RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 1 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022

Person’s at Risk: Contractor’s Workforce, Survey Team, Members of Public


Risk Owner Project Manager, Project HSE, Construction Manager, Supervisors, Survey Staff, Labour, Site Management
Risk Classification Revised Risk Classification
Risk Level Residual
Low/ Action to be Taken to Reduce Risk risk
S/N Activity Element Significant Potential Hazards Risk Rating Risk Rating
Severity
(R) Medium/ Severity
(R) Low/
PROBABILITY (P) PROBABILITY (P)
(S) High (S)
PXS PXS Medium/
High
 Engineering (GIS) drawings are to be followed.
 Obtain NOC from authorities. Relevant permits to be obtained from Transco.
Survey to locate if  Competent personnel to perform the job.
01 Unfamiliar Site layout conditions. 3 3 9 High Risk 1 3 3 Low Risk
any present utilities  Use of cable detector to identify the underground utilities.
 Workers to wear mandatory PPE.
 Daily task briefing to be conducted by the surveyor/supervisor.
Prepare work area Hazards:  Separate traffic area shall be marked for vehicle and personnel for Low Risk
02 3 2 6 Moderate 1 2 2
 Slip, Trip and Fall Hazards movement at site.
Risk
 Falling Object  The concerned Engineer In-charge and supervisor shall inspect the work area
 Movement of Vehicles prior commencing the task
 Poor Work area  Personnel involved in the activity shall be fit for work and trained in the
 Unauthorized Entry hazards and risks, together with control measures to be adopted in carrying
Consequence/Impact: out the task in hand.
 Serious Injury  The concerned supervisor needs to inspect the work area prior starting the
 Minor Cuts/injury task.
 Broken Bones  All operation shall ensure compliance with COVID-19 prevention
 Serious Injury to hand and body requirement as per approved plan.
parts.  Plant & Equipment and tools must be in good condition, inspected & tagged
 Minor accordingly.
 Cut/Laceration/injury  Work area shall be barricaded with provision of appropriate hazard warning
signage.
 All persons shall be briefed about the hazards and risks involved in the
activity through Pre Task Briefing by the concerned Supervisor/Foreman and
records to be maintained.
 The work area must be kept clean and tidy at all times by ensuring high
standard of housekeeping to make sure that the access and egress to the
workplace is safe and free from any obstruction.
 Materials must be appropriately managed and stacked to prevent any sort of
hazard, such as obstruction to work area, etc.
 All employees shall wear the mandatory PPE at site (Helmet, Safety Shoes,

Page 1 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 2 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
Reflective vest and Coverall).
 Refer OSHAD-SF Cop 8.0 General Workplace Amenities V 3.1 June 2018.Cop
9.0 Workplace Wellness V3.0 July 2016, Project HSE Plan, COVID-19
Preventive Control Measures Emergency Plan Rev; 0, ALDAR EHSMS
Management System Rev; 06 1st July 2019 & ALDAR/ADM OSH/EHS Alert.

 Ensure that the entire vehicle shall have valid UAE registration UAE, including
valid and relevant driving license to operate the plant and equipment.
 Driver shall follow the site safety rules (Viz. Such as, Speed limit, One way
System etc.)
 Competent Banks man should be deployed to control the traffic management
at site.
Hazards:  Reverse alarm shall be operational for the equipment and competent flagman
 Vehicle breakdown/failure due to shall be deployed to manage the vehicle maneuvering.
due to unsafe training  In-house training emphasizing the use of pedestrian access only must be
 Unfamiliarity with hazard/risks at conducted to all operative.
sites, Reversing policy, load
 Ensure that windows and mirrors are kept clean and clear.
Movement of handling arrangements, sheeting
 Do not allow passengers to ride on vehicles unless safe seating is provided
Machineries/ etc.
03 Vehicles and  Over Speeding
 Do not reverse without checking behind the vehicle for pedestrians, vehicles or Low Risk
3 4 12 High Risk any obstructions. 1 3 3
storing of  Reckless Vehicles Movement and
Material operation.  Do not remain on vehicles during loading operations, unless the driver’s
 Unsafely stacked load behind the
position is adequately protected.
vehicle  Do not attempt to get on or off moving vehicles.
Consequence/Impact:  Do not make adjustments with the engine running and guards removed.
 Traffic Incident – vehicle collision  Ensure when transporting load is secured and no loose material is kept and
& Personal Injuries loads are safe to transport.
 Never carry loose or poorly stacked loads.
 Refer to the OSHAD-SF Cop 44.0 Traffic management and logistic V 3.0 July
2017, Cop 36.0 Plant and equipment V 3.0 July 2016, Aldar Management
EHSMS System Rev-06 1st July 2019, Project HSE Plan, Traffic Management
Plan, COVID-19 Preventive Control Measures Emergency Plan Rev:0 &
ALDAR/ADM OSH/EHS Alert

