MINUTES OF MEETING
ITEMS:
Start date
No Description Action by Status Due date
Finish date
1. ARCHIEVE CENTER WORKS
1.1 PREPARATION WORKS
1.1.1. DEMOLISH WORKS NA OPEN S:08/05/24
NA started with demolish works on Wednesday.
Demolish Work still pending due to EDTL removal of electrical cables. S: 01/06/24
EDTL cable was already removed, demolish work already done. CLOSED F:02/06/24
EXISTING ELECTRICAL POLE & ELECTRICAL FOR WORK NA OPEN S:13/05/24
EDTL will comes today to site to check.
NA to check with EDLT to understand what and when will they do.
NA to provide Electrical panel for construction works.
NA confirmed that EDTL yesterday did site visit and today will come to move the
1.1.2.
electrical line. S:27/05/25
Still pending, NA already follow up several times but still no confirmation of date. F:28/05/24
Electrical cable already removed; Electrical panel is still pending due to EDTL F:02/06/24
delivery of electrical counter. OPEN 03/06/24
Contractor's response: Letter to increase electrical power and add meter cable has
been submitted to EDTL but no team has come to move it, for the time being the
contractor is still using the existing power which is still sufficient
TREE REMOVAL NA OPEN S:13/05/24
NA confirmed that PAX will be in charge to remove, today will do site visit.
NA confirmed that to be able to cut the tree, they need EDTL to move electrical line F: 24/05/24
1.1.3 and pole first.
Still pending. Will be removed after EDTL work. S:29/05/24
Works ongoing, NA to finalize today F:30/05/24
NA OPEN F:03/06/24
Removing tree roots will be done manually because there are underground
electrical cables at the tree roots. The contractor has done the excavation with an
excavator but it caused erosion on the fence wall
POSITION OF THE BUILDING CNC OPEN S:13/05/24
During site visit executed between BA, NA and CNC, it was found the
implementation building location was in conflict with an existing building, due to a
mistake on topographic survey during design project. The solution proposed by NA
and BA is to move building position 3,50m meters to south.
CNC approved request from NA & BA to move the building 3,50m to south.
CNC to request the Design company to make the rectification of this point so it can
be submitted on the AS-BUILT drawings.
CNC The project owner has confirmed to the design consultant but they have no files
1.1.4. because the techniques that design the project are all working in the government.
The solution is the project owner, project supervision and contractor will have
excavated the new land we see if it is true that the building must move south
3.50m.
Today NA bring Survey Team to check and leveling. S:03/06/24
The location of the building has been measured and excavation has been carried out NA INFO F:08/06/24
according to the dimensions. INFO
1|Page
Sensitivity: Internal
OFFICES AND TEMPORARY STORAGE NA OPEN S:13/05/24
BA requests to NA to add more workers to speed works of office installation, as at F:17/05/24
this moment only the HSE engineer on site and no condition for other team and
expert to work on site.
3 Offices to be installing, to finalize by this week. To include AC, power sockets,
1.1.5. window facing the construction site, door with locker, Table & Chair and
bookshelves.
NA is working on ongoing works and offices will be ready by Saturday morning. F: 25/05/24
BA already moved to the office by this morning. Request to NA to provide more 2 27/05/24
desks.
NA is able to delivery two more desk by this afternoon F:03/06/24
The table is ready Close F: 05/06/24
SITE CLEARING NA OPEN S:13/05/24
Works ongoing S:27/05/24
1.1.6 F:04/06/24
Pending due to EDTL works.
Works ongoing and will be finish tomorrow
F: 05/06/24
DEMOLISH OF EXISTING DRAINAGE NA OPEN 13/05/24
NA to provide start date
1.1.7 Still pending due to EDTL works S:01/06/24
This work was completed yesterday. CLOSED S:02/06/24
Excavation of land for drainage has been installed, but is hampered by the erosion of
tree roots, causing the new channel to be eroded. F:04/06/24
2|Page
Sensitivity: Internal
SAND FILL FOR SHEAR WALL NA OPEN S:24/05/24
Dates provided from Schedule of Works F:04/06/24
Dates provided from revised Schedule of Works S:12/06/24
1.2.1.4
F:22/06/24
NA to revised the Schedule of Work. S:?
