No. 01.12.2015 Respondent Claimant Intimated about the acceptance of the bid amount of Rs. 68,94,00,000/-, made by the Claimant. Requested to sign and return the duplicate copy of the LOA acknowledgement of the same within seven days receiving of the said letter. 23.12.2015 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing of the mobilization advance of 10%. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for st drawing 1 installment of the mobilization advance. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for drawing 2nd installment of the mobilization advance. 13.01.2016 Claimant Respondent Requested permission of the Respondent for submission of the bank guarantee for rd drawing 3 installment of the mobilization advance. 23.01.2016 Respondent Claimant Requested to meet the obligations and responsibilities that must bear by the Claimant as per Clause-10.1.1(c) and (d) of the contract agreement. 17.02.2016 Claimant Respondent Submitted the details of the consulting engineer as design consultant for preparation of the project report for the said project.
29.02.2016 Claimant Respondent Requested to provide the
site plan/ Center line details to commence marking of the Center line at site.
09.03.2016 Claimant Respondent Claimant requested to follow
up with the Amin and instructed to complete site ROW within next 2 days from 7th of March 2016. 14.03.2016 Claimant Respondent Requested to arrange for providing ROW of remaining stretch in order to avoid delays in design and further idling charges. 15.03.2016 Claimant Respondent Requested to hand over the ROW as decided in meeting held in 02.02.2016. 15.03.2016 Claimant Respondent Claimant stated that he had not received any replied of the said letter. Hence, requested to submit the remaining ROW. 16.03.2016 Claimant Respondent Requested to release the payment of 1st mobilization advance. 16.03.2016 Claimant Respondent Requested to release the bank guarantee of Rs. 1,51,66,800.00 towards payment of 1st Installment of mobilization advance of Rs. 1,37,88,000.00 as early as possible. 16.03.2016 Claimant Respondent Informed about the issuance of the bank guarantee for nd payment of 2 installment of mobilization advance. 17.03.2016 Claimant Respondent Requested to provide the forest MOC of the proposed road and dispense the permission for cutting the trees coming on the road starch. 17.03.2016 Claimant Respondent Requested to provide police protection to our staff & machineries at site of the said work. 17.03.2016 Claimant Respondent Requested to remove the electric poles & other poles and to provide us the road free of encumbrance. 18.03.2016 Claimant Respondent Stated various points that needed compliance of the Respondent. 18.03.2016 Claimant Respondent Due to PLFI naxal group have killed four people engaged in the road construction therefore police protection is needed to carry out the work at site and requested to provide full protection needed of the said work. 21.03.2016 Claimant Respondent Requested to release the mobilization advance. 21.03.2016 Claimant Respondent Claimant notice that they were not allowed proceed with clearing and grubbing by local people. The following details of the plot where the structure is not being dismantled are given in the said letter. 31.03.2016 Claimant Respondent Requested NOC from the respondent for the inception of the work between the Chainage 4+300 to 4+500,that is needed for marking of the centerline. 25.04.2016 Claimant Respondent Submitted clarifications and updates on the issues and queries raised by the Respondent. 25.04.2016 Claimant Respondent Claimant requested to take necessary action to resolve the payment issue wherein claimant can get site free of encumbrances. 04.05.2016 TL Claimant Submitted a list of documents that are needed to be provided by the Claimant. 11.05.2016 Claimant Respondent Noticed regarding the work has been stopped due to various hindrances at site has been listed on the said letter and requested to take necessary action to resolve the payment issue, trees cutting permission from the concerned department. 17.05.2016 Claimant Respondent Claimant informed that the situation escalated in a violent manner. Requested to take immediate action. 19.05.2016 Claimant Respondent Claimant informed that the situation escalated in a violent manner. Requested to provide security of 24 hrs and do the need full. 19.05.2016 Claimant Respondent The Claimant was informed about the construction of a bypass around Gumla town connecting NH-23 and NH-78, as noted in reference to the meeting held, which is being followed in the said letter. 23.05.2016 Claimant Respondent Requested to grant the permission for stone blasting. 23.06.2016 Claimant Respondent Submitted the utilization certificate for mobilization advance along with other expenditures and requested to release the third installment of mobilization advance. 04.07.2016 Claimant AE Submitted drawings and design for minor bridge and culvert. 14.07.2016 TL Claimant Informed about correction that are require to be implemented by the Claimant in design and drawing of pavements. 25.07.2016 Respondent Claimant MOM held on 12.07.2016 & 15.07.2016 04.08.2016 Claimant Respondent Claimant intimated that due to hurdle of Rainy Seasons Crusher Plant would not be able to shift. Hence, requested that, it would be shift the same at the earliest. 09.08.2016 Respondent Claimant Informed that meeting held on 04.08.2016 at office of secretary. 17.08.2016 TL Claimant Requested to provide status of drawings and design of the culvert, one major bridge and six minor bridges. 18.08.2016 Claimant Respondent Noticed regarding the handing over of ROW on March 16, 2016 and stated that the referred letter, which was not refuted by the department and authority engineer, has been follows in the said letter. 19.08.2016 TL Claimant Submitted a list of structure for which design and drawings are to be submitted by the Claimant. 