Page 2 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 3 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022

 Make sure a safe access and aggress are identified.


 Ensure the condition of the truck/trailer is appropriate (checks; the
tires, mirrors, alarms, flash icons, etc…)
 Arrange Safety Induction to the drivers and helpers prior to start
delivery.
 Ensure all equipment and lifting accessories have valid 3rd party
certificate.
 All the lifting equipment shall be color coded as per project Color
coding chart.
 Load must be secure to carry out with provision of tag line (Tag line
shall be tie to the load and shall be at
Hazard:
 least 16mm thick and at least 5 meter length)
 Damage to load due to
 Safe load indicator must be operational for lifting equipment’s.
 Supervisor must be ensure proper stacking of materials.
falling during lifting.
 Provide flash icons on the project load if applicable.
 Damage to load due to
 Maintain the speed at 10km/hr. inside the site boundary of the
falling out of lifting load
project.
 Struck by object
 Get a Lifting permit and make it complete prior to start the lifting.
 Damage to cables & other
 Select a safe place to unload and store the doors.
Lifting Operation materials Moderate
04 2 3 6  Ensure the weather condition is safe. 1 3 3 Low Risk
using equipment  Damage due to Risk  Ensure the crane is in good condition and having a valid third party
(Hi- Ups etc.) Equipment/ Machineries/
inspection certificate.
Vehicles
 Ensure the crane operator having a valid UAE Driving License and
Consequence/Impact:
Third party training certificate.
 Personnel Injuries
 Ensure the slings and lifting tackles having appropriate SWL and a
 Cuts & abrasions
valid third party inspection certificates.
 Personnel Injuries
 Only competent & 3rd party certified trained rigger will lead the
 Burns
task.
 Ensure a proper communication between the crane operator and
rigger Viz.
 Isolate the lifting area with warning tapes and signs.
 Do not allow anyone to work under suspended load.
 Provide leather hand gloves and goggles for all along with the basis
PPE’s.
 Refer to the OSHAD-SF Cop 44.0 Traffic management and logistic
V 3.0 July 2017, Cop 36.0 Plant and equipment V 3.0 July 2016,
Aldar Management System Rev-06 July 2019, Project HSE Plan,
Traffic Management Plan, COVID-19 Preventive Control Measures
Emergency Plan Rev: 03. & OSH/EHS Alert.

Page 3 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 4 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022

 Avoid manual handling if possible and use mechanical mean (Wheel


barrow; hydraulic trolley, etc.) to avoid the Manual Handling Hazards
as a priority.
 Keeps the load close to your body twisting, turning and bending of
the back should be avoided.
 Check weight / size / stability and condition of the load.
 Adequate stacking of materials to prevent the slip trip hazards.
 Workers to keep the working area clean during the activity and at end
Hazard: of each working day.
 loads that are unstable,  The workers must wear proper hand gloves when carrying out the
unbalanced or hard to hold materials.
05 Manual Handling 3 3 9 High Risk 1 3 3 Low Risk
 Slip, Trip & Fall  Six steps to correct lifting: Feet apart, Knees bent (not squat), Back
 Work related upper limb Disorder straight (not necessarily vertical – 15 to 20 degrees), Arms close to
 Personal not aware the body, Hands palms grasp, Head chin out and up.
 Supervisor shall ensure operatives are familiar with Manual Handling
Hazards & Risk.
 Ensure the use of suitable task specific PPE such as hand & foot
protection.
 Ref OSHAD-SF Cop 14.0 Manual Handling & ergonomics V 3.1 June
2017, Cop 2.0 Personal Protect Equipment (PPE) Aldar Management
System Rev-06 July 2019, Project HSE Plan, & ALDAR/ADM
OSH/EHS Alert.

