Professional Documents
Culture Documents
Rejoinder MG KUNDU 28.02.2024 Corrected
Rejoinder MG KUNDU 28.02.2024 Corrected
) PRAKASH PRABHAKAR
BETWEEN
M/s MG-KUNDU-SHIVALAYA(JV).
……… CLAIMANT
AND
A. Preliminary Rejoinder:
1. That, the whole of the defense being beyond the terms of the
1
evidencing the conduct and intent of the parties and the very
this rejoinder.
the same has no privity or the same has not been shared to the
only a representative of the Govt. of Haryana who was assigned the job of
signing duly appointed by the Govt. of Haryana to enter into the contract, is
JV. also hence nothing wrong has been done and Govt of Haryana has been
rightly made a party.Hence, the Claim Petition against the Govt. of Haryana is
1.[2.] The defense in Para- 2 is admitted to the extent the same are
matter of record.
2
Rejoinder to the defense on account of “scope of work”
could be able to take decision for deletion of work for one road
3
between the MSV and the Respondent having not privity to the
site and delayed the start of the work” is not correct and the
failed to deploy manpower and machinery and rather he has reassured the
respondent that from his side he will do whatever possible to ensure timely
completion. The Claimant did not concede that there is any breach in
appointing of manpower and machinery from his side. The Letter clearly
shows exibits that the work was affected by Force majeure events, local
pertinent to state that the Claimant through its letter dtd. 24.09.2011
provided the details of his men and machinery deployed at the site. The
reference of the same from the SOC of the Claimant having been
its right to deal the same, if the Respondent would submit the
same hereinafter.
Further it is submitted that it is false that work program was not submitted
4
20.06.2011 (R-4) , this becomes noteworthy that date of start was 08.06.2011.
The Consultant was hostile since start of the work and even after submission
of work program he was repeatedly asking for revised program again and
again (R-5) .
Claimant
drawing and cross drainage details from the claimant, but Respondent has
Claimant to coverup its own inaction and failures in removal of all the
hindrances like tree, electric lines, water and sewer lines.(Ref C-9 series and
R-9).
true context as to how the same are of no use so far as the claims
5
3.[5.] The averments made in Para-5 with reference to Clause-7.2
does not also help the Respondent as Firstly, it can only visit and
examine the site of the works and its surrounding to the extent,
provision of Clause-7.2.
4.[6.] The defense in para -6, with reference to Clause-110, 110.1 and
to obtain the same being a private agency and not the owner of
Requirement (page no. 116-117 of Vol. II of SOC). This clause makes it clear
that for the removal of hindrances the Claimant would do the follow-up
6
work with the authorities but the main cost for removal/shifting will be
borne by the respondent and respondent will actively assist the Claimant in
117, Vol. II, SOC). This clause clearly contradicts the Respondent's
position. This clause clarifies that the Claimant will handle follow-up
work with authorities for hindrance removal, while the Respondent bears
the primary cost for removal/shifting and actively assists the Claimant in
this process.
not help the Respondent as (i) The same are equally routine
writing (iv) For which only the work to the extent the scope was
7
in the table bearing Sl. No. 1 to 43 during the course of the
argument.
8
that part of the work which are dropped from the
9
to claimant’s letter dated 30.08.2012(C-9/41). The
TO ANSWER)
The Claimant’s letter dated 14.02.2015 shedspurt some light on the working
delays after the issuance of the taking over certificate. post, issuance of
10
It is ffurther submitted that though the bridges were got manufactured
as early as during 7/2014 but the issue remained under fire and no
decesion could be taken with regard to finalization of the bearing of
the bridge even after manufacturer of the bridge and decesion of the
bearing could only be conveyed a week back.”
11
descoped earlier, without prejudice it is stated as per the
bills No.10th, 11th and 12th with the mentioning that the work is
not correct, the Claimant replied to Exhibit R/71 & R/72, vide
12
was replied vide Claimants letter dated 30.06.2018(C12/3),
R/73 is denied as the same was not having any privity with
the Claimant.
