SL NO.

DATE FROM TO PARTICULAR


29.02.201 Claimant Respondent Requested to provide the
6 site plan/ Center line
details to commence
marking of the Center
line at site.
09.03.201 Claimant Respondent Claimant requested to
6 follow up with the Amin
and instructed to
complete site ROW
within next 2 days from
7th of March 2016.
14.03.201 Claimant Respondent Requested to arrange for
6 providing ROW of
remaining stretch in
order to avoid delays in
design and further idling
charges.
15.03.201 Claimant Respondent Claimant stated that he
6 had not received any
replied of the said letter.
Hence, requested to
submit the remaining
ROW.
17.03.201 Claimant Respondent Requested to provide the
6 forest MOC of the
proposed road and
dispense the permission
for cutting the trees
coming on the road
starch.
17.03.201 Claimant Respondent Requested to provide
6 police protection to our
staff & machineries at
site of the said work.
17.03.201 Claimant Respondent Requested to remove the
6 electric poles & other
poles and to provide us
the road free of
encumbrance.
18.03.201 Claimant Respondent Due to PLFI naxal group
6 have killed four people
engaged in the road
construction therefore
police protection is
needed to carry out the
work at site and
requested to provide full
protection needed of the
said work.
21.03.201 Claimant Respondent Claimant notice that they
6 were not allowed
proceed with clearing
and grubbing by local
people. The following
details of the plot where
the structure is not being
dismantled are given in
the said letter.
25.04.201 Claimant Respondent Claimant requested to
6 take necessary action to
resolve the payment
issue wherein claimant
can get site free of
encumbrances.
04.05.201 TL Claimant Submitted a list of
6 documents that are
needed to be provided
by the Claimant.
11.05.201 Claimant Respondent Noticed regarding the
6 work has been stopped
due to various
hindrances at site has
been listed on the said
letter and requested to
take necessary action to
resolve the payment
issue, trees cutting
permission from the
concerned department.
17.05.201 Claimant Respondent Claimant informed that
6 the situation escalated in
a violent manner.
Requested to take
immediate action.
19.05.201 Claimant Respondent Claimant informed that
6 the situation escalated in
a violent manner.
Requested to provide
security of 24 hrs and do
the need full.
19.05.201 Claimant Respondent The Claimant was
6 informed about the
construction of a bypass
around Gumla town
connecting NH-23 and
NH-78, as noted in
reference to the meeting
held, which is being
followed in the said
letter.
23.05.201 Claimant Respondent Requested to grant the
6 permission for stone
blasting.
04.07.201 Claimant AE Submitted drawings and
6 design for minor bridge
and culvert.
14.07.201 TL Claimant Informed about
6 correction that are
require to be
implemented by the
Claimant in design and
drawing of pavements.
25.07.201 Respondent Claimant MOM held on 12.07.2016
6 & 15.07.2016
04.08.201 Claimant Respondent Claimant intimated that
6 due to hurdle of Rainy
Seasons Crusher Plant
would not be able to
shift. Hence, requested
that, it would be shift the
same at the earliest.
09.08.201 Respondent Claimant Informed that meeting
6 held on 04.08.2016 at
office of secretary.
17.08.201 TL Claimant Requested to provide
6 status of drawings and
design of the culvert, one
major bridge and six
minor bridges.
18.08.201 Claimant Respondent Noticed regarding the
6 handing over of ROW on
March 16, 2016 and
stated that the referred
letter, which was not
refuted by the
department and
authority engineer, has
been follows in the said
letter.
19.08.201 TL Claimant Submitted a list of
6 structure for which
design and drawings are
to be submitted by the
Claimant.
23.08.201 Claimant Respondent Stated as for obnoxious
6 calls from Mr. Pradhan,
who is speaking to the
claimant concerning
stopping the work in a
life-endangering manner
and has threatened to
harm Mr. Sanjay
Agarwal and his family’s
lives. Hence, it is
requested that you
register a complaint and
do the needful.
