer vào dung dịch
minutes
-Nước
- Water(nước
(testedđã được thí
impurity nghiệm )
components Khuấy đều dung dịch bằng máy trộn Soda và nước;
thành phần tạp chất) -Thời gian trộn: 10 15
phút.
--Dung
The dịch
fluidsđược
will bơm
be
CHECK
KIỂM DRILLING
TRA DUNG FLUIDS
DỊCH KHOAN DRILLING FLUIDS STORING pumped
từ thùngfromtrộn
the mixing
lên hệ
TRẠM CHỨA
STATION container to storeage tank
DUNG DỊCH KHOAN thống bể chứa.
Quality of drilling fluids system;
Chấtoflượng
Standard drillingdung
fluidsdịch khoan --Dung dịch sau
The mixed khiwait
fluids trộn
Store the drilling fluids in Silos or
Tiêu -chuẩn
- Density; dung dịch khoan:
Viscosity tanksdung
Chứa or sinks
dịch khoan trong hệ thống chờ a trong
in time thờifor gian
full
-Dung
- Sand trọng- pH
content; ; -Độ nhớt; Silo hoặc bể chứa hoặc Tank chứa trương nởbefore
expansion hoàn using
toàn
-Hàm lượng cát ; -Nồng độ PH. (for 2h) khi sử dụng
trước
(khoảng 2h)
Fail đạt
Không
- The fluids
-Dung dịchberfore
trướcbeing
khi
supplied into the
KỂMDRILLING
TRA cấp xuống hố
boreholes will khoanbe
CHECK
được
checkedkiểm tra chất
the quality:
DUNG DỊCH KHOAN
FLUIDS
lượng:
+Density:
Checktrathechất
quality of drilling +1.01:1.15g/cm3
Tỷ trọng dung dịch:
Kiểm lượng dung +Sand contend: <63;zoor
fluids before drilling 1.01 1.05g/cm
trước khi khoan +Viscosity:18:45 seconds
+ Hàm lượng cát: ≤2%;
(funnel 1500/946cc)
+pH:8.5-11.5
Độ nhớt: 37 48 giây
(phễu 1500/946cc);
Pass
Đạt + Độ PH: 8.5 11.5.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 20
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 21
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 22
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 23
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 24
Rev.C
2.4m wide square base; cylindrical silo with a diameter of 2200mm; The height is 6000mm. Before erection, the ground will be reinforced with a
layer of smooth bricks and compacted by an excavator. The steel plate is placed on the reinforced ground before placing the Silos on it.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 25
Rev.C
R+1000 500
Axes
Tim cọc
R
Focal points 1-2
Casing
R+1000
500
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 26
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 27
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 28
Rev.C
Drilling work
13 - Checking the vertical direction:
- The vertical direction of drilled piles will be checked by check the koden machine. Maximum
permitted deviation of pile compared to depth in any levels is <= 1%.
- Completed holes with too big deviation as prescribed 1%, their bore hole wall shall be
adjusted by widening in the opposite direction of deviation. Pile body will be expanded but overall
deviation will decrease to the required level.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 29
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 30
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 31
Rev.C
- Rebar fabricating yard is next gathering yard and storage area; the surface shall be flat, dry
and well drained when necessary. Area of fabricating yard depends on quantity and progress of
each specific project.
- Stored reinforcements and finished steel cages but not be used shall be covered by tapurlin
when it rains or it does not rain but the rebar fabricating is not conducted.
b- Fabricating the bored pile steel cages:
- The steel cages will be fabricated as approved shopdrawings and in compliance with norms of
reinforcement work as defined in Vietnamese Standard.
- he steel cages will be fabricated on steel or wood frames which are higher 30 cm in minimum
from the ground to avoid flooding.
- The steel cages can be fabricated each cage under length of standard rebar (11,7m) or longer
cages (2x11,7m; 3x11,7m or option) to save time. The selection depends on the construction
conditions of each specific project.
- Steel bars will be linked together according to the fastening method according to the design
drawings.
- The ultrasound tubes are placed into the steel cages in right position and fixxed by zinc wires
and hooks under the tube botttom to avoid falling tubes when loading by cranes.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 32
Rev.C
fastening joints, steel bars connecting with alternating steel bars and longitudinal steel bars are
made on the same 01 section cross-section.
- The ultrasound tubes between cages are connected by welding after the main reinforcement
between the two cages is connected fixedly. During placing the steel cages, the ultrasonic pipes
will be fixed into the steel cages by zinc wires with a minimum distance of 4m/connection.
- It is necessary to fulfill the ultrasonic tubes with the water to prevent uplift and during
checking water level in the ultrasound tubes to detect leakage due to non-ensured welding
connection. In case of leakage, pull up the cages to repeat welding. The ultrasonic tubes are
covered with taps after placing the cages.