23.08.2016 Claimant Respondent Stated as for obnoxious calls from Mr. Pradhan, who is speaking to the claimant concerning stopping the work in a life-endangering manner and has threatened to harm Mr. Sanjay Agarwal and his family’s lives. Hence, it is requested that you register a complaint and do the needful. 21.09.2016 Claimant Respondent Requested that not to withdraw the forces. 22.09.2016 TL Claimant Stated concerning the Hydrology report of major and minor bridge and pavement design are being follows in the said letter. 29.09.2016 Claimant Respondent Submitted the utilization certificate for mobilization advance along with other expenditures and requested to release the third installment of mobilization advance. 24.10.2016 Claimant Respondent Requested to increase the protection at the site to stop there unauthorized personal from ordering to stop the work. 26.10.2016 Claimant Respondent Requested to process for forest clearance so that work can go unhindered to the locatition. 18.11.2016 Claimant Respondent Informed that due to farmer cultivated rice in the Claimant area it is getting difficult to proceed the further work hence, requested to take the necessary step for the same so that the work can be executed in those area. 26.11.2016 Claimant Respondent Requested to extend/prolong 4 days add up to the completion of the said project. 29.11.2016 TL Claimant Minutes of Meeting on dated 26.11.2016 22.12.2016 Claimant Respondent Noticed regarding the handing over of ROW on March 16, 2016 and stated that the referred letter, which was not refuted by the department . and authority engineer, has been follows in the said letter. 09.01.2017 TL Claimant Intimated that 2nd milestone seems to be failed against your commitment to highest Authority officers. 10.01.2017 Claimant Respondent Requested to get the land owner of the area paid earliest and remove the work hurdle shortly, and also time lost in such land acquisition should be amicably compensated in extra days. 13.01.2017 Claimant TL Requested to recommend and process the desired Fixation of Appointment Date from 02.02.2016 to 16.03.2016 ASAP. 16.01.2017 Claimant TL Noticed regarding the handing over of ROW on March 16, 2016 wherein fixation of appointment date in 16.03.2016 and stated that the referred letter, which was not refuted by the department . and authority engineer, has been follows in the said letter. 20.01.2017 Claimant Respondent Intimated that 1st and 2nd Mile stone in the period of (02.02.016 to 01.08.2016) & (02.08.2016 to 01.02.2017) respectively failed due to the non-availability of sufficient working days and the factors responsible have been elucidated in this letter. 25.02.2017 Claimant TL Intimated that 1st and 2nd Mile stone in the period of (02.02.016 to 01.08.2016) & (02.08.2016 to 01.02.2017) respectively failed due to the non-availability of sufficient working days and the factors responsible have been elucidated in this letter.` 01.03.2017 TL Claimant EE notice regarding reseind the work for poor progress. 20.03.2017 TL Claimant Stated on Time Extension for 1st and 2nd Milestone. Hence, requested to expedite the progress of work as per provision of contract agreement. 01.04.2017 Respondent Claimant Submitted the Project Performance Review and Cure Period Notice. 11.04.2017 Claimant Respondent Informed regarding the Naxal threatening. 12.04.2017 Claimant Respondent Submitted an application for extension of time under Clause-10.5 of the EPC agreement by providing all necessary details which caused delay in completion of the work. 12.04.2017 Claimant TL Submitted the Application for EOT under CL.10.5 of the EPC agreement. 24.04.2017 Claimant Respondent Informed about due to naxal bandi there is no work at site. 03.05.2017 TL Claimant Submitted the details of Chainage wise Hindrances at site on account of pending land acquisition. 08.05.2017 TL Claimant Requested concurrence of revised box culvert drawings for review. 09.05.2017 TL Claimant Informed regarding the EOT. 23.05.2017 Claimant Respondent Intimated that due to unavailable of land 10% of project work cost is hampered and requested to give the permission to accomplish the work. 05.06.2017 Claimant Respondent Stated regarding the compliance against intension to issue termination notice as per clause 23.1.2 of Article 23 of Contract Agreement. 04.07.2017 Claimant DG, MORTH Requested to allow Milestone extension of the said work. 05.07.2017 Claimant Respondent Requested to release the amount withheld from 1st and 2nd SPS on account of milestone. 08.07.2017 TL EE Requested for release of an amount hold in IPC 1st 2nd against failure of milestone-I & II. 12.07.2017 Claimant Respondent Informed the local villagers removed the pillars for which work has been unable to proceed. Requested to do the needful. 27.07.2017 TL Claimant Submitted the resource based programme for examine in detailed. Hence, requested to do the needful. 01.08.2017 TL Claimant Submitted comments against the submission of design and drawings of 5 (nos) minor bridges. 04.08.2017 TL Claimant Notice on failure of Milestone III and subsequent effects as per clause 10.3.2 under Article 10 of Contract Agreement. 04.08.2017 TL Claimant Submitted comments against the submission of design and drawings of 2 (nos) minor bridges. 14.09.2017 TL Respondent Requested to revoke intension to termination letter. 20.10.2017 Claimant AE Informed about resubmission of drawings and design at chainage 3+490, 5+050, 8+370, 10+507 and 11+650. 24.10.2017 TL Respondent Informed about the resources based work programme and progress reviewed against intention to issuance of Termination Notice as per Clause 23.1.2 of Article 23. 31.10.2017 Claimant TL Informed about the accomplishing 26.33% of financial progress till 31st October, 2017 against 20.18%. 01.11.2017 Claimant Respondent Requested permission for use of boulders after blasting of the rocks. 02.11.2017 Jharkhand State Respondent Not visible Clearly. forest Development Authority. 09.11.2017 Claimant Respondent Informed about achievement of Milestone-I and Milestone-II with the revised target set for July to Oct 2017. 