NAME OF WORK : DETAILED CUM ABSTRACT QUOTATIONS FOR THE PROPOSED

CONSTRUCTION OF R.C.C.ROOF BASEMENT,GROUND,FIRST,SECOND,THIRD,FOURTH


D.NO;203/A, FLOORS HOSPITAL BUILDING AT D
THIRD,FOURTH FLOORS HOSPITAL BUILDING , NANDHAN CANCER HOSPITAL
AT ONGOLE,PRAKASHAM DIST.
BELONGS TO: DR.YARRAM RAMAKRISHNA REDDY
Basement Floors
S.No Description Of work No Length Bredth Dep/Heig Quantity Rate Per Amount
1 Supplying and Fixing of Teak Wood Doors,
Windows and Ventilators
Door 4 1.52 2.1 12.77
Door-1 1 1.21 2.1 2.54
Door-2 4 1 2.1 8.40
Windows 9 1.5 1.35 18.23

41.93 7800 Sqmt 327085.2

2 P.G.V.T.VERTIFIED TILES under C.C.1:4:8 using


40mm chipes including cost & conveyance
all materials also completed
control room 1 8.07 3.3 26.63
tps room 1 5 2.8 14.00
mould room 1 5 2.8 14.00
control room-2 1 6.7 2.5 16.75
dosimetry 1 3.23 4.83 15.60
physician room 1 3 2.8 8.40
waiting hall 1 6.03 9.44 56.92
Brachy therapy 1 6.37 5.05 32.17
corrider 1 2.16 4.72 10.20
194.67 3900 sqmt 759208.32

3 Celling For all rooms: As per Flooring Qty 194.67 390 sqmt 75920.832

4 Provison for General electrification&lightings ----------- Ls ----------- 600000

5 Provison for Sanitary,water supply&fixations ----------- Ls ----------- 500000.00

6 provision of interior work ----------- Ls ----------- 1282900.00

7 Provison for Painting ----------- Ls ----------- 600000.00

8 Provison for Bore well ----------- Ls ----------- 200000.00

9 Provison for RAMP ----------- Ls ----------- 760000.00

9 Provison for External Stair case ----------- Ls ----------- 60000.00

Total : 5165114.35
SAY 51,65,200/-
Ground floor :
TOTAL COST OF BASEMENT FLOOR BUILDING
In words
(Rupees FIFTY ONE LAKHS SIXTY FIVE THOUSAND TWO HUNDRED RUPEES only ) /-