Info Schedule Work F:?
STONE FOUNDATION FOR EXTERNAL RAMP (1PC:3SN) NA OPEN S:30/05/24
Dates provided from Schedule of Works F:10/06/24
Dates provided from revised Schedule of Works S:22/06/24
1.2.1.5 F:03/07/24
NA to revised the Schedule of Work S:?
Info Schedule Work F:?
1.2.2 CONCRETE
3|Page
Sensitivity: Internal
4.3. METHOD OF STATEMENT – MS
4.3.1 NA to submit MS Excavation Works NA OPEN 21/05/24
NA to submit MS Removal of Tree
NA to submit MS Mobilization
NA to submit MS Layout Plan NA 27/05/24
NA to submit MS by this afternoon. INFO 04/06/24
4.3.1.1 LAYOUT PLAN – AC.MS.001.2024 OPEN
NA submitted MS 001 NA 10/05/24
Under Review – Not Approved BA 10/05/24
NA to submit REV 001 NA 15/05/24
INPUT
4.3.1.2 CUTTING TREE – AC.MS.002.2024 OPEN
NA submitted MS 002 NA 27/05/24
Under review – Not Approved BA 29/05/24
NA to submit REV 001 NA 03/06/24
F:04/06/24
4.3.1.3. EXCAVATION WORKS – AC.MS.003.2024 OPEN
NA submitted MS 003 NFO 27/05/24
Under Review – Not Approved 01/06/24
NA to submit REV 001 06/06/24
INFO 05/06/24
5. OTHER BUSSINESS
SAFETY NA OPEN 13/05/24
Fire Extinguisher missing
PPE to add works and who supply gloves for each utility
5.1.
Still missing. NA to supply by this afternoon. 27/05/24
Fire Extinguisher already on site but PPE for workers still missing. 03/06/24
NA to deliver complete PPE. F 04/06/24
Complete
DELAY ACCUMULATION
Accumulation of delay compared to the first Work Plan submitted after Notice of
Proceed
5.3. At this time, NA has an estimated accumulated delay of 25 days. BA INFO 27/05/24
At this time, NA has an estimated accumulated delay of 45 days. BA INFO 03/06/24
BA requests to NA to improve Schedule o Works, to increase workers on site by
provide additional hours or Night shift.
For the excavation work that was supposed to be completed on 20/06/24, we
were able to complete it on 08/06/24 and we will work extra hard to catch up
on this delay.
CONTRACTOR TEAM ON SITE
5.4. BA requests NA to present the complete team on site this week. NA INFO 03/06/24
INFO 10/06/24
BA CNC MOP NA
-Engº Christophe Nortier - Engº Augusto Napoleão Fernandes - Engº Rofinos Marcal
Copies: Participants:
☒ BA
☒ CNC
☒ MOP
☒ NA
* Dates in red are the ones presented in previous MoM that have been modified and/or exceeded or postponed
* Comments in Green are updated items introduced this week for clarify
4|Page
Sensitivity: Internal
ANNEX Nº1
PROGRESS REPORT FOR AFS & MS
5|Page
Sensitivity: Internal
NEW CONSTRUCTION NATIONAL CENTRE
ARCHIEVE FOR CENTRO NACIONAL
CHEGA
PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE FOR CENTRO NACIONAL CHEGA DATE 5-Jun-24
WALL WORKS
Plastering (1 Pc : 3 Sn)
PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE FOR CENTRO NACIONAL CHEGA DATE 5-Jun-24
Check comments
27/05/2024 AC.MS.002.2024 Method work Cut Tree 0 27-5-2024 07-06-2024 NA&QC 29-05-2024 Not Approved 03-06-2024
and submit revision
Check comments
27/05/2024 AC.MS.003.2024 Implementation Method Basement Excavation 0 27-5-2024 07-06-2024 NA&QC 01-06-2024 Not Approved 06-06-2024
and submit revision
6|Page
Sensitivity: Internal
On Thursday, the contractor put the soil in sacks to try to prevent
erosion, but with the condition of the ground water it was continuously
pumped by 2 submersible machines and 2 diesel engines so that the water
shortage could be controlled.
7|Page
Sensitivity: Internal
Saturday 08/06/24 excavation work has been completed
8|Page
Sensitivity: Internal