The Chronology submitted by the respondent itself reflects apathy and autocratic
working style of the Respondent and autocratic way of working . The submission of
execution of any additional items. Approval for the rates submitted by the Claimant,
was inexplicably delayed until 11.10.2012, after the lapse of seven years, such
approval was never officially communicated to the Claimant. The claimant upon
receiving verbal information, the Claimant was pressured to revise the bill
by the Claimant vide latter dated 12.07.2012 was accorded on dated 11.10.2019 after
laps of 7 long years (not communicated to the Claimant even as on date) on getting
verbal information claimant was forced to revise its part of bill from 8,80,19,496/- to
4,25,95,389/- Vide letter dated 08.11.2019( R-74) and even after the such delayed
approval payment has not been released till date. Demand of fund was initially
raised for an amount of Rs. 4,25,95,389/- vide Respondents letter dated 15.11.2019,
same was revised maliciously for an amount of Rs. 3,04,58,424/- vide letter dated
20.01.2020, without any knowledge or consent of the Claimant The initial demand
for funds (₹4,25,95,389) was submitted via the respondent's letter dated 15.11.2019
having been maliciously revised to ₹3,04,58,424 (Letter dated 20.01.2020) without the
13
13. That, the defense in Para-13 is not correct as the steel bridge at
owned by M/s DARCL Logistics Ltd Gurgaon, exceeding the weight limit of
350 tonnes damaged the bridge structure, causing its collapse. with a heavy
load exceeding 350 tonnes load has hit the steel bridge resulting in to
The fact is that the that the said bridge had collapsed due to an impact from
any overloaded Trailor for which the bridge was not designed. DGM-III
14
you may deem fit at your end against the transport
company.”
Such incidents fall under the purview of the Respondent and other
related entities.
above.
1. The defense in para-1 is not correct as the Claimant has filed its
15
Companies Act, 1956 under the aegis of Department of Industries
upon in the SOC. Moreover, the alleged reduction of the final bill
16
Tribunal to adjudicate the disputes the right of which the
REJOINDER FOR:
17
3. The defence in Para-8 is denied. As the reasons for non-
18
penalty/coercive action has been imposed on the Claimant
contract once taking over is issued for any part of the work,
third party at the risk and cost of the Claimant the cause of
to strict proof for the same. Moreover, the Claimant will deal
para.
correct as the works to the extent there was scope and the
19
The submission on account of final bill being repetitive the
any suggestion that there was the delay of 199 days due to
compensation events.
to R/194 denied to the extent the same are routine and follow
20
import and context of those letters which are connected with
21
6. The defense in Para-d (i) that “the Engineer was not
record.
9. The defense in Para-d (iv) that “the Engineer vide its letter
22
the same Engineer recommending time extension
and as per the law of the land, the Engineer was required
Respondent.
compensation events.
work.
23
vi) As to why it has not effected execution of the alleged
Claimant.
viii) Why road work of 2.5Km. was de-scoped and the re-
scoped.
24
extension the Claimant did raise claim for prolongation is
The defense that “the Claimant continued the work at the site on
IPC), which was evaluated at the old rates. and continued the
25
work and actually after stipulated completion date quantum
of work of Rs (63,05,77,448-45,42,22,848=17,63,54,600/-)
( 12th& Final Bill - 8th IPC) was evaluated as per old rates
11. The defense in Para-h that “it is not admitted to the extent
26
(F) RE: FACT SHEETS CRYSTALIATION OF “CLAIMS” INTO
“DISPUTES”:
facts sheets from July, 2012 till January, 2020 are entirely
Claimant without its approval and thereafter take shelter that it was
The Claimant has submitted its rates based on its input costs, same were scrutinized
by the engineer and forwarded to the Respondent, the work was got executed, and
final bill was submitted vide Claimant letter dated 06.02.2018. in the month of
November 2019 claimant was verbally informed that NS items were approved and it
was asked to amend the bills based on approved rates to get the payment ,
accordingly same was partially corrected (under duress) ) in the hope of getting
some payment vide letter dated 08.11.2019 after approval of NS items and even after
that payment has not released even as on date that goes to show the high
27
Respondent has secretly and illegally deducted the cost of collapsed bridge
structure which was 100% complete except for sticking of some cosmetic items as
mentioned by the Respondent in its SOD without any fault of the Claimant and
In November 2019, the claimant was verbally informed of the alleged approval of NS
items and instructed to modify its bills based on the purported rates to receive
payment. The claimant partially complied with this request (under duress) via a
letter dated November 8, 2019, in the hope of securing partial payment. However,
despite the claimed approval, no payment has been received to date. This sequence
Furthermore, the Respondent has secretly and illegaly deducted the cost of the
collapsed bridge structure, which the claimant asserts was 100% complete except for
deduction was reportedly made without the claimant's consent, information, or any
departmental procedure and even as on date has not released the payment.
iii) The averments made in Para-c that “the Claimant was given
28
completion certificate” is the evasive as it was the
Feb 2017 the Respondent has not formally taken over the
DLP was cleared except for two number steel bridges, and
LIMITATIONS:
29
i) The averments made in Para-“a to c” to the extent the same
[ii)] The averments made in Para-d that “the Claimant left the
Instead, the engineer has cleared the DLP for of all works
assumed that the clock of limitation has started, it could not have
30
Punjab and Haryana Chandigarh vide its petition u/s 11 and filed an
appointed this Hon’ble Tribunal vide its order dated 28.07.203. Thus,
from this aspect as well, the claim is well within the period of
and 15.01.2019.
