TIMELINE PEKERJAAN

INSTALASI HVAC, RF SHIELDING, QUINCH PIPE MRI


RS HARAPAN BUNDA
ID Task Task Name Duration Start Finish Predecessors Resource Names20 Aug '23 27 Aug '23 03 Sep '23 10 Sep '23 17 Sep '23 24 Sep '23 01 Oct '23
Mode TWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW
1 PEKERJAAN HVAC, RF SHIELDING, QUINCH PIPE MRI 40 days Thu 24/08/23 Mon 02/10/23

2 PEKERJAAN INSTALASI RF SHIELDING 32 days Thu 24/08/23 Sun 24/09/23

3 Pabrikasi 10 days Thu 24/08/23 Sat 02/09/23

4 Pengiriman 10 days Sun 03/09/23 Tue 12/09/23 3

5 Instalasi 12 days Wed 13/09/23 Sun 24/09/23 4

6 PEKERJAAN INSTALASI HVAC 11 days Thu 14/09/23 Sun 24/09/23

7 Pengiriman 1 day Thu 14/09/23 Thu 14/09/23 5SS+1 day

8 Instalasi 10 days Fri 15/09/23 Sun 24/09/23 7

9 PEKERJAAN EXAUST DAN PIPA QUENCH 8 days Mon 25/09/23 Mon 02/10/23

10 Pengiriman 1 day Mon 25/09/23 Mon 25/09/23 5

11 Instalasi 7 days Tue 26/09/23 Mon 02/10/23 10

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: MRI HARBUN Split External Tasks Inactive Summary Manual Summary Progress
Date: Mon 26/02/24 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only