Page 4 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 5 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022

 Identify the presence of underground installations & take


necessary safety precautions.
 Existing underground utility services approved drawing should be
obtained for the work area.
 Existing underground utilities shall be communicated to all
operatives in the details.
 PTW from the HSE Department must be obtain prior to start any
excavation work and JSA shall be carried out by task engineer and
communicated to the workforce.
 Employ cable avoiding tools (CAT) prior to excavating.
 Always refer to the approved drawing for the designed exaction
Hazards: edge slope.
 Damage to the existing serves.  Appropriate diversions for the underground utilities whenever
 Water influx. required.
 Falling in to exaction (Plant &  Provide protection for the existing underground utilities and avoid
Trill Pit Person) mechanical exaction. Any Excavation beside to live electrical
(Manual) /  Fumes or toxic ground gases. cable, Water line & Internet cables etc. must ensure additional
Manual  Noise & Duct system precaution (Viz. NOC/Permit from authorized authorities) is
06 3 3 9 High Risk 1 3 3 Low Risk
Excavation only  Slip, Trip & Falling hazards required.
above /crossing  Reduced stability and building  Excavator, JCB etc. must not be used until buried utilities are
Transco Line  Edge collapse. expose.
Consequence/Impact:  Safety spotter shall be stand to ensure the exposed utilities will be
 Personal injury – Minor Cut Injure kept an eye with.
 Personal Injure  De-Energized or isolate if need the power/waterline prior to the
 Environment Impact excavation.
 Keep the plant equipment at least 2 meter away from the edge of
the excavation.
 Only competent engineer & Supervisor shall lead the task. During
the operation he must be present at workplace.
 Adequate barrication with warning signs shall be proved around
the excavated area.
 Supervisor shall ensure all operatives must wearing task specific
PPE during the operation.
 Refer to OSHAD-SF Cop 29.0 Excavation, Cop 46.0 Underground
Construction, ALDAR EHSMS Rev 06 1st July 2019 &
ALDAR/ADM Safety Alert.

Page 5 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 6 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
07 Trenching / Hazards  Obtain NOC /Permit from relevant authority if work out side of the Moderate
3 3 9 High Risk 2 2 4
excavating &  Contact with buried or project parameter. Risk
Backfilling overhead services.  Excavation permit will be obtained for the excavation from the HSE
 Water influx. department.
 Falling into exaction (Plant &  Before starting any excavation work PTW for excavation shall be
Person) obtained from the HSE team & it’s completely filled , signed by
 Fumes or toxic ground gases. authorized personnel (Activity Engineer, Electrical Engineer, and
 Noise & Duct approved by Construction Manager)
 Slip, Trip & Falling hazards  JSA will be generated by activity Engineer and communicated to all
 Edge collapse. involved personnel through TBT prior to start the activity.
Consequence/Impact  Trial pit shall be carried out using hand tools with wooden handle
 Personal injury – Minor Cut until reaching 90cm to locate buried live cables.
Injure  Excavation machine should be inspected as per daily inspection
 Personal Injure  checklist foe mobile plant & equipment’s (Operator & Equipment’s
 Environment Impact must have valid documents such as Registration, license, 3rd
party certificate of the operator and equipment’s)
 Flagman/Banksman should be provide. Operator & Task
supervisor shall ensure he must keep safe distance from the
equipment’s
 If underground utilities are found during the excavation , Fibrex
shall ensure that’s its adequately supported/protected from any
damage.
 Mechanical excavation is prohibited near to the underground
utilities area viz. Water pipeline & Electrical cable etc. only manual
excavation and use hand shovel with wooden handle.
 Safe access of the trench shall be provide by using slop and ladder
for safe access and egress to excavation.
 Safety control measures shall be provided over 1.2 meters
 deep (Viz. sloping, benching or shoring) depending on the actual
condition either one of them must be carried out to prevent soil
collapsed or cave-in. Shoring for excavations over 6 m deep shall
be designed by an approved Engineer and shoring installed shall
be approved and signed off by an approved Engineer.
 Competent & designated person shall be onsite at all times when
excavation activities are conducted. Inspections shall be done
every shift, be documented.
 Excavations shall be inspected by a Competent Person and the
results recorded:
o At the start of each shift
o After rain or high wind conditions
o After freezing and/or thawing temperatures occur
o After any condition that can change the integrity of the
soil
o Heavy duty activities that would change the
characteristics of the soil around the excavation

