Professional Documents
Culture Documents
Sanjay Aggarwal
Sanjay Aggarwal
Versus
MASTER INDEX
Sl .no Particulars Pages
1 Index-I
2 Court fees
3 Urgent Application
4 Notice of Motion
5 Petition Under Section-11(6) of
Arbitration and Conciliation, 1996
along with supporting affidavits
6 Statement of Truth
7 Certificate by way of Affidavit under
Order XI Rule 6(3) of Commercial
Court Act, 2015
INDEX-III
Sl.
No.
Document Whether Who is in the Mode of Line PG
Petitioner Power/ Execution/I of
has possession/c ssuance of Custo
Original or ontrol Receipt dy
Office Copy
or
Photocopy
INDEX-III
1
Copy of the Photo Petitioner Petitioner Original
Power of Copy filed along
Attorney with
dtd.30.05.2019 Petition
Party
Filed through
Versus
XXXXXXXXXXXXXXX
…Respondents
INDEX-1
Filed through
Versus
XXXXXXXXXXXXXXXXXXXXXXX
…Opp. Party
URGENT APPLICATION
Sir,
“____________________________”
Yours Faithfully
Filed through
Versus
XXXXXXXXXXXXXXXXXXXXXXXXX
…Opp. Party
NOTICE OF MOTION
Sir,
Filed through
SYNOPSIS
The present Petition under Section 11(6) of the Arbitration and
Conciliation Act 1996 is being preferred for the appointment of an
arbitrator on behalf of the Opp. Party as it has failed to appoint its
nominee Arbitrator in terms of the Contract Agreement.
That, the Petitioner being the finest bidder was awarded with the
work “Earthwork, Construction of CC, Block Pavement Approach
Road, P-way Track work, Boundary Wall Pre-Engineered
Warehouse, Admin Building and Other Allied works for
development of MMLP At-Jajpur Road, Jajpur, Odisha” arising
out of the Agreement No. CON/EP/MMLP Jajpur/Civil & Electrical
works/2018, dtd.15.04.2019. The petitioner then immediately began
executing the work, mobilizing its workforce and machinery and
taking all necessary precautions; nonetheless, certain defaults that
were not attributable to the Petitioner resulted in unnecessary delay
and the execution of the work suffered as a result.
That, the Petitioner approached the Opp. Party and stated that it has
become impossible to complete the work due to the steep rise in the
rates of various components because of the COVID-19 pandemic,
and further requested an extension of time until 31.12.2021, with the
benefit of price escalation with regard to the value of works
completed after the scheduled period of 18 months and the
remainder of the work remaining to be executed; or to close the
contract under Clause-61 of GCC of the agreement.
That, while the Opp. Party agreed that the obstacles were at their
fault but still denied all of the Petitioner's demands in its letter dtd.
01.07.2021. Finding no other option, the Petitioner intimated its
intention to terminate the contract in its pleader's notice dated
07.07.2021, unless a favourable decision on the mitigating financial
demands was reached within 15 days of receipt of the said letter.
After the period of 15 days, the Petitioner restated the
9
abovementioned proposals in the interest of the work vide its
Pleader's notice dtd.19.07.2021.
That the Opp.Party, in its letter dtd.12.07.2021, issued a 7days notice
directing the Petitioner to show cause as to why action under Clause-
62 of the GCC should not be conducted against him. The Petitioner
promptly responded to the abovementioned notice vide letter dtd
23.07.2021 and further again mentioned that it has cancelled the
contract in the abovementioned letter due to the Opp. Party's
complete lack of concern. The petitioner also stated that any
subsequent terminations under Clause-62 of the GCC would be in
violation of Sections 53, 54, 55, 73, 74, and 75 under Indian Contract
Act, 1872.
That, though the Petitioner had already terminated the contract vide
its letter dtd.23.07.2021, the Opp. Party forwarded a 48-hour notice
vide letter dtd.30.07.2021 informing its intention to terminate the
contract. The Petitioner stated in its reply dtd.02.08.2021 that it is
unable to take any action towards the completion of the project since
the contract has already been terminated and it is no longer able to
do so. However, without taking into account the Petitioner's
representations in different letters, the Opp. Party again terminated
the contract as per Clause-62 of the GCC in its letter dtd. 03.08.2021
and the Opp. Party also informed the Petitioner by letter dtd.