17.11.2017 Claimant Respondent Requested to provide a final decision regarding the shifting of electrical poles. 06.12.2017 TL Respondent Submitted the status of the hindered land. 09.12.2017 TL Claimant Submitted monthly program for completion of the project and requested to expedite the progress of the work. 22.12.2017 Claimant Respondent Requested to entreat the electric department to carry out the assigned work, further requested to refund the DD of Rs. 1,25,903/-. 02.01.2018 TL Claimant Informed about a meeting that is to be held by AE on 6th January 2018 along with the agenda that is to be discussed in the same meeting. 09.01.2018 TL Claimant Informed about the slow progress of the work that may be the reason for non achievement of Milestone –III & IV in appropriate time. 05.02.2018 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the designated timeframe for Milestone-IV. 15.02.2018 TL Claimant Urged the Claimant to expedite the work progress. 08.03.2018 Respondent Claimant 13.03.2018 Claimant The Collector, Informed about the hindrances Gumla created by the Local Villagers due to the non-payment of the compensation for the land acquisition. 13.03.2018 Claimant SP, Gumla Requested to arrange proper security arrangements due to threats at the site. 17.03.2018 TL Claimant Requested to incorporate corrections made by the TL on the drawings and to submit the same for verification. 19.03.2018 Claimant SP, Gumla Informed about the hindrances created by the Local Villagers due to the non-payment of the compensation for the land acquisition. 26.04.2018 TL Respondent Submitted the review( facts and figures) of work progress for the perusal of the Respondent. 15.05.2018 Respondent Claimant Submitted the intention to terminate the contract under Clause-23.1.2 of Article 23 due to slow progress in work and failure to achieve Milestone- I,II,III & IV in a timely manner. 21.05.2018 TL Claimant Informed about the intention for termination of the contract under Clause-23.1.2 of Article 23 due to slow progress in work and failure to achieve Milestone- I,II,III & IV in a timely manner. 04.07.2018 TL Respondent Requested to revoke the intention for termination notice issued to the Claimant as per Clause-23.1.2 of Article-23. 06.07.2018 Claimant Respondent Requested for extension of time with rescheduling of milestone, by submitting proper reasons and arguments. 06.07.2018 Claimant Respondent Requested for time extension till 31st march 2019 and rescheduling milestone as per revised work programme. 13.07.2018 MoRTH Respondent Requested to comply with the decision taken by the Hon’ble Minister (RTH, S&WR, RD & GR) by end of the first week of September 2019. 23.07.2018 TL Claimant Informed about the acceptance of revision of plan and profile without any time extension. 24.07.2018 Respondent Claimant Informed about the withdrawal of the notice of termination of the contract. 24.07.2018 Respondent Claimant Informed regarding withdrawal for termination notice. 11.08.2018 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 13.08.2018 TL Respondent Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 13.09.2018 TL Claimant Informed about the slow progress of work as per re- revised resource based work programme. 04.10.2018 TL Claimant Requested to submit the EOT claim up to May 2018. 31.10.2018 Claimant TL Submitted the day wise calculation sheet for EOT. 20.11.2018 TL Respondent Informed about the proposal of EOT submitted by the Claimant. 12.01.2019 TL Claimant Informed about the potential action that may be taken under clause-10.3.2 due to failure to meet the scheduled completion date. 15.01.2019 Claimant TL Informed about the resubmission of drawings for minor and major bridge as per plan and profile of the road. 19.01.2019 TL Claimant Informed about the slow progress of the work and requested to expedite the work progress. 23.01.2019 TL Claimant Informed about the topics discussed in the meeting under the chairmanship of ADG on 19.01.2019. 23.01.2019 TL Claimant Requested for submission of drawings for minor and major bridge as per plan and profile of the road. 29.01.2019 TL Claimant Informed about the topics discussed in the meeting under the chairmanship of ADG on 19.01.2019. 05.02.2019 TL Claimant Informed about the slow progress of the work. 05.02.2019 TL Claimant Submitted their comments on revised design and drawings for highway, major and minor bridge. 04.04.2019 TL Claimant Submitted progress review report up to 31.03.2019 in view of the meeting held by DG (RD) and SS in Delhi in 25.03.2019. 09.04.2019 TL Claimant Submitted progress review report up to 07.04.2019 in view of the meeting held by DG (RD) and SS in Delhi in 25.03.2019. 30.04.2019 Claimant Respondent Requested to withdraw bank guarantee invocation letter till final decision of higher authority. 16.05.2019 Claimant Respondent Submitted the list of available machineries, material and Man power required for execution of the work. 17.05.2019 TL Claimant Requested to submit the preparedness to complete the bituminous work by June 2019 and all balance work in all respect by Dec. 2019. 20.05.2019 TL Respondent Requested to submit the preparedness of the claimant for completion of work by June-2019. 01.07.2019 TL Respondent Submitted the valuation of the Unpaid works as per Clause- 23.5 of Article-23 of Contractor Agreement & valuation of balance work for Tender. 05.09.2019 TL Respondent Submitted the valuation of unpaid work after termination as per Clause-23.5. 10.09.2019 Claimant DG, MoRTH Requested the Ministry to take action regarding to the termination of the contract further requested that required directions, to be given to relevant authority for the withdrawal of the termination order. 18.09.2019 TL Respondent Submitted the revaluation of the Unpaid works as per Clause-23.5 of Article -23 of the contract agreement. 05.12.2019 Claimant DG, MoRTH Submitted the Judgment of the High Court relating to revocation of the termination of the contract. 