21.09.201 Claimant Respondent Requested that not to
6 withdraw the forces.
22.09.201 TL Claimant Stated concerning the
6 Hydrology report of
major and minor bridge
and pavement design are
being follows in the said
letter.
24.10.201 Claimant Respondent Requested to increase the
6 protection at the site to
stop there unauthorized
personal from ordering
to stop the work.
26.10.201 Claimant Respondent Requested to process for
6 forest clearance so that
work can go unhindered
to the locatition.
18.11.201 Claimant Respondent Informed that due to
6 farmer cultivated rice in
the Claimant area it is
getting difficult to
proceed the further work
hence, requested to take
the necessary step for the
same so that the work
can be executed in those
area.
26.11.201 Claimant Respondent Requested to
6 extend/prolong 4 days
add up to the completion
of the said project.
29.11.201 TL Claimant Minutes of Meeting on
6 dated 26.11.2016
22.12.201 Claimant Respondent Noticed regarding the
6 handing over of ROW on
March 16, 2016 and
stated that the referred
letter, which was not
refuted by the
department . and
authority engineer, has
been follows in the said
letter.
09.01.201 TL Claimant Intimated that 2nd
7 milestone seems to be
failed against your
commitment to highest
Authority officers.
10.01.201 Claimant Respondent Requested to get the land
7 owner of the area paid
earliest and remove the
work hurdle shortly, and
also time lost in such
land acquisition should
be amicably
compensated in extra
days.
13.01.201 Claimant TL Requested to recommend
7 and process the desired
Fixation of Appointment
Date from 02.02.2016 to
16.03.2016 ASAP.
16.01.201 Claimant TL Noticed regarding the
7 handing over of ROW on
March 16, 2016 wherein
fixation of appointment
date in 16.03.2016 and
stated that the referred
letter, which was not
refuted by the
department . and
authority engineer, has
been follows in the said
letter.
20.01.201 Claimant Respondent Intimated that 1st and 2nd
7 Mile stone in the period
of (02.02.016 to
01.08.2016) & (02.08.2016
to 01.02.2017)
respectively failed due to
the non-availability of
sufficient working days
and the factors
responsible have been
elucidated in this letter.
25.02.201 Claimant TL Intimated that 1st and 2nd
7 Mile stone in the period
of (02.02.016 to
01.08.2016) & (02.08.2016
to 01.02.2017)
respectively failed due to
the non-availability of
sufficient working days
and the factors
responsible have been
elucidated in this letter.`
01.03.201 TL Claimant EE notice regarding
7 reseind the work for
poor progress.
20.03.201 TL Claimant Stated on Time Extension
7 for 1st and 2nd Milestone.
Hence, requested to
expedite the progress of
work as per provision of
contract agreement.
01.04.201 Respondent Claimant Submitted the Project
7 Performance Review and
Cure Period Notice.
11.04.201 Claimant Respondent Informed regarding the
7 Naxal threatening.
12.04.201 Claimant TL Submitted the
7 Application for EOT
under CL.10.5 of the EPC
agreement.
24.04.201 Claimant Respondent Informed about due to
7 naxal bandi there is no
work at site.
03.05.201 TL Claimant Submitted the details of
7 Chainage wise
Hindrances at site on
account of pending land
acquisition.
08.05.201 TL Claimant Requested concurrence
7 of revised box culvert
drawings for review.
09.05.201 TL Claimant Informed regarding the
7 EOT.
23.05.201 Claimant Respondent Intimated that due to
7 unavailable of land 10%
of project work cost is
hampered and requested
to give the permission to
accomplish the work.
05.06.201 Claimant Respondent Stated regarding the
7 compliance against
intension to issue
termination notice as per
clause 23.1.2 of Article 23
of Contract Agreement.
04.07.201 Claimant DG, Requested to allow
7 MORTH Milestone extension of
the said work.