- All steel cages are placed to design level and fixed by hanging into the mount of casing. Bar
used to hang the cages shall be calculated with length to suit the level of designed hanging.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 33
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 34
Rev.C
+ Plasticity of concrete is shown through the ability to keep the frame after slump test
+ Aggregates of concrete stones are not too big or small
+ Certificate of origin of concrete mixer trucks to demonstrate that concrete is right type
and does not exceed concrete setting time
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 35
Rev.C
to the station but it will be pumped to waste storage tanks to treat before transporting out of the
site.
- The first concrete amount poured into the piles will be surge concrete quantity on pile top
after finishing casting concrete. This concrete amount is in direct contact with drilling fluids and
often becomes contaminated, it should be removed. Removed quantity is usually 1m from the
surface.
- For the test pile, the top of the pile is horizontal to the ground level, the clean concrete is
allowed to reach the height of the pipe mouth, the process of withdrawing the wall pipe, the
concrete is still added to ensure the quality of the concrete. . (In some cases, an excavator or pump
truck can be used to add clean concrete during the removal of the bulkhead.)
- All figures during casting concrete include: time, quantity of concrete, surge level, depth of
tresime pipe, cut pipe length, slump ... etc. They shall be recorded accurately in compliance with
defined forms to form the documents of pile quality assessment in the future.
Casting concrete
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 36
Rev.C
- Use the cranes to withdraw the casing in vertical direction. The crane shall have large lifting
capacity; operation stand is near and face the withdrawal of casing position. Tilt angle of the crane
while drawing the casing is 70 degrees, withdraw the casing by the cable 4 with slow speed. Never
use the crane to shake casing during cable pull of casing.
- Cut all beards for hanging the steel cages and ensure free from obstructions before removing
the casing.
- Use excavators to support during removing casing but to ensure the impact of excavators and
cranes are completely independent on the casing body.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 37
Rev.C
A Surveying work
1 Wrong coordinates - Wrong entering of benchmarks - Check the determined coordinates - Re-determine the coordinates
of piles - Check and compare with coordinate
system in fact
- Fail total station - Test machine periodically, clean - Bring the total station to accreditation
regularly, store under the guidance of center for repair and recalibration
manufacturer - Replace by other total stations.
- Re-check 3rd benchmark after installing
coordinate system with 2 initial
benchmarks
B Drilling to give the holes
1 Wrong drilling Mistake on shop drawings - Re-check the shop drawings before - In case of wrong drilling, fill the pits
position of pile performing by crushed stones and re-drill correctly
center the pile position.
Wrong surveying work - Re-check the surveying work
Casing is oblique during drilling - Limit to hit bucker on Casing falsifying - Re-correct the casing
coordinates
- Compact casing tightly after being placed
2 Obstacles (rocks, - Geological conditions - Check carefully record of geological - Depending on the type of obstacles to
old foundation) in survey select the different overcome options:
the boreholes - Remnant old foundation - Check carefully record of current state of mace, grab bucket, vibratory hammer
old buildings, relevant information …etc.
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 38
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 39
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 40
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 41
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 42
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 43
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 44
Rev.C
- All workers in the shift must master and follow the general safety rules, clear the work and
coordinate smoothly;
- Shift handover must be serious and attentive in accordance with regulations on management of
motorcycle equipment;
- To determine the safety limit of the area where motorcycles operate to take measures to prevent
barriers and signs;
- When working at night, there must be enough lights. Dangerous places must have warning
lights and protection when there is no barrier cover even for a short time.
2 - Safety principle for crane:
- Do not park the crane where the soil has just been filled or compacted, it is necessary to spread
corrugated iron;
- The minimum safe distance between the crane's operating range and surrounding obstacles is at
least 5m;
- When dropping the crane hook at the lowest position on the winch drum, there must be at least
5-3 turns of the cable to prevent the cable from slipping;
- Do not place the crane near and below the power line with any voltage;
- Periodically check the crane, winch and gantry cable system;
- Operation must be smooth, not jerky;
- The position of the crane must be most convenient in observing the operator, the crane and the
place where the crane is lowered;
- When lifting the wheel, it must be jacked up or carefully inserted to avoid uneven settlement or
moving the crane while moving;
- When lifting the crane, do not stand below the crane's operating range before the crane has
stabilized on the ground;
- Do not drag or slant heavy objects, only pull up vertically;
- Do not move and rotate the boom to move the crane horizontally at the same time;
- For any reason to stop, it is necessary to lower the crane;
- Working at night must have lights.
3 - Safety principle for bored pile
- Before drilling, always pay attention to inspecting underground construction such as drainage
systems, power lines must be hung high, firmly fixed...