Page 6 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 7 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Spoils must be placed a minimum of 2 meters from the edge of the
excavation. Loose soil or rocks shall be removed from the sides of
excavation.
 If hazardous or unknown materials are suspected /encountered,
the work shall be discontinued until a qualified individual (or group),
i.e., environmental compliance lead, can identify the suspect
material and ensure that it is safe to continue working. If it is
determined that the material is hazardous, then all applicable
jurisdictional codes and standards must be followed in order to
handle these materials each employee in an excavation shall be
protected from cave-ins.
 Employees will not be permitted to work under loads or near
digging equipment. Employees shall be required to stand away
from any vehicle being loaded or unloaded to avoid being struck by
any spillage or falling materials.
 Foot traffic and/or walking around or behind excavation equipment
shall be avoided and all ground personnel shall establish positive
eye contact with equipment operators before moving into the path
equipment’s.
 No loaded or heavy plant& equipment shall be parked near to the
excavation for prevention of collapse.
 Provide sufficient number to hazards light and signs for awareness
of employees.
 Temporary barrication shall be provided during the excavation with
provision of competent watchman to prevent the interfering
between man and equipment’s.
Note: Any excavation beside to live electrical cable; must ensure
additional system precaution (i.e. NOC/ permit, etc.) are adhered
as per ADDC/ approved third party.
 Refer to the OSHAD-SF Cop 36.0 Plant and equipment V 3.0 July
2016, Cop
 21.0 Permit to Work System V 3.1 July 2019, Cop 29.0 Excavation
Work V 3.0 July 2016, Aldar Management EHSMS System Rev-06
1st July 2019, Project HSE Plan, Traffic Management Plan &
ALDAR/ADM OSH/EHS Alert
08 Usage of Power Hazards:  Periodical inspection shall be carried out based on inspection Moderate
3 4 12 High Risk 2 3 6
Tools  Electric Shock check list. Risk
 Electrocution  Inspect the power tools and supply cables for damages before use.
 Vibration  Use double insulated tool wherever possible, Provide body
 Noise earthling.
 Fire/ sparks  Take power supply through RCD 30mA.
 Dust  Only PAT tested passed tools shall be used at site.
 Miss Handling  Joints shall not be allowed to lie on water.
Consequence/Impact  Cables shall be protected against damages due to movement of
 Fatality vehicles.

Page 7 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 8 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Only authorized electricians shall be allowed to carry out repairs.
 Disconnect power supply while carrying out repairs.
 All the potable power tools rotating part shall be protect with guard.
 Read the tools instruction manual, and follow use and maintenance
guidelines.
 Do not wear loose clothing, Dangling objects or jewelry, Long hair
must be restrained.
 Project Engineer & Supervisor must ensure the electric wrench
machine have valid 3rd party certificate as per manufacture
recommendation,
 Unplug tools before installing, adjusting and changing any
accessory or attachment.
 Maintain solid footing and good balance when using the tools. Hold
or brace the tools securely. Be aware of your surrounding
environments.
 Always were the appropriate personal protective equipment. Safety
 Personal injury – Minor Cut Injure
glasses & Rubber gloves must worn while operating most power
 Personal Injure during the use of
tools. Other PPE may also be necessary (Refer to OSHAD- SF
Portable Power Tools.
Cop 2.0 PPE V 3.1 July 2018)
 Burns
 Do not lift or lower the power tool by using the power cord.
 Three-in plugs /industrial socket shall be used for power
connections.
 All the power tools must be inspected for monthly basis with
provision of inspection sticker as per project color coding chart.
 Warning “Do Not Use” tags are affixed to all portable power tools
under repair or maintenance preventing operative from using them.
 When using pneumatic tools, a safety clip or retainer must be
installed to prevent the equipment or hoses from coming apart.
Never point pneumatic tool at anyone.
 Ensure guards are fitted in position, stop button for emergency.
 All operative shall have Task specific PPE During the operation.
 Refer to OSHAD-SF Cop – 15 Electrical Safety V.3.1 June 2017,
Cop 35.0 Portable Power Tools V 3.0 July 2016, Aldar
Management System Rev-06 July 2019, Project HSE Plan. &
OSH/EHS Alert.
09 Use of Hand Hazards:  Ensure the use right tools for the job. Low Risk
3 2 6 Moderate 1 2 2
tools (Masonry  Miss Handling Slip, trip and fall.  Ensure all the hand tools are inspected monthly and color coded.
Risk
tools, Shovel,  Damaged worn out hand tools. And records to be kept at the store.
etc,.,)  Using incorrect type.  Defective tools should not be issued or used to perform the task, to
Consequence/Impact be checked by store keeper & Hand tools shall be free from oil,
 Improper use of hand tools, body grease &etc.
injuries  Chisel’s head shall have safety cap to avoid finger injury.
 Eye Injury  Don’t extend the spanner by using a pipe as an extension bar.
 Cut or penetrate skin easily  Never use a screw driver as a chisel
resulting in injury.  Don’t work with oily or greased hands.