13.01.2020 Claimant TL Requested to make the payment for the said work. 17.01.2020 Claimant Respondent Requested to restore the police protection in the work site. 17.01.2020 Claimant Respondent Requested to release the amount of BG for smooth process of work. 17.01.2020 Claimant Respondent Submitted the revised work program of the said work. Hence, requested to release the LD & Withheld for Milestone along with running bill. 18.01.2020 TL Claimant Informed about critical issues raised by the Respondent regarding foundation level quantity of concrete, design and drawings. Not visible Claimant TL Submitted two sets of plan and profile drawings for review. 22.01.2020 Claimant Respondent Notice regarding the said project was terminated on 24.04.2019 and police protection frim site was removed wherein EE had REVOKED the said tender on 10.01.2020. hence, requested to provide the protection for the smooth running of project. 23.01.2020 TL Claimant Submitted the pending design & drawings for the said work. 23.01.2020 TL Claimant Stated concerning the list of calibrated plants & equipment’s available or yet to be procured for batter QA & QC. 23.01.2020 TL Claimant Submitted the MTC & third party test report of material. 04.02.2020 TL Claimant Directed to resume the work immediately. 11.02.2020 Claimant TL Requested to send the proposal to authorities immediately so that EOT could be sanctioned. 11.02.2020 TL Claimant Instructed that to start the mobilization at site immediately. 14.02.2020 TL Claimant Submitted the key personnel needs to be deployed at site as per provision of contract agreement & good industry. 18.02.2020 TL Claimant Submitted the site inspection report dtd. 17.02.2020 as per Clause 4.7 of Section-6 Terms of Reference of Contract Agreement. 18.02.2020 TL Respondent Informed about the supplementary agreement between the Respondent and Claimant which is regarded as an integral part of the main contract agreement and in view of such supplementary agreement work program has also been approved up to 31.03.2021. And requested for the approval of EOT up to 31.03.2021 with shifting of Milestones in view of the supplementary agreement. 18.02.2020 TL Claimant Requested that material must be tested in third party laboratory and submitted the test results to this office at the earliest. 18.02.2020 TL Respondent Informed regarding the EOT up to 31.03.2021, and shifting of milestone, which is recommended as under the said letter without any extra financial implication to the Authority for the completion of the work. 21.02.2020 Claimant Respondent Resubmitted of GST Bill No.1 wherein releasing the same amount of Rs.59,85,966.00/- at the earliest. 21.02.2020 Claimant AE Informed about critical issues raised by the Respondent regarding foundation level quantity of concrete, design and drawings. 28.02.2020 TL Claimant Submitted various reasons for the rejection of deck slab caste for minor bridge at ch.11+650 from 24th to 26th Feb 2020. 04.03.2020 TL Claimant Informed about critical issues raised by the Respondent regarding foundation level quantity of concrete, design and drawings. 06.03.2020 Claimant Respondent Requested to see the bill which was released at the earliest. 18.03.2020 TL Claimant Submitted the return of incomplete GST Bill. 18.03.2020 TL Claimant Informed regarding the pending payment of the aid work. 21.03.2020 Claimant TL Stated that due to out break of Coronavirus, unprecedented rainfall and non-availability of funds work could not be proceed appropriately. Hence, requested to release the funds and do the needful at the earliest. 25.03.2020 Claimant Respondent Submitted the GST Bill No.3 25.03.2020 Claimant Respondent Intimated of force majeure. 26.03.2020 Claimant Respondent Resubmitted the GST Bill No.1. 02.04.2020 Claimant Respondent Requested to release of pending bill in SPC No.8 of Rs.4,27,89,823. 04.04.2020 Claimant Respondent Requested to resolve the persisting statement by allowing EOT and release all the payment of the said work. 06.04.2020 TL Claimant Resubmitted of GST Bill No.1 and requested to submit complete bill of the said project. 07.04.2020 TL Reg. Officer Requested to release the pending bill in SPS-8 of Rs .4,27,89,823/- 08.04.2020 Claimant Respondent Requested to approve the EOT and to make the payments against the pending dues for proper maintenance of the cash flow. 08.04.2020 TL Respondent Requested to bestow approval for EOT at the earliest. 13.04.2020 Claimant Respondent Requested to grant approval for EOT at the earliest. 16.04.2020 Claimant Respondent Submitted of Bill of Shifting of 33KV, HKV and LT Electrical line wherein requested to release the bill of the same amounting to Rs.77,99,539.22/-. 17.04.2020 Claimant DG & SS Stated regarding for releasing the blocked-up funds amounting to Rs.4,27,89,823/- & EOT 18.04.2020 TL Respondent Requested for release of Electrical utility shifting bill at the earliest. 20.04.2020 Claimant TL Requested of rescheduling the Schedule-H and the stage payment for Dense Bituminous Macadam & Bituminous Concrete quantities of the said work. 20.04.2020 Claimant AE Submitted of price variation of the said work. 25.04.2020 Claimant TL Informed about the EOT and Requested to release the mentioned amount at the earliest. 30.04.2020 TL Claimant Submitted of Escalation Bill of the said work. 05.05.2020 TL Claimant Informed about the failure of the contractor in achieving Milestone-IV and also stated about subsequent effect of such failure as per Clause-10.3.2 06.05.2020 Claimant Respondent Requested to find the price variation bill with CPI, WPI, Diesel Price etc. 07.05.2020 Claimant TL Submitted various reasons that contributed toward the delay in achievement in Milestone- IV, further requested to the Respondent to grant time extension till 30.06.2020. 07.05.2020 Claimant Dist. Collector, Requested for movement pass Gumla for certain employees for continuance of the work. 08.05.2020 TL Claimant Requested to submit fresh BG for release of enchased performance security amount. 11.05.2020 TL Claimant Submitted their reply towards the letter of the Claimant by responding to each and every statement made by the Claimant. 