05.07.201 Claimant Respondent Requested to release the
7 amount withheld from 1st
and 2nd SPS on account of
milestone.
06.07.201 Claimant Respondent Requested for time
st
8 extension till 31 march
2019 and rescheduling
milestone as per revised
work programme.
08.07.201 TL EE Requested for release of
7 an amount hold in IPC 1st
2nd against failure of
milestone-I & II.
12.07.201 Claimant Respondent Informed the local
7 villagers removed the
pillars for which work
has been unable to
proceed. Requested to do
the needful.
27.07.201 TL Claimant Submitted the resource
7 based programme for
examine in detailed.
Hence, requested to do
the needful.
01.08.201 TL Claimant Submitted comments
7 against the submission of
design and drawings of 5
(nos) minor bridges.
04.08.201 TL Claimant Notice on failure of
7 Milestone III and
subsequent effects as per
clause 10.3.2 under
Article 10 of Contract
Agreement.
04.08.201 TL Claimant Submitted comments
7 against the submission of
design and drawings of 2
(nos) minor bridges.
14.09.201 TL Respondent Requested to revoke
7 intension to termination
letter.
20.10.201 Claimant AE Informed about
7 resubmission of
drawings and design at
chainage 3+490, 5+050,
8+370, 10+507 and
11+650.
24.10.201 TL Respondent Informed about the
7 resources based work
programme and progress
reviewed against
intention to issuance of
Termination Notice as
per Clause 23.1.2 of
Article 23.
31.10.201 Claimant TL Informed about the
7 accomplishing 26.33% of
financial progress till 31st
October, 2017 against
20.18%.
17.03.201 TL Claimant Requested to incorporate
8 corrections made by the
TL on the drawings and
to submit the same for
verification.
23.07.201 TL Claimant Informed about the
8 acceptance of revision of
plan and profile without
any time extension.
24.07.201 Respondent Claimant Informed regarding
8 withdrawal for
termination notice.
15.01.201 Claimant TL Informed about the
9 resubmission of
drawings for minor and
major bridge as per plan
and profile of the road.
23.01.201 TL Claimant Requested for
9 submission of drawings
for minor and major
bridge as per plan and
profile of the road.
05.02.201 TL Claimant Submitted their
9 comments on revised
design and drawings for
highway, major and
minor bridge.
13.01.202 Claimant TL Requested to make the
0 payment for the said
work.
17.01.202 Claimant Respondent Requested to restore the
0 police protection in the
work site.
17.01.202 Claimant Respondent Requested to release the
0 amount of BG for smooth
process of work.
17.01.202 Claimant Respondent Submitted the revised
0 work program of the said
work. Hence, requested
to release the LD &
Withheld for Milestone
along with running bill.
18.01.202 TL Claimant Informed about critical
0 issues raised by the
Respondent regarding
foundation level quantity
of concrete, design and
drawings.
Not Claimant TL Submitted two sets of
visible plan and profile
drawings for review.
22.01.202 Claimant Respondent Notice regarding the said
0 project was terminated
on 24.04.2019 and police
protection frim site was
removed wherein EE had
REVOKED the said
tender on 10.01.2020.
hence, requested to
provide the protection
for the smooth running
of project.
23.01.202 TL Claimant Submitted the pending
0 design & drawings for
the said work.
23.01.202 TL Claimant Stated concerning the list
0 of calibrated plants &
equipment’s available or
yet to be procured for
batter QA & QC.
23.01.202 TL Claimant Submitted the MTC &
0 third party test report of
material.
04.02.202 TL Claimant Directed to resume the
0 work immediately.
11.02.202 Claimant TL Requested to send the
0 proposal to authorities
immediately so that EOT
could be sanctioned.
11.02.202 TL Claimant Instructed that to start
0 the mobilization at site
immediately.
