No. 01.12.2015 Respondent Claimant Intimated about the acceptance of the bid amount of Rs. 68,94,00,000/-, made by the Claimant. Requested to sign and return the duplicate copy of the LOA acknowledgement of the same within seven days receiving of the said letter. 23.12.2015 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing of the mobilization advance of 10%. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing 1st installment of the mobilization advance. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing 2nd installment of the mobilization advance. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing 3rd installment of the mobilization advance. 23.01.2016 Respondent Claimant Requested to meet the obligations and responsibilities that must bear by the Claimant as per Clause-10.1.1(c) and (d) of the contract agreement.
15.03.2016 Claimant Respondent Requested to hand over the
ROW as decided in meeting held in 02.02.2016. 16.03.2016 Claimant Respondent Requested to release the payment of 1st mobilization advance. 16.03.2016 Claimant Respondent Requested to release the bank guarantee of Rs. 1,51,66,800.00 towards payment of 1st Installment of mobilization advance of Rs. 1,37,88,000.00 as early as possible. 16.03.2016 Claimant Respondent Informed about the issuance of the bank guarantee for payment of 2nd installment of mobilization advance. 21.03.2016 Claimant Respondent Requested to release the mobilization advance. 17.02.2016 Claimant Respondent Submitted the details of the consulting engineer as design consultant for preparation of the project report for the said project. 18.03.2016 Claimant Respondent Stated various points that needed compliance of the Respondent. 31.03.2016 Claimant Respondent Requested NOC from the respondent for the inception of the work between the Chainage 4+300 to 4+500,that is needed for marking of the centerline. 25.04.2016 Claimant Respondent Submitted clarifications and updates on the issues and queries raised by the Respondent. 23.06.2016 Claimant Respondent Submitted the utilization certificate for mobilization advance along with other expenditures and requested to release the third installment of mobilization advance. 29.09.2016 Claimant Respondent Submitted the utilization certificate for mobilization advance along with other expenditures and requested to release the third installment of mobilization advance. 12.04.2017 Claimant Respondent Submitted an application for extension of time under Clause- 10.5 of the EPC agreement by providing all necessary details which caused delay in completion of the work. 01.11.2017 Claimant Respondent Requested permission for use of boulders after blasting of the rocks. 02.11.2017 Jharkhand State Respondent Not visible Clearly. forest Development Authority. 09.11.2017 Claimant Respondent Informed about achievement of Milestone-I and Milestone-II with the revised target set for July to Oct 2017. 17.11.2017 Claimant Respondent Requested to provide a final decision regarding the shifting of electrical poles. 06.12.2017 TL Respondent Submitted the status of the hindered land. 09.12.2017 TL Claimant Submitted monthly program for completion of the project and requested to expedite the progress of the work. 22.12.2017 Claimant Respondent Requested to entreat the electric department to carry out the assigned work, further requested to refund the DD of Rs. 1,25,903/-. 02.01.2018 TL Claimant Informed about a meeting that is to be held by AE on 6 th January 2018 along with the agenda that is to be discussed in the same meeting. 09.01.2018 TL Claimant Informed about the slow progress of the work that may be the reason for non achievement of Milestone –III & IV in appropriate time. 05.02.2018 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the designated timeframe for Milestone-IV. 15.02.2018 TL Claimant Urged the Claimant to expedite the work progress. 08.03.2018 Respondent Claimant 13.03.2018 Claimant The Collector, Informed about the hindrances Gumla created by the Local Villagers due to the non-payment of the compensation for the land acquisition. 13.03.2018 Claimant SP, Gumla Requested to arrange proper security arrangements due to threats at the site. 19.03.2018 Claimant SP, Gumla Informed about the hindrances created by the Local Villagers due to the non-payment of the compensation for the land acquisition. 26.04.2018 TL Respondent Submitted the review( facts and figures) of work progress for the perusal of the Respondent. 15.05.2018 Respondent Claimant Submitted the intention to terminate the contract under Clause-23.1.2 of Article 23 due to slow progress in work and failure to achieve Milestone- I,II,III & IV in a timely manner. 21.05.2018 TL Claimant Informed about the intention for termination of the contract under Clause-23.1.2 of Article 23 due to slow progress in work and failure to achieve Milestone- I,II,III & IV in a timely manner. 04.07.2018 TL Respondent Requested to revoke the intention for termination notice issued to the Claimant as per Clause-23.1.2 of Article-23. 