Professional Documents
Culture Documents
OM Problems Comprehensive
OM Problems Comprehensive
120
Standard deviation, = 15 newspapers. 15
Distribution of demand- Normal distribution.
Newspaper selling price- $1.25. 1.25
Newspaper purchase cost- $ 0.70. 0.7
Newspaper salvage value- $ 0.30. 0.3
Subcontract units
Regular time labour
Sub contracting
Total cost
Comparision of 3 plans
Cost
Inventory Carrying
Regular labour
Overtime labour
Hiring
Layoffs
Subcontracting
Total cost
80
8
5
per unit
per unit
Average requirement 50
Workforce required to produce 50 units per day 10
1488
75392
29760
105152
ase strategy
Expected Demand, a Production Days, b Demand per day a/b Basic production cost
900 22 41 14400
700 18 39 11200
800 21 38 12800
1200 21 57 19200
1500 22 68 24000
1100 20 55 17600
6200 124 99200
on of 3 plans
Plan 1 Plan 2 Plan 3
9250 0 0
99200 75392 99200
0 0 0
0 0 9026
0 0 9597
0 29760 0
108450 105152 117823.376623377
-2
-1
19 5714
11 3312
-13
9025.97402597403
Extra cost of decreasing production Total cost
14400
1212 12412.12
476 13276.19
24914.29
27311.69
7909 25509.09
9597.4025974026 117823.4
Week 1 2 3 4 5
Gross requirements 35 30 40 0 10
Scheduled reciepts
Projected on hand 35
Net requirements
Planned order receipts
planned order releases
Cost information
Holding cost 1 dollar per week
Ordering cost 100 dollars
Delivery lead time 1 week
find Cost of
1. Lot for Lot
2. Economic order quantity (EOQ)
3. Periodic Order Quantity(POQ)
Solution
1. Lot for Lot
Week 1 2 3 4 5
Gross requirements 35 30 40 0 10
Scheduled reciepts
Projected on hand 35 35 0 0 0 0
Net requirements 0 30 40 0 10
Planned order receipts 30 40 0 10
planned order releases 30 40 0 10 40
Q = sqrt((2*D*S)/H
Number of weeks in a year 52
Annual Demand (D) 1404
Ordering cost (S) 100
Holding cost (H) 52
EOQ 73.48 Units
3. POQ
Week 1 2 3 4 5
Gross requirements 35 30 40 0 10
Scheduled reciepts
Projected on hand 35 35 0 40 0 0
Net requirements 0 30 0 0 10
Planned order receipts 70 0 0 80
planned order releases 70 80
3 times ordered
Average weekly gross requ 27
POQ interval = EOQ/Avg Weekly Gross requirements
POQ Interval 3 Weeks
6 7 8 9 10
40 30 0 30 55
0 0 0 0 0
40 30 0 30 55
40 30 0 30 55
30 0 30 55
6 7 8 9 10
40 30 0 30 55 270
66 26 69 69 39
0 4 0 0 16
73 73
73 73
6 7 8 9 10
40 30 0 30 55 270
70 30 0 0 55
0 0 0 30 0
0 0 0 85 0
85
Job Job work time Job Due date (days)
A 6 8
B 2 6
C 8 18
D 3 15
E 9 23
Job Job work time Job Due date (days) Flow time Job lateness
A 6 8 6 0
B 2 6 8 2
C 8 18 16 0
D 3 15 19 4
E 9 23 28 5
28 70 77 11
ed as fair by
Critical ratio is an index number found by dividing
the time remaining until the due date by the work
time remaining on the job.