14.02.202 TL Claimant Submitted the key
0 personnel needs to be
deployed at site as per
provision of contract
agreement & good
industry.
18.02.202 TL Claimant Requested that material
0 must be tested in third
party laboratory and
submitted the test results
to this office at the
earliest.
18.02.202 TL Respondent Informed regarding the
0 EOT up to 31.03.2021,
and shifting of milestone,
which is recommended
as under the said letter
without any extra
financial implication to
the Authority for the
completion of the work.
21.02.202 Claimant Respondent Resubmitted of GST Bill
0 No.1 wherein releasing
the same amount of
Rs.59,85,966.00/- at the
earliest.
21.02.202 Claimant AE Informed about critical
0 issues raised by the
Respondent regarding
foundation level quantity
of concrete, design and
drawings.
28.02.202 TL Claimant Submitted various
0 reasons for the rejection
of deck slab caste for
minor bridge at
th
ch.11+650 from 24 to
26th Feb 2020.
04.03.202 TL Claimant Informed about critical
0 issues raised by the
Respondent regarding
foundation level quantity
of concrete, design and
drawings.
06.03.202 Claimant Respondent Requested to see the bill
0 which was released at
the earliest.
18.03.202 TL Claimant Submitted the return of
0 incomplete GST Bill.
18.03.202 TL Claimant Informed regarding the
0 pending payment of the
aid work.
21.03.202 Claimant TL Stated that due to out
0 break of Coronavirus,
unprecedented rainfall
and non-availability of
funds work could not be
proceed appropriately.
Hence, requested to
release the funds and do
the needful at the
earliest.
25.03.202 Claimant Respondent Submitted the GST Bill
0 No.3
25.03.202 Claimant Respondent Intimated of force
0 majeure.
26.03.202 Claimant Respondent Resubmitted the GST Bill
0 No.1.
02.04.202 Claimant Respondent Requested to release of
0 pending bill in SPC No.8
of Rs.4,27,89,823.
04.04.202 Claimant Respondent Requested to resolve the
0 persisting statement by
allowing EOT and
release all the payment
of the said work.
06.04.202 TL Claimant Resubmitted of GST Bill
0 No.1 and requested to
submit complete bill of
the said project.
07.04.202 TL Reg. Officer Requested to release the
0 pending bill in SPS-8 of
Rs .4,27,89,823/-
08.04.202 TL Respondent Requested to bestow
0 approval for EOT at the
earliest.
13.04.202 Claimant Respondent Requested to grant
0 approval for EOT at the
earliest.
16.04.202 Claimant Respondent Submitted of Bill of
0 Shifting of 33KV, HKV
and LT Electrical line
wherein requested to
release the bill of the
same amounting to
Rs.77,99,539.22/-.
17.04.202 Claimant DG & SS Stated regarding for
0 releasing the blocked-up
funds amounting to
Rs.4,27,89,823/- & EOT
18.04.202 TL Respondent Requested for release of
0 Electrical utility shifting
bill at the earliest.
20.04.202 Claimant TL Requested of
0 rescheduling the
Schedule-H and the stage
payment for Dense
Bituminous Macadam &
Bituminous Concrete
quantities of the said
work.
20.04.202 Claimant AE Submitted of price
0 variation of the said
work.
25.04.202 Claimant TL Informed about the EOT
0 and Requested to release
the mentioned amount at
the earliest.
30.04.202 TL Claimant Submitted of Escalation
0 Bill of the said work.
29.06.202 TL Claimant Informed about non-
0 submission of design and
drawing of form work
for review as per
MoRTH Clause 1503.1
and 1503.2.
08.08.202 Claimant AE Informed regarding the
0 EOT of the said work.
22.09.202 Claimant Respondent Informed regarding that
0 after getting such
persistence, AE wasn’t
convinced to release the
fund. Hence, requested
to take serious action in
this regards.
29.09.202 TL Respondent Requested for EOT
0 against force majeure
event due to COVID-19.