06.07.2018 Claimant Respondent Requested for extension of time with rescheduling of milestone, by submitting proper reasons and arguments. 13.07.2018 MoRTH Respondent Requested to comply with the decision taken by the Hon’ble Minister (RTH, S&WR, RD & GR) by end of the first week of September 2019. 24.07.2018 Respondent Claimant Informed about the withdrawal of the notice of termination of the contract. 11.08.2018 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 13.08.2018 TL Respondent Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 13.09.2018 TL Claimant Informed about the slow progress of work as per re- revised resource based work programme. 04.10.2018 TL Claimant Requested to submit the EOT claim up to May 2018. 31.10.2018 Claimant TL Submitted the day wise calculation sheet for EOT. 20.11.2018 TL Respondent Informed about the proposal of EOT submitted by the Claimant. 12.01.2019 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 19.01.2019 TL Claimant Informed about the slow progress of the work and requested to expedite the work progress. 23.01.2019 TL Claimant Informed about the topics discussed in the meeting under the chairmanship of ADG on 19.01.2019. 29.01.2019 TL Claimant Informed about the topics discussed in the meeting under the chairmanship of ADG on 19.01.2019. 05.02.2019 TL Claimant Informed about the slow progress of the work. 04.04.2019 TL Claimant Submitted progress review report up to 31.03.2019 in view of the meeting held by DG (RD) and SS in Delhi in 25.03.2019. 09.04.2019 TL Claimant Submitted progress review report up to 07.04.2019 in view of the meeting held by DG (RD) and SS in Delhi in 25.03.2019. 30.04.2019 Claimant Respondent Requested to withdraw bank guarantee invocation letter till final decision of higher authority. 16.05.2019 Claimant Respondent Submitted the list of available machineries, material and Man power required for execution of the work. 17.05.2019 TL Claimant Requested to submit the preparedness to complete the bituminous work by June 2019 and all balance work in all respect by Dec. 2019. 20.05.2019 TL Respondent Requested to submit the preparedness of the claimant for completion of work by June- 2019. 01.07.2019 TL Respondent Submitted the valuation of the Unpaid works as per Clause- 23.5 of Article-23 of Contractor Agreement & valuation of balance work for Tender. 05.09.2019 TL Respondent Submitted the valuation of unpaid work after termination as per Clause-23.5. 10.09.2019 Claimant DG, MoRTH Requested the Ministry to take action regarding to the termination of the contract further requested that required directions, to be given to relevant authority for the withdrawal of the termination order. 18.09.2019 TL Respondent Submitted the revaluation of the Unpaid works as per Clause- 23.5 of Article -23 of the contract agreement. 05.12.2019 Claimant DG, MoRTH Submitted the Judgment of the High Court relating to revocation of the termination of the contract. 05.05.2020 TL Claimant Informed about the failure of the contractor in achieving Milestone-IV and also stated about subsequent effect of such failure as per Clause-10.3.2 06.05.2020 Claimant Respondent Requested to find the price variation bill with CPI, WPI, Diesel Price etc. 07.05.2020 Claimant TL Submitted various reasons that contributed toward the delay in achievement in Milestone-IV, further requested to the Respondent to grant time extension till 30.06.2020. 18.02.2020 TL Claimant Submitted the site inspection report dtd. 17.02.2020 as per Clause 4.7 of Section-6 Terms of Reference of Contract Agreement. 18.02.2020 TL Respondent Informed about the supplementary agreement between the Respondent and Claimant which is regarded as an integral part of the main contract agreement and in view of such supplementary agreement work program has also been approved up to 31.03.2021. And requested for the approval of EOT up to 31.03.2021 with shifting of Milestones in view of the supplementary agreement. 08.04.2020 Claimant Respondent Requested to approve the EOT and to make the payments against the pending dues for proper maintenance of the cash flow. 07.05.2020 Claimant Dist. Collector, Requested for movement pass Gumla for certain employees for continuance of the work. 08.05.2020 TL Claimant Requested to submit fresh BG for release of enchased performance security amount. 11.05.2020 TL Claimant Submitted their reply towards the letter of the Claimant by responding to each and every statement made by the Claimant. 14.05.2020 Claimant TL Requested to release the amount of Rs. 2,17,93,658/- and extension of time to 31.08.2021 for completion of the Milestone. 26.05.2020 TL Claimant Requested to mobilize referred personnel at the site. 27.05.2020 Claimant TL Requested to change the payment schedule and asked for the payment for the completed work which were kept unpaid, till May 2020. 05.06.2020 Claimant SP Requested for deployment of 10 guards immediately at the camp site, as the work is getting carried at Naxal area. 05.06.2020 TL Claimant Informed about the ineligibility of the Claimant for receiving of partial payment as per Point-5 of Rule-171 of GFR,2017. 