14.05.2020 Claimant TL Requested to release the amount of Rs. 2,17,93,658/- and extension of time to 31.08.2021 for completion of the Milestone. 26.05.2020 TL Claimant Requested to mobilize referred personnel at the site. 27.05.2020 Claimant TL Requested to change the payment schedule and asked for the payment for the completed work which were kept unpaid, till May 2020. 05.06.2020 Claimant SP Requested for deployment of 10 guards immediately at the camp site, as the work is getting carried at Naxal area. 05.06.2020 TL Claimant Informed about the ineligibility of the Claimant for receiving of partial payment as per Point-5 of Rule-171 of GFR,2017. 08.06.2020 Claimant TL Requested to release Rs. 1,74,35,872.26/- withheld in form of Security Deposit. 11.06.2020 TL Respondent Requested for partial release of Retention money with necessary statutory deductions if necessary. 11.06.2020 Claimant DG, MoRTH Requested to pass appropriate order to CE, for release of EOT as per the fresh application of the Claimant. 13.06.2020 Claimant AE, Feedback Requested to release the funds Infra for execution of the work. 16.06.2020 TL Claimant Submitted their reply towards the letter of the Claimant by responding to each and every statement made by the Claimant. 22.06.2020 TL Claimant Requested to submit the interim EOT for the project with work programme and revised milestones. 26.06.2020 Claimant TL Requested to grant interim EOT at least for 3 months as the earlier approval of EOT will accelerate the progress of work. 27.06.2020 TL Claimant Informed about the shifting of milestones as per the recommended time extension. 29.06.2020 TL Claimant Informed about non- submission of design and drawing of form work for review as per MoRTH Clause 1503.1 and 1503.2. 08.08.2020 Claimant AE Informed regarding the EOT of the said work. 22.09.2020 Claimant Respondent Informed regarding that after getting such persistence, AE wasn’t convinced to release the fund. Hence, requested to take serious action in this regards. 29.09.2020 TL Respondent Requested for EOT against force majeure event due to COVID-19. 05.10.2020 TL Claimant Informed regarding the resume of work. 22.10.2020 TL Claimant Submitted the GST Bill No-2 of the said work. 29.10.2020 Claimant Respondent Requested to provide security for staff and machineries. 06.11.2020 TL Claimant Notice regarding on slow progress of work as a result Milestone IV which is going to be failed and subsequent effects as per Clause 10.3.2 of Article 10. 06.11.2020 TL Claimant Informed regarding the resume of the work at the earliest. 11.11.2020 Claimant Respondent Requested to extend the validity of DO for upliftment of Bitumen as the same as expired. 11.11.2020 TL Respondent Submitted the month wise physical & financial progress for last six month. 28.11.2020 Claimant TL Notice regarding on slow progress of work as a result Milestone IV which is going to be failed and subsequent effects as per Clause 10.3.2 of Article 10. 03.12.2020 TL Claimant Informed about the points discussed during the site inspection of CE dated 02.12.2020. 21.12.2020 Claimant AE Enclosed is the said work of Stage Payment Statement 11 and requested to release the amount of Rs. 2,02,78,691/-. 22.12.2020 Claimant Respondent Requested to issue DO for upliftment of Emulsion from Hindustan Colas for construction of by pass around Gumla town. 24.12.2020 Claimant Respondent Submitted the Price Variation of escalation bill along with all relevant documents of the said work and requested to release the amount of Rs.98,18,730/-. 14.01.2021 TL Claimant Requested for relies of Interim Payment Statement No.11. 18.01.2021 TL Claimant Requested to submit the revised formation levels (FRL) and its has been stated that extra time extension and financial condition shall be considered in this account. 25.01.2021 Claimant TL Informed regarding the Non- availability of VG-40 at HPCL. Requested to do the needful. 28.01.2021 Claimant Respondent Requested to release the mentioned payment at the earliest. 28.01.2021 Claimant Respondent Requested to give the permission for VG-30 grade Bitumen, so that the work could be completed within the stipulated time period. 29.01.2021 TL Claimant Requested to submit the source details and post approval of the source. 01.02.2021 Claimant TL Requested to give the permission for VG-30 grade Bitumen, so that the work could be completed within the stipulated time period. 12.02.2021 Claimant AE Intimated that due to delay in releasing the payment the work is being obstructed. Hence requested to look in to the matter at the earliest. 12.02.2021 Claimant AE Stated regarding the status of compliance of CE MOM held on 28.01.2021 and requested to release the payment at the earliest. 12.02.2021 Claimant AE Requested to arrange security camp to protect staffs & machineries from any unwanted incidence. 16.02.2021 Claimant TL Informed regarding to conduct the necessary tests at Gumla town. 20.02.2021 Claimant Respondent Intimated that due to delay in releasing the payment the work is being obstructed. Hence requested to look in to the matter at the earliest. 22.02.2021 Claimant Respondent Intimated that due to such types of hindrances work was not being able to maintain the progress hence, requested to release the payment immediately. 24.02.2021 Claimant TL Informed that, due to the non- availability of VG-40 at HPCL, the said work has been unable to proceed further. Hence, it was requested to grant permission for the use of VG- 40-grade bitumen for the work. 25.02.2021 TL Claimant Stated regarding for requirement of fund or delay in payment of the said work. 26.02.2021 TL Respondent Informed regarding the pending payment of RA Bill No.13 which is recommended as RA Bill No.12 of the said work. 26.02.2021 Claimant AE Enclosed Stage Payment Statement and requested to releasing the amount of Rs.83,16,444/- of the said work. 28.02.2021 Claimant AE Submitted the Escalation Bill and requested to release the amount of Rs. 63,77,443/-. 