04.08.2021 that it has urged the Branch Manager to encash the Bank
Guarantee given by the Petitioner. Despite the fact that the Petitioner
had addressed the Hon'ble District Judge Khurdha under Section 9 of
the Arbitration and Conciliation Act, 1996 (ARBP No. 25/2021) and
received a favourable Order from the Hon'ble District Judge for a
stay of invocation. Despite the fact that the Hon'ble District Judge's
Order was personally communicated to the Opp. Party on 11.08.2021,
as well as vide letter dtd. 14.08..2021, the Opp. Party took no action in
response to the aforementioned ruling.
That, in light of the foregoing, the Petitioner vide letter dtd.
09.06.2021 requested the Opp. Party to take mitigating measures and
allow the Petitioner to complete the work. The Petitioner also
requested in the said letter that if the Opp. Party fails to take such
10
mitigating steps, the said letter shall be construed as a letter under
Clause-63 of the GCC for the purpose of resolving the disputes, and
that if the Opp. Parties fail to resolve the disputes within 120 days,
the Petitioner will have no choice but to refer the disputes to a duly
constituted Arbitration Tribunal.
However, the Opp. Party did not take any action in appointing the
Arbitration Tribunal, which forced the Petitioner to issue a another
Pleader's Notice dtd.11.03.2022, seeking the Opp. Party to appoint an
Arbitrator in accordance with the Contractual Conditions. However,
irrespective of such intimation and subsequent reminders the Opp.
Party has failed to take any step towards appointment of Arbitrator.
Due to such inordinate delay, the Petitioner is being constrained file
this present petition.
LIST OF DATES & EVENTS
dtd. 30.05.2019.
2019-2021 The Petitioner faced various hindrances during
Opp. Party.
28.06.2021 The Petitioner informed the Opp. Party that it
31.12.2021.
01.07.2021 The Opp. Party denied to comply with the
Petitioner’s requests.
11
Petitioner.
13.07.2021 The Petitioner replied to the 7-Days Notice of the
terminated.
03.08.2021 The Opp. Party terminated the contract under
Bank Guarantee.
14.08.2021 The Petitioner informed the Opp. Party about the
invocation.
06.09.2021 The Petitioner requested the Opp. Party to take
12
Tribunal.
11.03.2022 The Petitioner requested the Opp. Party to
conditions.
13
Versus
XXXXXXXXXXXXXXXXXXXXXXX
…Opp. Party
MEMO OF PARTIES
Sanjay Aggaarwal
Aged About __________, S/O__________________,
addressed at 35-36,First Floor, Millennium Plaza,
Raipur, Chhattisgarh.
…..Petitioner
-Versus-
XXXXXXXXXXXXXXXXXXXXXXXXXX
Versus
XXXXXXXXXXXXXXXXXXXXXXXXXXXX
…Opp. Party
.2015.”
3. That, the Petitioner and The Opp. Party had entered into
Conciliation Act.
“XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX”
.
Copy of the agreement dtd.15.12.2015 is annexed herewith
as Annexure-P/2
Hon’ble Court:
petitioner.
C.
Court:
(morrum).
designs.
capital crisis.
etc.
Party.
Annexure-P/3
access to the entire site but vide letter dtd. 01.07.2021 the
mitigating steps for the interest of the work the Opp. Party
53, 54, 55, 73, 74 and 75 of the Indian Contract Act, 1872.
22
Series
23
Annexure-P/7
Annexure-P/8
10. That, when the matter stood thus; the Petitioner vide letter
has been taken by the Opp. Party. The said clause is quoted
“34.0 CLAIMS
in respect thereof.
Annexure-P/9
Annexure-P/10
PRAYER
PETITIONER THROUGH
New Delhi
Date:
VERIFICATION:
believed to be correct.
PETITIONER