08.06.2020 Claimant TL Requested to release Rs. 1,74,35,872.26/- withheld in form of Security Deposit. 11.06.2020 TL Respondent Requested for partial release of Retention money with necessary statutory deductions if necessary. 11.06.2020 Claimant DG, MoRTH Requested to pass appropriate order to CE, for release of EOT as per the fresh application of the Claimant. 13.06.2020 Claimant AE, Feedback Requested to release the funds Infra for execution of the work. 16.06.2020 TL Claimant Submitted their reply towards the letter of the Claimant by responding to each and every statement made by the Claimant. 22.06.2020 TL Claimant Requested to submit the interim EOT for the project with work programme and revised milestones. 26.06.2020 Claimant TL Requested to grant interim EOT at least for 3 months as the earlier approval of EOT will accelerate the progress of work. 27.06.2020 TL Claimant Informed about the shifting of milestones as per the recommended time extension. 09.06.2021 Claimant Respondent Informed about the opening of escrow account in Punjab National Bank for release of performance security. 10.06.2021 TL Respondent Requested to release the price variation bill no.-4, amounting to Rs. 66,86,576/-. 10.06.2021 TL Respondent Requested to make payment against IPC-15 amounting to Rs. 1,50,16,755/-. 15.06.2021 TL AE Requested to process the payments towards the tests conducted on structures. 25.06.2021 Claimant Respondent Requested to verify that no legal proceeding exists in the project. 30.06.2021 TL Claimant 13.08.2021 Claimant Regional Officer, Submitted CA certificate for the MoRTH reference of RPO. 14.08.2021 Claimant AE Submitted reasons for delays and requested for time extension along with rescheduled Milestone-V as per revised work program. 23.08.2021 TL Claimant Requested for the payment of GST bill, Escalation bill and running bill. 30.08.2021 TL Respondent Submitted a detailed layout of the meeting held at Ranchi on 26th August 2021. 18.09.2021 Claimant AE Requested to release the price variation bill and GST bill. 18.09.2021 Claimant AE Requested for payment of legitimate dues pending against Claimant. 22.09.2021 TL Respondent Informed about the execution of the 6 minor bridges according to the approved designs and drawings. 23.09.2021 TL Claimant Provided a tabular depiction of the statements of Contractor and AE. 04.10.2021 Claimant Respondent Submitted the details of the availability of the machineries at the site along with material stock. 07.10.2021 TL Claimant Submitted a list of work which according to the Team Leader, needed to get executed immediately. 12.10.2021 TL Claimant Requested to work as per the standards and specifications set forth in contract agreement and quality control and quality assurance plan. 13.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 23.10.2021 TL Claimant Provided a detailed description about the financial and physical progress of work and expressed discontentment regarding the same. 23.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 29.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 29.10.2021 TL Claimant Requested to submit resource based work program. 06.11.2021 TL Claimant Requested to submit resource based work program. 12.10.2021 TL Claimant Informed that no productive work at the site can be taken up till monsoon. 12.11.2021 Claimant Respondent Requested written confirmation for construction of the Toll Plaza. 16.11.2021 TL Claimant Requested to submit required compliances/details relating to the points mentioned by the Team Leader along with necessary details about drawings/designs, manpower etc. 18.11.2021 Claimant AE Submitted EOT letter with other supporting documents along with Resource based work program. 18.12.2021 Claimant Respondent Submitted their response against the cure period notice of the Respondent and requested to withdraw/expunge the same notice for completion of the work. Further mentioned that if the cure period notice is not withdrawn by the Respondent, the Respondent shall treat this letter as cure period notice of the Claimant by release of the payment and pending dues. 24.12.2021 TL Claimant Submitted detailed progress report about the financial and physical progress of work. 27.12.2021 TL Claimant Submitted the remarks of the AE against the cure period notice of the contractor. 14.01.2022 Claimant AE Requested for de-scoping of Toll Plaza from the scope of the work. 14.01.2022 Claimant AE Informed that the work at Ch 11+650 have been executed as per drawing and design approved by the Authority. 29.01.2022 Claimant AE Requested to release the pending payment against the execution of minor bridge work. 16.02.2022 Claimant Respondent Requested to release the withheld amount along with GST Bill. 16.02.2022 Claimant Respondent Requested to sanction the time extension pending at the office of the Respondent. 20.02.2022 Claimant AE Requested to release the pending funds for smooth execution of the work. 24.02.2022 TL Claimant Requested to submit the revised work program for EOT recommendation. 