Professional Documents
Culture Documents
(Asce) Ei 1943-5541 0000262
(Asce) Ei 1943-5541 0000262
Abstract: Since its publication in 2005, the New Engineering Contract Version 3 (NEC3) [ICE (2013). New Engineering Contract 3]
has increasingly been promoted as a relational contracting instrument for establishing mutual trust and for facilitating interorganizational
collaboration. However, only a few empirical studies have documented the use of this contract in practice. Therefore, the current research
investigates the initiation, execution, benefits, and critical factors in the implementation of NEC3-based relational practices. The lessons
learned from this implementation are compared with those derived from the application of the integrated project delivery (IPD) approach
in the United States. This study also analyzes the NEC3 Engineering and Construction Contract (ECC) [ICE (2005). NEC3 Engineering and
Construction Contract] through a case study of the first pilot project in Hong Kong to adopt this new contract. Study findings not only
reinforce the usefulness of well-established relational components (namely proactive risk mitigation, efficient change management,
and transparent cost monitoring) in the NEC3/ECC, but also highlight local experiences (such as early implementation, joint problem solving,
interorganizational team development, and regular partnering review) to enhance relational contracting further. Finally, NEC3 implementa-
tion is compared with that of the IPD. These results are beneficial to clients and contracting organizations, particularly inexperienced ones,
in terms of the proper implementation of NEC3-based relational contracting for future projects. DOI: 10.1061/(ASCE)EI.1943-5541
.0000262. © 2015 American Society of Civil Engineers.
Author keywords: New Engineering Contract Version 3 (NEC3); Engineering and Construction Contract (ECC); Integrated project
delivery (IPD); Relational contracting; Hong Kong.
The case project was commissioned by the HKSAR Drainage Serv- Contract Administration
ices Department in 2006 and was the first pilot project to adopt
As illustrated in Fig. 1, NEC3/ECC has several structured compo-
the NEC/ECC contract on a trial basis (Chan 2012). At the time,
nents to facilitate partnering practice. These components can im-
NEC3/ECC was a new contract alternative for the governmental
prove performance in terms of effective work collaboration,
client; thus, the client hired a technical consultant to support the
proactive risk mitigation, limiting cost disputes, and improved
implementation of this contract for the case project. With reference
project outcomes, among others (Wright and Fergusson 2009;
to the advice of the technical consultant, the client evaluated
Hughes 2013). Seven critical factors in good relational contracting
different contract options, prepared tender documents, consulted
practice were identified by reviewing the opinions of the client’s
government agencies, briefed bidders, and selected contractors; this
project executives (Tsui 2012a; Chan 2012). These factors are
meticulous process lasted for more than 30 months from mid-2005 listed as follows:
to early 2009 (Chan 2012). Fig. 1 illustrates a four-phase structured 1. Early implementation: In the studied case, the client adopted
application framework show the process of applying the contract to several strategies to promote partnering practice: (1) employing
the case project. a technical consultant, (2) evaluating the contract, (3) briefing
bidders, and (4) establishing start-up workshops. These efforts
Contract Evaluation and Bidding Briefing facilitated the use of NEC3/ECC and the realization of part-
nering practice.
A consultant-led management mode was adopted for the case 2. Proactive risk mitigation: Early warning systems are an effec-
project, and a corresponding traditional biparty partnering arrange- tive means of proactively mitigating risk. Such systems were
ment was implemented to align the interests of both client and con- included in the NEC3/ECC to encourage the project team to
tractor. The client evaluated six main options in terms of client response proactively to matters that may impair the perfor-
requirements and project conditions with the assistance of the tech- mance of their endeavours. In the case project, a total of 15
nical consultant. The client then selected the Option C target con- early warning notices were issued by the contractor or project
tract with activity schedule as the construction contract because this manager in relation to contract price adjustments, milestone
option aligned the interest of the contracting parties through the delay, and quality-defect correction, among others. All of
pain/gain share mechanism, fair risk sharing, and alternative design the issues related to these notices were resolved promptly
improvement (Tsui 2012b). The core clauses of the NEC3/ECC in joint meetings (Chan 2012).