05.10.202 TL Claimant Informed regarding the
0 resume of work.
22.10.202 TL Claimant Submitted the GST Bill
0 No-2 of the said work.
29.10.202 Claimant Respondent Requested to provide
0 security for staff and
machineries.
06.11.202 TL Claimant Notice regarding on slow
0 progress of work as a
result Milestone IV
which is going to be
failed and subsequent
effects as per Clause
10.3.2 of Article 10.
06.11.202 TL Claimant Informed regarding the
0 resume of the work at
the earliest.
11.11.202 Claimant Respondent Requested to extend the
0 validity of DO for
upliftment of Bitumen as
the same as expired.
11.11.202 TL Respondent Submitted the month
0 wise physical & financial
progress for last six
month.
28.11.202 Claimant TL Notice regarding on slow
0 progress of work as a
result Milestone IV
which is going to be
failed and subsequent
effects as per Clause
10.3.2 of Article 10.
03.12.202 TL Claimant Informed about the
0 points discussed during
the site inspection of CE
dated 02.12.2020.
21.12.202 Claimant AE Enclosed is the said work
0 of Stage Payment
Statement 11 and
requested to release the
amount of Rs.
2,02,78,691/-.
22.12.202 Claimant Respondent Requested to issue DO
0 for upliftment of
Emulsion from
Hindustan Colas for
construction of by pass
around Gumla town.
24.12.202 Claimant Respondent Submitted the Price
0 Variation of escalation
bill along with all
relevant documents of
the said work and
requested to release the
amount of Rs.98,18,730/-.
14.01.202 TL Claimant Requested for relies of
1 Interim Payment
Statement No.11.
18.01.202 TL Claimant Requested to submit the
1 revised formation levels
(FRL) and its has been
stated that extra time
extension and financial
condition shall be
considered in this
account.
25.01.202 Claimant TL Informed regarding the
1 Non-availability of VG-
40 at HPCL. Requested
to do the needful.
28.01.202 Claimant Respondent Requested to release the
1 mentioned payment at
the earliest.
28.01.202 Claimant Respondent Requested to give the
1 permission for VG-30
grade Bitumen, so that
the work could be
completed within the
stipulated time period.
29.01.202 TL Claimant Requested to submit the
1 source details and post
approval of the source.
01.02.202 Claimant TL Requested to give the
1 permission for VG-30
grade Bitumen, so that
the work could be
completed within the
stipulated time period.
12.02.202 Claimant AE Intimated that due to
1 delay in releasing the
payment the work is
being obstructed. Hence
requested to look in to
the matter at the earliest.
12.02.202 Claimant AE Stated regarding the
1 status of compliance of
CE MOM held on
28.01.2021 and requested
to release the payment at
the earliest.
12.02.202 Claimant AE Requested to arrange
1 security camp to protect
staffs & machineries
from any unwanted
incidence.
16.02.202 Claimant TL Informed regarding to
1 conduct the necessary
tests at Gumla town.
20.02.202 Claimant Respondent Intimated that due to
1 delay in releasing the
payment the work is
being obstructed. Hence
requested to look in to
the matter at the earliest.
22.02.202 Claimant Respondent Intimated that due to
1 such types of hindrances
work was not being able
to maintain the progress
hence, requested to
release the payment
immediately.
24.02.202 Claimant TL Informed that, due to the
1 non-availability of VG-40
at HPCL, the said work
has been unable to
proceed further. Hence,
it was requested to grant
permission for the use of
VG-40-grade bitumen for
the work.
25.02.202 TL Claimant Stated regarding for
1 requirement of fund or
delay in payment of the
said work.
26.02.202 TL Respondent Informed regarding the
1 pending payment of RA
Bill No.13 which is
recommended as RA Bill
No.12 of the said work.
26.02.202 Claimant AE Enclosed Stage Payment
1 Statement and requested
to releasing the amount
of Rs.83,16,444/- of the
said work.