01.03.2021 TL Claimant Informed regarding to expedite the progress of work from 1st Feb to 28th Feb, 2021 04.03.2021 Claimant Respondent Requested to release the payment at the earliest. 09.03.2021 Claimant Respondent Intimated regarding the facts of delay and default in completion of the project upon resolution of which work execution would progress and called upon to take a decision within 15 days. 23.03.2021 TL Respondent Requested to process the pending aforesaid payment at the earliest. 24.03.2021 Claimant AE Requested for EOT up to 31.03.2021. 02.05.2022 TL Claimant Submitted the revised work programme and resubmit the same to expedite the process for approval of EOT. 05.05.2021 Claimant AE Enclosed Stage Payment Statement – 11 and Submitted the Bill No-SPS-15. Hence, requested to release the same amount of Rs.87,28,368/- at the earliest. 12.05.2021 TL Claimant Submitted the compliance report of the said letter and requested to release the payment against minor bridge. 13.05.2021 TL Claimant Instructed to submit the compliance report of the said letter and requested to release the payment against the major bridge. 09.06.2021 Claimant Respondent Informed about the opening of escrow account in Punjab National Bank for release of performance security. 10.06.2021 TL Respondent Requested to release the price variation bill no.-4, amounting to Rs. 66,86,576/-. 10.06.2021 TL Respondent Requested to make payment against IPC-15 amounting to Rs. 1,50,16,755/-. 10.06.2021 Claimant AE Requested to grant permission for the forest land clearance of the said work. 14.06.2021 TL Claimant Informed regarding the concur of General Arrangement Drawing for PCC Wing Wall and requested to do the needful. 15.06.2021 TL AE Requested to process the payments towards the tests conducted on structures. 21.06.2021 TL Claimant Intimated regarding the site inspection report of the said work. 22.06.2021 TL Claimant Requested to submit all the necessary documents for review of design and drawings. 22.06.2021 TL Claimant Requested to submit the resource based work th programme by 30 September 2021 and informed about the approval of EOT application submitted by the Claimant. 25.06.2021 Claimant Respondent Requested to verify that no legal proceeding exists in the project. 30.06.2021 TL Claimant 13.08.2021 Claimant Regional Officer, Submitted CA certificate for MoRTH the reference of RPO. 14.08.2021 Claimant AE Submitted reasons for delays and requested for time extension along with rescheduled Milestone-V as per revised work program. 23.08.2021 TL Claimant Requested for the payment of GST bill, Escalation bill and running bill. 30.08.2021 TL Respondent Submitted a detailed layout of the meeting held at Ranchi on 26th August 2021. 18.09.2021 Claimant AE Requested to release the price variation bill and GST bill. 18.09.2021 Claimant AE Requested for payment of legitimate dues pending against Claimant. 22.09.2021 TL Respondent Informed about the execution of the 6 minor bridges according to the approved designs and drawings. 22.09.2021 TL Claimant Intimated that after a numerous stipulation of communication still embedment of founding layer is not sufficient considering weathered rock. Hence requested to go through the matter of the said letter. 23.09.2021 TL Claimant Provided a tabular depiction of the statements of Contractor and AE. 29.09.2021 TL Claimant Intimated regarding the Major Bridge foundation and substructure design and drawings is review and concurred by the authority. 04.10.2021 Claimant Respondent Submitted the details of the availability of the machineries at the site along with material stock. 07.10.2021 TL Claimant Submitted a list of work which according to the Team Leader, needed to get executed immediately. 12.10.2021 TL Claimant Requested to work as per the standards and specifications set forth in contract agreement and quality control and quality assurance plan. 13.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 23.10.2021 TL Claimant Provided a detailed description about the financial and physical progress of work and expressed discontentment regarding the same. 23.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 29.10.2021 Claimant AE Requested to forward the time extension proposal to higher authorities for sanction in the interest of the project. 29.10.2021 TL Claimant Requested to submit resource based work program. 29.10.2021 TL Claimant Requested to submit the compliance report as per the following points on the said letter immediately. 29.10.2021 TL Claimant Requested for the submission of resource based work programme for reviewing of the EOT proposal submitted by the Claimant. 06.11.2021 TL Claimant Requested to submit resource based work program. 12.10.2021 TL Claimant Informed that no productive work at the site can be taken up till monsoon. 12.11.2021 Claimant Respondent Requested written confirmation for construction of the Toll Plaza. 16.11.2021 TL Claimant Requested to submit required compliances/details relating to the points mentioned by the Team Leader along with necessary details about drawings/designs, manpower etc. 18.11.2021 Claimant AE Submitted EOT letter with other supporting documents along with Resource based work program. 16.12.2021 TL Claimant Requested to submit the roadside furniture, traffic control devices, and road safety details review and concurred at the earliest. 18.12.2021 Claimant Respondent Submitted their response against the cure period notice of the Respondent and requested to withdraw/expunge the same notice for completion of the work. Further mentioned that if the cure period notice is not withdrawn by the Respondent, the Respondent shall treat this letter as cure period notice of the Claimant by release of the payment and pending dues. 24.12.2021 TL Claimant Submitted detailed progress report about the financial and physical progress of work. 27.12.2021 TL Claimant Submitted the remarks of the AE against the cure period notice of the contractor. 