were modified twofold according to the local requirements on cash 3. Efficient change management: NEC3/ECC addresses pricing
payment and based on local experience regarding the response to and managing changes (mainly claims) through quick
4. Transparent cost monitoring: This critical factor refers to the sensusDOCS 2009), AIA C195, and AIA C191 (AIA 2009)],
establishment of open-book accounting as specified in NEC3/ NEC3/ECC contracts simplify risks in multiparty contract negotia-
ECC. In this arrangement, a designated account, namely the tion and implementation as a result of its biparty setup. Nonethe-
open-book account, receives payments from a client. In turn, less, IPD are more advantageous than NEC3 for large projects that
the funds in this account are used to pay contractor and the require multiparty collaboration to provide deliverables with com-
recognized suppliers. The case project established this ac- plicated functionality requirements. Thus, NEC3 must be devel-
counting method to improve its cost transparency and payment oped further according to the setup adopted in IPD under which
management. Moreover, it facilitated cost auditing after pro- all key stakeholders involved in a project collaborate under a
ject completion (Chan 2012). building information modeling (BIM)-based virtual working envi-
5. Joint problem solving: An on-site joint office that housed staff ronment. This trend is perceived to be inevitable for future con-
from both contracting parties was established to realize the struction projects. In addition, NEC3 has more advantages than
aims of the case project. This office handled joint activities, IPD in the risk management process through a combination of sev-
such as the coordination of temporary transportation as a result eral risk mitigation and sharing methods such as capped pain/gain
of construction. Two of the senior executives involved in sharing, early warning, compensation events, and open-book ac-
the case project both stated that this mechanism contributed counts. This process can be applied to various projects in any scale.
to the successful application of NEC3/ECC (Tsui 2012a; Chan Finally, the findings of this study serve as a reference to enhance the
2012). application of the NEC-based relational contracting approach both
6. Interorganizational team development: The individuals in- locally and internationally.
volved in the case project formed the Fuk Man Club, which
consisted of staff members from the client, consultant and
contractor sides who had been within the team since the start Acknowledgments
of the project in 2012. This social organization organized sev-
eral inter-organizational team development activities, includ- The work described in this paper has been funded by The Hong
ing soccer games, volunteer services, and dragon boat Kong Polytechnic University and the National Natural Science
competitions (Tsui 2012a). Foundation of China (Grant No. 71390523).
7. Regular partnering reviews: During project execution, partner-
ing review surveys were conducted regularly among the two
on-site groups in the bimonthly partnering workshops. These References
surveys were administered among the managerial staff from
the consultant and contractor sides and among frontline staff AIA (American Institute of Architects). (2009). “Integrated project delivery
representatives. The results of separate surveys in both groups (IPD) family.” 〈http://www.aia.org/contractdocs/referencematerial/
AIAB099123〉 (Nov. 26, 2014).
revealed that, on average, the ratings of partnerships among
Chan, K. K. (2012). “Administration experience from Project Manager’s
the two groups increase gradually as the project progressed perspective.” 〈http://www.dsd.gov.hk/EN/Files/AD%2020120202%20
(Chan 2012). HKIE_revised.pdf〉. (Dec. 10, 2013).
ConsensusDOCS. (2009). “Construction contracts built by consensus.”
Post-Project Review 〈http://www.consensusdocs.org/about.html〉 (Jul. 2, 2009).
Drainage Services Department. (2013). “Technical manuals: New con-
The results of a post-project review indicated that the case project struction contract.” 〈http://www.dsd.gov.hk/EN/Technical_Manuals/
successfully met its three prescribed objectives through NEC3/ NEC_Corner/ index.html〉 (Jan. 7, 2014).
ECC implementation in the following aspects: (1) a local landmark Gerard, R. (2005). “Relational contracts—NEC in perspective.” Lean
was developed to deep public appreciation as evidenced by the nine Constr. J., 2(1), 80–86.
appreciation letters sent by the local community, (2). the project Hughes, K. (2013). “Understanding the NEC3 ECC contract: A practical
was completed 6 months ahead of schedule, and (3) the target handbook.” Routledge, Abingdon, England.
saving of 5% (HKD 1.5 million) was reached. ICE (Institution of Civil Engineers). (2005). NEC3 Engineering and
Construction Contract, Thomas Telford, London.
ICE (Institution of Civil Engineers). (2013). NEC3 April 2013 Edition
Conclusions Complete Family of Contracts, Thomas Telford, London.
Tsui, W. (2012a). “Tender preparation and administration of NEC con-
The successful application of NEC3 in the first pilot project in tracts.” 〈http://www.dsd.gov.hk/EN/Files/DD%2020120602_revised
.pdf〉 (Dec. 10, 2013).
Hong Kong not only validates the role of this relational contracting
Tsui, W. (2012b). “Why NEC in Hong Kong? DSD’s experience on NEC.”
approach in improving interorganizational collaboration and 〈http://www.dsd.gov.hk/EN/Files/DD%2020121121_revised.pdf〉 (Dec.
project delivery effectiveness but also provides new evidence for 10, 2013).
the potential application of NEC3-based relational contracting Wright, J. N., and Fergusson, W. (2009). “Benefits of the NEC ECC form
approach in small or medium projects, which is seldom addressed of contract: A New Zealand case study.” Int. J. Proj. Manage., 27(3),
in previous studies. This success has paved the way for the 243–249.