[iii)] The contract provides and it is the practice and law that if
31
performed by the Respondent at the risk and cost of the
32
bill, the Respondent has power left to determine the final
bill ex-parte.
9.1, 7.4 and 4.1 is without any substance, all the IPC’s were
33
released after following due procedure, the and Engineer
TO ABOVE CLAUSES)
heavy load exceeding 350 tonnes load has hit the steel bridge
interveining night of May 7-8, 2016 . In the light of this , you are
road to traffic. Besides this, you may take any appropriate legal
actionwhich you may deem fit at your end against the transport
RECORD)
vii)[x)] The defense that “the Claimant was fully responsible for
34
Respondent” is correct but, the contract nowhere provides
reflective tapes and hight gauge etc. were not fixed” and
35
obligation of the Claimant and the Respondent has not
made out a case that it has incurred any cost for doing the
arbitrary manner by the Respondent for more than ten years , any
commercial intity can not not further invest crores of rupees with out
decesion with respect to the next Bridge and eventually due to non
2017,Even when Claimant was hard pressed for want of funds and
the Respondent was not forthcoming & sincere about making his
36
the Respondent who, following the collapse of the first bridge,
February 2017, even while the Claimant faced financial hardship and
before execution of work, if the Respondent was not satisfied with the
REFERENCE OF DOCUMENTS)
x)[xv)] The defense that “the approved NS items rate were duly
37
as Firstly, the NS items rate was prepared unilaterally and
PREPARATION OF DRAWINGS:
38
ii) The defense of the Respondent that “no such type of
the contract.
BC:
39
i) At the outset the Claimant beg apology for mistake in the
ii) The whole of the defense against this claim is denied with
iii) The alleged defense with reference to R/195 and R/196 are
40
v) The alleged determination of the rate for variation on
THAN 25%:
definitions of “cost”.
[iii)] That, Respondent’s denial that Claimant is not entitled for new rates
being variation below less that 25% as provided in Clause 12.3(a) is
grade
12 Construction of Cu 150282.95 107997.326 28.14%
41
GSB m
Water bound
macadam grading Cu
13 a 57219.35 26122.312 54.34%
no. 3 (53 mm to 22.4 m
mm)
Water bound
mcadam grading Cu
13b 49535.68 26701.433 46.10%
no. 2 (63mm to m
45mm)
Brick masonry
Cu
29 work in 1:4 in 14160 5656.226 60.05%
m
foundation
Supplying , fitting
in foundation
varied more than 25 %. Respondent in is SOD has argued that the quantities
have not exceeded more than 25%, but here the contract provided for
42
i) The defense of the Respondent with reference to delay
43
Asudha Road laid to delay in completion of even the
44
CLAIM NO.6: AMOUNT PAYABLE BEING THE LOSS OF
CONTRACT.
India.
does not help the Respondent for the reasons that Firstly,
the copy of the judgment has not been produced for kind
45
provided under Clause-16.2 of the contract had not arisen
provided the details and has claimed lum sum amount does
46
compensation/damage applying its discretion and to this
argument.
not spelt out as to how and to which effect the Claimant had
the steel bridges and one road after issuance of the taking
47
of Rs.51 Cr. within the schedule period notwithstanding
political/administrative decision.
of argument.
viii) The defense that the Claim is indirect losses and damage is
Engineering.
MACHINERIES.
iii) The defense with reference to the time extension for various
48
contract the compensation event and the reasons thereof
Employer.
correspondences.
49
i) The defense in Para-8 that “the work of steel bridge was
made above.
proof thereof.
ON ACCOUNT OF GST:
of compensation events.
50
legislation, over and above the agreed cost, the same
manner.
claimed.
ii) Since the Claimant has not objected to the period of interest
EXPENSES:
51
The rest of the defense of the Respondent is denied
PRAYER
In view of the fact stated above the Hon’ble Tribunal may be pleased to
reject the defense of the Respondent and award the claims as prayed in
the SOC and substantiated through the Rejoinder mentioned above for
Place:
Authorized Signatory
52