14.01.2022 Claimant AE Requested for de-scoping of Toll Plaza from the scope of the work. 14.01.2022 Claimant AE Informed that the work at Ch 11+650 have been executed as per drawing and design approved by the Authority. 14.01.2022 Claimant AE Requested to De-Scope the Toll Plaza from the scope of the work. 29.01.2022 Claimant AE Requested to release the pending payment against the execution of minor bridge work. 16.02.2022 Claimant Respondent Requested to release the withheld amount along with GST Bill. 16.02.2022 Claimant Respondent Requested to sanction the time extension pending at the office of the Respondent. 20.02.2022 Claimant AE Requested to release the pending funds for smooth execution of the work. 21.02.2022 TL Claimant Submitted the roadside furniture, traffic control devices, and road safety details with supper imposed on a Google sheet of P&P drawings review and concurred at the earliest. 24.02.2022 TL Claimant Requested to submit the revised work program for EOT recommendation. 24.02.2022 Claimant Respondent Submitted reasons for delay in execution of the work, requested for time extension and rescheduling of Milestone- V as per revised work program. 25.02.2022 TL Claimant Provided a tabular depiction of the statements of Contractor and AE, regarding release of the funds. 25.02.2022 TL Claimant Informed about the excavation for construction of Major Junction work @ Ch. 12+680 on 4th Feb 2022. 25.02.2022 Claimant Respondent Requested to release the pending funds at an earliest for smooth working at the site. 02.03.2022 Claimant AE Requested to release the funds and other withheld amount against minor bridge work and bitumen work. 07.03.2022 Claimant Respondent Requested for sanction of EOT for completion of balance work. 07.03.2022 Claimant Respondent Requested to release the withheld payment of the said work. 11.03.2022 Claimant AE Submitted the road signage plan. 14.03.2022 Claimant AE Informed regarding opened the road for traffic by constructing a diversion near the major bridge. 14.03.2022 Claimant AE Requested to release of withheld payment at the earliest. 14.03.2022 Claimant Respondent Stated that due to unavailability of fund bill was not being able to paid. Hence, requested to look in to the matter. 14.03.2022 Claimant Respondent Requested to purchase the aggregate for the said work. 14.03.2022 TL Claimant Requested to release the pending dues. 14.03.2022 TL Claimant Requested to submit the GST Bill which is pending for payment. 15.03.2022 TL Claimant Informed regarding the unavailability of Aggregate of the said work. 17.03.2022 Claimant AE Submitted the road signage plan. 21.03.2022 Claimant Dist. Collector Requested to release the payment at the earliest and the following details which has been mentioned in the said letter. 28.03.2022 TL Claimant Stated that the company didn’t give any financial support to the site. Hence, it was requested to release the pending dues for the said work. 28.03.2022 TL Claimant Requested to release the Performance Security Deposit at the earliest. 28.03.2022 TL Claimant Submitted the roadside furniture, traffic control devices, and road safety details with supper imposed on a Google sheet of P&P drawings review and concurred at the earliest. 30.03.2022 Claimant AE Informed regarding the various reasons which have affected and delayed the work in the said letter. Hence, requested to approved the EOT at the earliest. 02.04.2020 Claimant Respondent Informed about the site requirement metal beam crash Barrier needs to be provided at the following chainnage and requested to issue the change of scope notice under clause 13.2. 06.04.2022 Claimant Respondent Intimated due to international pressure and the delay in sanctioning the EOT, the huge fund has been blocked, hence the request to recommend the EOT at the earliest. 07.04.2022 TL Claimant Submitted the Change of Scope proposal, wherein the metal beam crusher is to be provided and fixed at the high embankment. Hence, it was requested to do the needful and execute the work at the earliest. 07.04.2022 Claimant Respondent Requested to release the Security Deposit amounting to Rs.1,40,36,315/-. 13.04.2022 Claimant Respondent Requested to approve the EOT so that bills could be processed to complete the work. 13.04.2022 Claimant Respondent Requested to grant the permission to do DBM on the site. 14.04.2022 Claimant Respondent Requested to release the retention money at the earliest. 14.04.2022 Claimant Respondent Requested to make an interim payment of 90% of the price adjustment ill as per the circular. 14.04.2022 Claimant Respondent Requested to extension of relaxation in schedule H/G which is granted to improve the liquidity of funds. 16.04.2022 Claimant Respondent Requested to release the retention money of Rs.1,40,36,315/- of the said work. 16.04.2022 TL Claimant Submitted the road side furniture and traffic control devices & road safety details review and concurred at the earliest. 18.04.2022 Claimant AE Requested to release the Security deposit of Rs.1,40,36,315/-. 19.04.2022 TL Claimant Informed that the work which is made at Ch:2+850 to 2+900 is not good in case of rock blasting and removing. Hence, requested to complete the work at the earliest. 20.04.2022 Claimant Collector, Gumla Intimated that to complete the bituminous work with in stipulated time period. 21.04.2022 TL Claimant Requested to arrange the fund for the requirement of project completion in the due time period for the said work. 22.04.2022 Claimant Respondent Requested to recommend the EOT for the said work. 23.04.2022 Claimant Respondent Informed that the work program can be achieved on timely payment of RA bill and price escalation by the department. 23.04.2022 Claimant Respondent Requested to release the retention money amounting to Rs.1,33,42,364/- of the said work. 07.05.2022 Claimant Respondent Requested to release the retention money of Rs.1,33,00,000/- of the said work. 09.05.2022 TL Respondent Clarification sought by SE is as follows:
a. The justification for the
delay in working is duly supported by documents. b. Stated regarding the opinion on the cause of the delay.