28.02.202 Claimant AE Submitted the Escalation
1 Bill and requested to
release the amount of Rs.
63,77,443/-.
01.03.202 TL Claimant Informed regarding to
1 expedite the progress of
work from 1st Feb to 28th
Feb, 2021
04.03.202 Claimant Respondent Requested to release the
1 payment at the earliest.
09.03.202 Claimant Respondent Intimated regarding the
1 facts of delay and default
in completion of the
project upon resolution
of which work execution
would progress and
called upon to take a
decision within 15 days.
23.03.202 TL Respondent Requested to process the
1 pending aforesaid
payment at the earliest.
24.03.202 Claimant AE Requested for EOT up to
1 31.03.2021.
10.06.202 Claimant AE Requested to grant
1 permission for the forest
land clearance of the said
work.
02.05.202 TL Claimant Submitted the revised
2 work programme and
resubmit the same to
expedite the process for
approval of EOT.
05.05.202 Claimant AE Enclosed Stage Payment
1 Statement – 11 and
Submitted the Bill No-
SPS-15. Hence, requested
to release the same
amount of Rs.87,28,368/-
at the earliest.
12.05.202 TL Claimant Submitted the
1 compliance report of the
said letter and requested
to release the payment
against minor bridge.
13.05.202 TL Claimant Instructed to submit the
1 compliance report of the
said letter and requested
to release the payment
against the major bridge.
14.06.202 TL Claimant Informed regarding the
1 concur of General
Arrangement Drawing
for PCC Wing Wall and
requested to do the
needful.
21.06.202 TL Claimant Intimated regarding the
1 site inspection report of
the said work.
22.06.202 TL Claimant Requested to submit all
1 the necessary documents
for review of design and
drawings.
22.06.202 TL Claimant Requested to submit the
1 resource based work
programme by 30th
September 2021 and
informed about the
approval of EOT
application submitted by
the Claimant.
22.09.202 TL Claimant Intimated that after a
1 numerous stipulation of
communication still
embedment of founding
layer is not sufficient
considering weathered
rock. Hence requested to
go through the matter of
the said letter.
29.09.202 TL Claimant Intimated regarding the
1 Major Bridge foundation
and substructure design
and drawings is review
and concurred by the
authority.
29.10.202 TL Claimant Requested to submit the
1 compliance report as per
the following points on
the said letter
immediately.
29.10.202 TL Claimant Requested for the
1 submission of resource
based work programme
for reviewing of the EOT
proposal submitted by
the Claimant.
16.12.202 TL Claimant Requested to submit the
1 roadside furniture, traffic
control devices, and road
safety details review and
concurred at the earliest.
14.01.202 Claimant AE Requested to De-Scope
2 the Toll Plaza from the
scope of the work.
21.02.202 TL Claimant Submitted the roadside
2 furniture, traffic control
devices, and road safety
details with supper
imposed on a Google
sheet of P&P drawings
review and concurred at
the earliest.
07.03.202 Claimant Respondent Requested for sanction of
2 EOT for completion of
balance work.
07.03.202 Claimant Respondent Requested to release the
2 withheld payment of the
said work.
. 11.03.202 Claimant AE Submitted the road
2 signage plan.
. 14.03.202 Claimant AE Informed regarding
2 opened the road for
traffic by constructing a
diversion near the major
bridge.
14.03.202 Claimant AE Requested to release of
2 withheld payment at the
earliest.
14.03.202 Claimant Respondent Stated that due to
2 unavailability of fund
bill was not being able to
paid. Hence, requested to
look in to the matter.
14.03.202 Claimant Respondent Requested to purchase
2 the aggregate for the said
work.
14.03.202 TL Claimant Requested to release the
2 pending dues.
14.03.202 TL Claimant Requested to submit the
2 GST Bill which is
pending for payment.