24.02.2022 Claimant Respondent Submitted reasons for delay in execution of the work, requested for time extension and rescheduling of Milestone- V as per revised work program. 25.02.2022 TL Claimant Provided a tabular depiction of the statements of Contractor and AE, regarding release of the funds. 25.02.2022 TL Claimant Informed about the excavation for construction of Major Junction work @ Ch. 12+680 on 4th Feb 2022. 25.02.2022 Claimant Respondent Requested to release the pending funds at an earliest for smooth working at the site. 02.03.2022 Claimant AE Requested to release the funds and other withheld amount against minor bridge work and bitumen work. 25.05.2022 Claimant Respondent Requested to release Rs. 5,56,72,273/- withheld against different heads so that the remaining works could be completed without any further delay. 14.06.2022 TL Claimant Submitted the compliance report to RO for observation of the EOT proposal of the Claimant. 15.06.2022 TL Claimant Informed about the site inspection program that is to be done by Regional Office Ranchi Officials. 15.06.2022 Claimant Respondent Submitted reasons for delay in execution of the work, requested for time extension till 30th October 2022 further requested for rescheduling of Milestone-V as per revised work program. 01.07.2022 Claimant Respondent Requested to make the payment of pending dues. 14.07.2022 Claimant AE Requested for the approval of the positive and negative scope of the work. 19.07.2022 TL Claimant Informed that authority may take any action against the Claimant due to lack of progress in executing of the work at the site. 19.07.2022 TL Claimant Requested for the approval of the positive and negative scope of the work. 23.07.2022 Claimant AE Requested to release the bill for the work done which is very much necessary for increasing of the liquidity of the project. 29.07.2022 Claimant Respondent Submitted the photographs of the maintenance work as per the instructions of the AE. 05.08.2022 Claimant Respondent Requested for further directions of the CE against the recommendation of the termination of the project. 10.08.2022 Claimant Respondent Submitted various points that needed through reconsideration before foreclosure/termination of the contract. 17.08.2021 Claimant AE Submitted the design and drawings for the Bridges at Ch. 0+140Km and Ch 7+190 Km. 22.08.2022 Claimant Respondent Submitted photographs to show the work progress at the site. 27.08.2022 Respondent Claimant Informed that the erroneous GST bill submitted by the Claimant would be rectified by an expert to be appointed by the RO, MoRTH , for early payment of such bills. 27.08.2022 Claimant DG, MoRTH Submitted the details of the GST Bills, Price variation Bills which are withheld by the Authorities against each RA bill and requested for making the payment of all such withheld. amounts for proper and smooth functioning of the work. 28.08.2022 Claimant Respondent Informed about the cost incurred for repair and maintenance work as per the instructions of the Respondent and requested for releasing some of the withheld amount for completion of the BC works at the earliest. 03.09.2022 Claimant Respondent Requested for making the payment against the bill submitted by the AE as per the directions of the Respondent. 05.09.2022 Claimant Respondent Attached the photographs of WMM work under progress at Hilly Chainage of the road. 10.09.2022 Claimant Respondent Informed that due to heavy rainfall and for Karma Jayanti, the work has been stopped at the site. 20.09.2022 Claimant Respondent Informed about the discussion held during the meeting under CE and requested to release pending dues for achieving the pace required for completion of the work. 28.09.2022 Claimant Respondent Informed about the unnatural deductions made by the authorities while making payments, requested to release further payments and to grant time extension till 31st December 2022 as per Clause 10.5(i) of the contract agreement and to approve the drawings and designs submitted within 15 days (about 2 weeks) from receiving of the letter. 10.10.2022 Claimant Respondent Submitted a cure period notice as per Clause-23 for curing of the defaults as no proper action had been taken by the respondent for approval of extension of time, payment of pending dues and approval of drawings. Also, mentioned that if the authorities do not cure the faults within 15 days of receiving the notice, then the Claimant shall terminate the contract agreement. 04.11.2022 Claimant Respondent Submitted the notice of termination of the contract owing to the defaults on the part of the respondents. 04.11.2022 Respondent Claimant Submitted a notice regarding the intention to terminate the contract as per Clause 23.1.2 of the Contract agreement. 14.11.2022 Claimant Respondent Informed that the termination of the contract agreement has been taken up due to the default of the authorities and that the termination process initiated by the Respondent is highly improper, rather it does not have any contractual and legal backing. 1