Submitted the work
programme. 09.05.2022 Claimant Respondent Requested to take note of the following letter that to release the retention money as per letter dated.11.04.2022. 12.05.2022 Claimant AE Submitted the compliance report of the work. 25.05.2022 Claimant Respondent Requested to release Rs. 5,56,72,273/- withheld against different heads so that the remaining works could be completed without any further delay. 14.06.2022 TL Claimant Submitted the compliance report to RO for observation of the EOT proposal of the Claimant. 15.06.2022 TL Claimant Informed about the site inspection program that is to be done by Regional Office Ranchi Officials. 15.06.2022 Claimant Respondent Submitted reasons for delay in execution of the work, requested for time extension till 30th October 2022 further requested for rescheduling of Milestone-V as per revised work program. 01.07.2022 Claimant Respondent Requested to make the payment of pending dues. 14.07.2022 Claimant AE Requested for the approval of the positive and negative scope of the work. 19.07.2022 TL Claimant Informed that authority may take any action against the Claimant due to lack of progress in executing of the work at the site. 19.07.2022 TL Claimant Requested for the approval of the positive and negative scope of the work. 23.07.2022 Claimant AE Requested to release the bill for the work done which is very much necessary for increasing of the liquidity of the project. 29.07.2022 Claimant Respondent Submitted the photographs of the maintenance work as per the instructions of the AE. 05.08.2022 Claimant Respondent Requested for further directions of the CE against the recommendation of the termination of the project. 10.08.2022 Claimant Respondent Submitted various points that needed through reconsideration before foreclosure/termination of the contract. 17.08.2021 Claimant AE Submitted the design and drawings for the Bridges at Ch. 0+140Km and Ch 7+190 Km. 22.08.2022 Claimant Respondent Submitted photographs to show the work progress at the site. 27.08.2022 Respondent Claimant Informed that the erroneous GST bill submitted by the Claimant would be rectified by an expert to be appointed by the RO, MoRTH , for early payment of such bills. 27.08.2022 Claimant DG, MoRTH Submitted the details of the GST Bills, Price variation Bills which are withheld by the Authorities against each RA bill and requested for making the payment of all such withheld. amounts for proper and smooth functioning of the work. 28.08.2022 Claimant Respondent Informed about the cost incurred for repair and maintenance work as per the instructions of the Respondent and requested for releasing some of the withheld amount for completion of the BC works at the earliest. 03.09.2022 Claimant Respondent Requested for making the payment against the bill submitted by the AE as per the directions of the Respondent. 05.09.2022 Claimant Respondent Attached the photographs of WMM work under progress at Hilly Chainage of the road. 10.09.2022 Claimant Respondent Informed that due to heavy rainfall and for Karma Jayanti, the work has been stopped at the site. 20.09.2022 Claimant Respondent Informed about the discussion held during the meeting under CE and requested to release pending dues for achieving the pace required for completion of the work. 28.09.2022 Claimant Respondent Informed about the unnatural deductions made by the authorities while making payments, requested to release further payments and to grant time extension till 31st December 2022 as per Clause 10.5(i) of the contract agreement and to approve the drawings and designs submitted within 15 days (about 2 weeks) from receiving of the letter. 10.10.2022 Claimant Respondent Submitted a cure period notice as per Clause-23 for curing of the defaults as no proper action had been taken by the respondent for approval of extension of time, payment of pending dues and approval of drawings. Also, mentioned that if the authorities do not cure the faults within 15 days of receiving the notice, then the Claimant shall terminate the contract agreement. 04.11.2022 Claimant Respondent Submitted the notice of termination of the contract owing to the defaults on the part of the respondents. 04.11.2022 Respondent Claimant Submitted a notice regarding the intention to terminate the contract as per Clause 23.1.2 of the Contract agreement. 14.11.2022 Claimant Respondent Informed that the termination of the contract agreement has been taken up due to the default of the authorities and that the termination process initiated by the Respondent is highly improper, rather it does not have any contractual and legal backing.