Page 8 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 9 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Task specific safety training to be provided by HSE team.
 Task specific PPE’s to be worn (Gloves, goggles, mask, helmet,
shoe, vest, full sleeved coverall) at all time during the operation.
 Refer to Aldar Management System Rev-06 July 2019, Project HSE
Plan, COVID-19 Preventive Control Measures Emergency Plan
Rev:03 & OSH/EHS Alert

 Ensure the use right tools for the job.


 Ensure all the hand tools are inspected monthly and color coded.
Hazards: And records to be kept at the store.
 Ergonomics  Defective tools should not be issued or used to perform the task, to
 Slip, Trip & Falling be checked by store keeper & Hand tools shall be free from oil,
Hazards grease &etc.
 Dust  Chisel’s head shall have safety cap to avoid finger injury.
Housekeeping Consequence/Impact Moderate  Don’t extend the spanner by using a pipe as an extension bar.
10 3 2 6 1 2 2 Low Risk
(Cleaning)  Cut or penetrate skin Risk  Never use a screw driver as a chisel
easily resulting in  Don’t work with oily or greased hands.
injury.  Task specific safety training to be provided by HSE team.
 Personal injury  Task specific PPE’s to be worn (Gloves, goggles, mask, helmet,
 Minor Cut Injure shoe, vest, full sleeved coverall) at all time during the operation.
 Eye injury  Refer to Aldar Management System Rev-06 July 2019, Project
HSE Plan, COVID-19 Preventive Control Measures Emergency
Plan Rev:03 & OSH/EHS Alert

11 Fire Hazard:  No Smoking/Smoking Hazards Policy shall be communicated to all Moderate


3 4 12 High Risk 1 4 4
 Highly Flammable (hessian the employees by safety officer. Risk
cloth for  Adequate fire extinguishers and water buckets should be provide
 curing) at workplace by task specific supervisor.
 Smoking  Disciplinary action shall will be taken against the violators such as
 Storage at Workplace smoking at workplace and storing the waste.
 Waste  All waste materials shall be removed after the completion the task.
Consequence/Impact  Designated hessian cloth box shall be provided with provision of
 Burn injury adequate warning signs and firefighting arrangements.
 Serious Injury  Used quantity of materials shall be kept in workplace for only daily
 Property damage use.
 Supervisor shall ensure provide firefighting arrangement (Portable
Fire extinguishers, Water bucket etc. ) at near to workplace and his
operative must familiar the location of equipment’s.

Page 9 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 10 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Note: All COSHH materials shall store in COSHH storage area as
per SDS storage requirement to eliminate the risk of fire incident at
workplace.
 Refer OSHAD-SF Cop 8.1 General Workplace Amenities V 3.1
June 2018, Cop 54.0 Waste Management V 3.0 July 2016,
OSH/EHS Alert

Hazard:  New workers to be acclimatized with the hot weather.