- Wastes during the drilling process are always kept away from the borehole;
- Arrange enough light and means of communication for people working on the construction site;
- The machine moving path must be stable;
- The vertical and horizontal slope must be within the allowable limit according to the machine
history;
- Equipment and machinery must be firm and stable;
- Regularly check the pulley, lifting cable... of the boom and the drill bucket before the shift. If
there is a problem, it must be repaired immediately;
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 45
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 46
Rev.C
- The work area must not be filled with oil or flammable substances. When a fire occurs, a fire
extinguisher equipped in the welding area must be used according to TCVN 9380 - 2009;
- It is raining, heavy fog is not allowed to work outdoors;
- When working at height, must wear safety belt;
- Within 10m, it is forbidden to contact sparks;
- When finished, cut off the power of the device.
- Braze:
- Inspection, maintenance, installation, transportation of oxygen cylinders must comply with
regulations (TCVN 9380-2009);
- It is absolutely forbidden to carry out welding when the oxygen bottle has no pressure reducer
and there is no safety device on the gas generator or there is a damaged device;
- Before installing the pressure reducer on the oxygen cylinder, remove all dust and grease from
the valve;
- Gas cylinders must have full safety equipment. Fire prevention tank, manometer, safety valve...
Safety valve must be sensitive, manometer must be accurate;
- The use of metal foils is allowed. Tin-lead aluminum for making safety films.
- Prohibit the use of red copper and alloys with a copper content of more than 70% to
manufacture auxiliary parts of gas cylinders;
- Before doing so, check that the water level of the fire prevention tank must always be at the
same level as the test faucet;
- It is forbidden to install 2 soldering irons in one fire prevention tank;
- When welding, do not wrap the rubber hose leading to the bottle, clamp it under the armpit,
clamp it on the thigh, when arranging it is forbidden to flatten the tube, the red wire leads to
gas, the black wire leads to oxygen;
- It is forbidden to carry a burning torch outside of the workplace or escalate;
- Only those who have been trained professionally and have appropriate professional
qualifications can repair, assemble and test gas cylinders and oxygen cylinders;
- Transporting oxygen bottles must use spring-loaded means or keeping stacks of bottles must
have soft materials, the stack of bottles must not exceed 3 layers. When transporting the bottles
must have caps, caps and caps must be lined up on the same side. Horizontally compared to the
means of transport;
- Transporting oxygen cylinders over short distances allows for manual standing, when gloves
are prohibited. Transport within the workshop must use trolleys with rubber wheels. Avoid
carrying oxygen bottles on your shoulders
XI. PROCEDURES OF ENTRY CONSTRUCTION SITE
Arrival:
- Present the pass to the construction site to the security guard;
- Get a working card from the security guard.
When going out:
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 47
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 48
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 49
Rev.C
- Disconnect the device when not in use, do not pull the power cord to disconnect, must unplug
the outlet;
- Avoid knotting, twisting, tying or twisting the power cord. Electrical equipment must be kept
clean and dry;
- Do not use hand tools near flammable or gaseous places;
- Do not stand near wet places when using electrical equipment;
- Do not make temporary repairs to the power cord, if damaged it must be replaced;
XVII. DUST, NOISE AND VIBRATION
- Around the construction site is a fence separating the construction area from the outside. The
fence has a minimum height of 2m, the fence is made of thick corrugated iron with stiff ribs
and V5 steel oblique struts;
- The transportation of materials, loose construction materials, construction waste, mud, soil,
domestic waste, is covered to ensure no spillage during transportation. The methods of motor
vehicles when leaving the construction site must be washed to ensure that they do not pollute
the street;
- Construction waste when transported from above must be packed in bags or transported in
sealed pipelines. Do not dump construction waste that falls freely from above;
- Do not use equipment that causes noise in excess of the permissible limit according to TCVN
5949 - 1995.
- Do not use explosive energy equipment, and test piles with hammers weighing >600kg causing
noise and vibration affecting residential areas and neighboring structures.
XVIII. ENVIRONMENTAL HYGIENE
- Before leaving the construction site, the vehicles transporting waste soil and concrete must be
cleaned, sprayed and cleaned. Waste soil must be dumped in the right place prescribed by the
city;
- The construction site will always be kept clean from rubbish, the drilling mud will be
immediately removed from the site, there is a drainage system, there is a car wash system when
leaving the site. construction site, fully arrange toilets, accommodation for workers and be
checked regularly;
- Due to the nature of the construction of bored piles with a lot of mud, in order to avoid making
the site muddy, the drilled soil will be transported out of the construction site from 9pm the
previous night. until 4:00 a.m. the following morning and transported to the location specified
by the city. There is a dedicated cleaning team responsible for cleaning the construction gate
area and the street area in the construction site.
XIX. BOREHOLE SAFETY
- Before filling the old borehole, the entire Site must be notified in advance;
- There are signs of dangerous areas that prohibit people and vehicles from passing through;
- Having a system of occupational safety signs;
- Stretch seat belts around hazardous areas;
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 50
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 51
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 52
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 53
Rev.C
QUANG TRACH I THERMAL POWER PLANT Working Bored pile method statement -Page 54