Appendix E1 – TSF Management Plan

• decant pond water quality


• embankment condition.
• MRM will continue to be responsible for post mine closure monitoring, and maintenance of the
recovery system (if required), until closure criteria have been met and it is demonstrated that recovery
wells are no longer required.
MRM has invested more than $10 million since 2006 to continuously improve the performance and
management of the TSF.
MRM is committed to reducing the off-site environmental risks of the TSF, as shown by the TSF commitments
outlined in Section 7.

A summary of the TSF risks and contingency plans are shown in Table 2.

Table 2 TSF Risk Assessment, Mitigation Measures, and Contingency Plans

Risk Mitigation Monitoring Contingency


Surface water Runoff and decant water to flow to Regular updating of the water Pump water from Water
overflow Water Management Dam. balance modelling of the site water Management Dam to
Water Management Dam designed management system, to minimise other storages.
to be above the 1 in 500-year flood overflow risk. Increase the capacity of
level Regular inspection of the decant the Water Management
Maintain a suitable freeboard before system, to ensure efficient Dam.
each wet season. operation. Discharge as per
All runoff and decant water in the approved discharge
Water Management Dam to be licenses.
reused in the processing plant,
evaporated or discharged as per the
discharge license.
Failure of TSF Design in accordance with ANCOLD Regular inspection of embankment Engineered remediation
embankment guidelines for high hazard dams. integrity to be undertaken. measures in accordance
Engineering analysis of embankment Monthly piezometric monitoring of with ANCOLD
stability has confirmed a factor of phreatic surface levels within guidelines.
safety well in excess of minimum embankment.
requirements. Independent annual inspections.
Erosion of Only hard durable NAF rock that is Regular inspection of rock face Replace any rocks
outer face of resistant to erosion is to be used on integrity to be undertaken. showing signs of erosion
TSF outer face. with more competent
embankment material.
Seepage from Embankment has clay core with cut- Ongoing monitoring of seepage Increase the number or
TSF off key. rates through recovery bores and pumping rate of
Ponded water in TSF kept away from observation bores. recovery bores.
perimeter embankment. Monthly inspection of Install seepage collection
Geopolymer barrier installed around embankment for evidence of trenches.
eastern embankment. seepage.
Network of recovery bores installed
in identified seepage areas.
TSF to be capped with low
permeability layer, to prevent
ongoing entry of water at closure.
Maintain recovery bores post closure
(if required), until seepage head in
TSF reaches design level.

McArthur River Mine Phase 3 Development Project


Draft Environmental Impact Statement E1-10