 Excess physical work  Avoid highly physical tasks during the hottest part of the day & high
 Consuming alcohol, caffeine Humidity area.
or carbonated drinks.
 Supervisor shall ensure operatives are familiar with heat stress
Working in Hot
Moderate symptoms such as Heat Rush, Heat Stocks etc.
12 weather Consequence/Impact: 2 3 6 1 3 3 Low Risk
Risk  Refer to OSHAD-SF Cop11.0 Safety in the Heat V 3.1 July 2017,
condition  Heat related illness
Aldar
 Heat Stress
 EHSMS Management System Rev-06 July 2019, COVID-19
 Lack of body Acclimatization Preventive Control Measures Emergency Plan Rev:0. Project HSE
 Dehydration Plan and OSH/EHS Alert
 Before entering the office and Site he must go through TSR to
monitor the body temperature.
 Avoid the visitor entry at site and offices to prevent COVID- 19.
 Provide sanitizers for each punching machine, or cancel the
biometric where applicable.
Hazards:  Finger Biometrics has been suspended on 21/3/20. Only face
 Temperature(Fever) scanning on going at the project.
 COVID-19 Symptoms  Awareness to be increased with several trainings.
 Cough, Shortness of Breath etc.  Adequate awareness (COVID-19) signs shall be displayed at site.
Consequences:  Any suspicion to be reported and isolated in quarantine room (to be
 Most Common Illness (Running designated and disinfected 4 times a day)
Nose, fever dry cough, Tiredness)  To have the full support to stop any suspicion and reported to the
COVID-19 Moderate
13  difficulty breathing or shortness of 2 4 8 High Risk team leader 1 4 4
Prevention Risk
breath  Power tools & Hand tools to be cleaned on daily basis disinfected.
 chest pain or pressure  Emergency vehicle with trained nurse and driver to be ready for any
 loss of speech or movement suspicion if ambulance is not advisable.
 Death  All Employees shall wearing mandatory PPE (Medical mask, Hand
Personnel Affected: gloves etc.)
 Project Employees & 3rd Party  Legal and Other Reference: ADM Circular No 004/2020, 005/2020,
Employees. 006/2020, 007/2020, ALDAR Circular-ALDAR Covid-19 Protocols for
project Site; OSHAD SF Element 2 Risk Management; ALDAR
OSH/EHS MS Element 5 Risk Management & WHO (World health
Organization)
 Directives and guidelines, COVID-19 Preventive Control Measures
Emergency Plan Rev: 03. Project HSE Plan and OSH/EHS Alert.
14 Adjacent work Hazards: Low Risk
3 2 6 Moderate 1 2 2
 Unauthorized personnel
Risk
at work location, risk of Only authorized personnel to be allowed near the working area

Page 10 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 11 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Hazards to be communicated to the workforce through JSA and
acknowledged by the workforce
 Communicate and coordinate the activity with the teams nearby
injury, risk of fall and ensure no clashing in between the works occurs
Consequence/Impact:  Refer to Aldar Management System Rev-06 July 2019, project
 Personal Injury HSE Plan and OSH/EHS Alert
 Minor Cut crush Injury

 Effective Heat Stress Management should be in place.