15.03.202 TL Claimant Informed regarding the
2 unavailability of
Aggregate of the said
work.
17.03.202 Claimant AE Submitted the road
2 signage plan.
21.03.202 Claimant Dist. Requested to release the
2 Collector payment at the earliest
and the following details
which has been
mentioned in the said
letter.
28.03.202 TL Claimant Stated that the company
2 didn’t give any financial
support to the site.
Hence, it was requested
to release the pending
dues for the said work.
28.03.202 TL Claimant Requested to release the
2 Performance Security
Deposit at the earliest.
28.03.202 TL Claimant Submitted the roadside
2 furniture, traffic control
devices, and road safety
details with supper
imposed on a Google
sheet of P&P drawings
review and concurred at
the earliest.
30.03.202 Claimant AE Informed regarding the
2 various reasons which
have affected and
delayed the work in the
said letter. Hence,
requested to approved
the EOT at the earliest.
02.04.202 Claimant Respondent Informed about the site
0 requirement metal beam
crash Barrier needs to be
provided at the
following chainnage and
requested to issue the
change of scope notice
under clause 13.2.
06.04.202 Claimant Respondent Intimated due to
2 international pressure
and the delay in
sanctioning the EOT, the
huge fund has been
blocked, hence the
request to recommend
the EOT at the earliest.
07.04.202 TL Claimant Submitted the Change of
2 Scope proposal, wherein
the metal beam crusher
is to be provided and
fixed at the high
embankment. Hence, it
was requested to do the
needful and execute the
work at the earliest.
07.04.202 Claimant Respondent Requested to release the
2 Security Deposit
amounting to
Rs.1,40,36,315/-.
13.04.202 Claimant Respondent Requested to approve
2 the EOT so that bills
could be processed to
complete the work.
13.04.202 Claimant Respondent Requested to grant the
2 permission to do DBM
on the site.
14.04.202 Claimant Respondent Requested to release the
2 retention money at the
earliest.
14.04.202 Claimant Respondent Requested to make an
2 interim payment of 90%
of the price adjustment
ill as per the circular.
14.04.202 Claimant Respondent Requested to extension
2 of relaxation in schedule
H/G which is granted to
improve the liquidity of
funds.
16.04.202 Claimant Respondent Requested to release the
2 retention money of
Rs.1,40,36,315/- of the
said work.
16.04.202 TL Claimant Submitted the road side
2 furniture and traffic
control devices & road
safety details review and
concurred at the earliest.
18.04.202 Claimant AE Requested to release the
2 Security deposit of
Rs.1,40,36,315/-.
19.04.202 TL Claimant Informed that the work
2 which is made at
Ch:2+850 to 2+900 is not
good in case of rock
blasting and removing.
Hence, requested to
complete the work at the
earliest.
20.04.202 Claimant Collector, Intimated that to
2 Gumla complete the bituminous
work with in stipulated
time period.
21.04.202 TL Claimant Requested to arrange the
2 fund for the requirement
of project completion in
the due time period for
the said work.
22.04.202 Claimant Respondent Requested to recommend
2 the EOT for the said
work.
23.04.202 Claimant Respondent Informed that the work
2 program can be achieved
on timely payment of RA
bill and price escalation
by the department.
23.04.202 Claimant Respondent Requested to release the
2 retention money
amounting to
Rs.1,33,42,364/- of the
said work.
07.05.202 Claimant Respondent Requested to release the
2 retention money of
Rs.1,33,00,000/- of the
said work.
09.05.202 TL Respondent Clarification sought by
2 SE is as follows:

a. The justification
for the delay in
working is duly
supported by
documents.
b. Stated regarding
the opinion on the
cause of the delay.
c. Submitted the
work programme.

09.05.202 Claimant Respondent Requested to take note of


2 the following letter that
to release the retention
money as per letter
dated.11.04.2022.
12.05.202 Claimant AE Submitted the
2 compliance report of the
work.