Hazards:  Provide sufficient cool drinking water in the vicinity of working area
 Working in hot and provision of Oral-Rehydration Solution (ORS) jug.
condition/high  Frequent break as per heat stress program requirements
temperature  Arrange shaded area wherever possible
 High humidity  Cordon working area from the public.
 Excess physical work  Employees Shall Be Trained on Heat Stress Prevention Recognition
 Breach of work area by Moderate and Treatment.
15 General Welfare 3 2 6 1 2 2 Low Risk
Public Risk  Supervisor shall ensure all operative shall have & use task specific
Consequence/Impact: PPE during the operation at workplace.
 Heat stress – Heat  Operation leading team shall ensure provided adequate resources to
Stork comply with OSHAD-SF Cop 8.1 General Workplace Amenities V 3.1
 Serious Injury / Fatality July 2018
 Minor cut & Crush  Refer OSHAD-SF Cop 8.1 General Workplace Amenities V 3.1 June
Injury 2018, Aldar Management System rev Rev-06 July 2019, Project HSE
Plan & OSH/EHS Alert
 PTB (Pre Task Briefing) to be conducted by the concerned
Hazards: foreman /supervisor prior to work commencement
 General housekeeping should be provided at the end of the task.
 Poor
 Ensure all scraps are disposed in a safe manner to designated waste
housekeeping.
disposal area.
 Slip/trip/fall
General: Work Medium  All necessary precautions will be adopted to prevent fire.
16  Fire 3 2 6 2 2 4 Low Risk
Completion Risk  Job specific PPE’s to be worn (Gloves, goggles, mask, helmet, shoe,
Consequence/Impact:
vest, full sleeved coverall, full body harness etc.) at all time during the
 Personal Injury ill
activity.
health while out of
 Refer OSHAD-SF Cop 8.1 General Workplace Amenities V 3.1 June
the office.
2018, Aldar Management System rev Rev-06 July 2019, Project HSE
Plan & OSH/EHS Alert
17 Welfare facilities Inadequate rest shelter,  Provision of adequate rest shelters considering the work force at site. Low Risk
3 3 9 High Risk 1 3 3
Lack of drinking water,  Provision of sitting arrangement, drinking station, first aid
Lack of toilet facilities, arrangement, etc.
Storage to materials in non-  Provision of adequate toilet facility at site.
designated areas – rest  Safety signage to be posted on all rest shelter as awareness.
shelter,  Storage of construction materials and flammable materials is
prohibited in the rest shelters.

Page 11 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 12 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
 Smoking in rest shelters and toilets is prohibited.
 Cleaning and maintenance of the rest shelter & toilet to be done
 Regular inspection of site welfare facilities to be carried by site
supervisor and ensure checklist to be filled and maintained.
 Daily task briefing to be conducted by Site Supervisor to aware
workers regarding the adverse weather condition.
 Availability of standby emergency team.
 Immediate suspension of all high risk activities such as lifting,
Sandstorm leads to poor excavation, etc.,
18 Adverse weather visibility and inability to 3 3 9 High Risk  All workers to be evacuated from trenches during the adverse 1 3 3 Low Risk
work. weather.
 Ensure all areas are barricaded and all signage are supported with
enough ballast materials.
 Construction team shall be reinstate all damage occurred by the
adverse weather once the weather is normal.

Risk Grading Matrix


SEVERITY
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent/Almost Certain (5) 5 10 15 20 25

Absolutely Unacceptably High


15 – 25 Extreme Risk
Activity or process should not proceed in current form
Unacceptably High
8 – 12 High Risk Activity or process should be modified to include remedial planning and action and be subject to detailed EHS risk assessment

Acceptable but must be managed at “As Low As Reasonably Practicable” (ALARP) Activity or process can operate subject to management
4–6 Moderate Risk and / or modification
Acceptable without required further action
1 -3 Low Risk
No action required unless escalation of risk is possible

Page 12 of 13 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
RA Ref: WBG-HSE-RA-005

Risk Assessment
Rev No: 01
Date: 18-12-2022
Page 13 of 13
Potable water woks
Company Name: Western Bainoona Group For General Contracting (WBG) Project Title: Riyadh City Development– Infrastructure &
Streetscape - Phase 7A
Work Description: Potable Water Works Near/On TRANSCO Assets Date: 18/12/2022
Hierarchy of Control (Controls identified may be a mixture of the hierarchy in order to provide minimum operator exposure):
Elimination Eliminate the hazard.
Substitution Provide an alternative that is capable of performing the same task and is safer to use.

Engineering Controls Provide or construct a physical barrier or guard or technical measures

Administrative Controls Develop policies, procedures practices and guidelines, in consultation with employees, to mitigate the risk. Provide training, instruction and supervision about the hazard.

Personal Protective Equipment Personal equipment designed to protect the individual from the hazard.

Date of next review (If applicable): / /

Prepared By: Kashif Sharif, Eddie Young ............................................................. Approved By: Akram Hijazi ……………………………………………………

Designation: HSE Supervisor, Group QHSE Manager ........................................... Designation: Project Director ………………………………………………

Signature: ............................................................................................................. Signature: ……………………………………………………………………………

Page 13 of 13 Appendix 5