PROJECT: NEW CONSTRUCTION ARCHIEVE Date: 3/JUNE/2024

BUILDING CENTRE FOR CHEGA REPORT NUMBER: 004/AC/2024


Place: Chega, Balide
EMPLOYER: Centro Nacional Chega (CNC)
Meeting type: Technical ☒ Planning ☐ Extraordinary ☐ Other ☐
CONSULTANT: Bernabad Arquitectura SLP (BA)
GOVERNMENT: Ministry of Public Work
CONTRACTOR: Nazareth (NA) in JV with Quatro Chega, Blide
Next Meeting: Date: 10/6/2024 Place:
Colegas 09:00 a.m
This confirms and records our interpretation of the discussions which occurred and our understanding reached during this meeting. Unless notified in writing
within seven days of the date below, we will assume that the following interpretation as description is complete and accurate. The instruction noted in this minute
shall be applied the site

MINUTES OF MEETING
ITEMS:
Start date
No Description Action by Status Due date
Finish date
1. ARCHIEVE CENTER WORKS
1.1 PREPARATION WORKS
1.1.1. DEMOLISH WORKS NA OPEN S:08/05/24
NA started with demolish works on Wednesday.
Demolish Work still pending due to EDTL removal of electrical cables. S: 01/06/24
EDTL cable was already removed, demolish work already done. CLOSED F:02/06/24
EXISTING ELECTRICAL POLE & ELECTRICAL FOR WORK NA OPEN S:13/05/24
EDTL will comes today to site to check.
NA to check with EDLT to understand what and when will they do.
NA to provide Electrical panel for construction works.
NA confirmed that EDTL yesterday did site visit and today will come to move the
1.1.2.
electrical line. S:27/05/25
Still pending, NA already follow up several times but still no confirmation of date. F:28/05/24
Electrical cable already removed; Electrical panel is still pending due to EDTL F:02/06/24
delivery of electrical counter. OPEN 03/06/24

Contractor's response: Letter to increase electrical power and add meter cable has
been submitted to EDTL but no team has come to move it, for the time being the
contractor is still using the existing power which is still sufficient
TREE REMOVAL NA OPEN S:13/05/24
NA confirmed that PAX will be in charge to remove, today will do site visit.
NA confirmed that to be able to cut the tree, they need EDTL to move electrical line F: 24/05/24
1.1.3 and pole first.
Still pending. Will be removed after EDTL work. S:29/05/24
Works ongoing, NA to finalize today F:30/05/24
NA OPEN F:03/06/24
Removing tree roots will be done manually because there are underground
electrical cables at the tree roots. The contractor has done the excavation with an
excavator but it caused erosion on the fence wall
POSITION OF THE BUILDING CNC OPEN S:13/05/24
During site visit executed between BA, NA and CNC, it was found the
implementation building location was in conflict with an existing building, due to a
mistake on topographic survey during design project. The solution proposed by NA
and BA is to move building position 3,50m meters to south.
CNC approved request from NA & BA to move the building 3,50m to south.
CNC to request the Design company to make the rectification of this point so it can
be submitted on the AS-BUILT drawings.
CNC The project owner has confirmed to the design consultant but they have no files
1.1.4. because the techniques that design the project are all working in the government.
The solution is the project owner, project supervision and contractor will have
excavated the new land we see if it is true that the building must move south
3.50m.
Today NA bring Survey Team to check and leveling. S:03/06/24
The location of the building has been measured and excavation has been carried out NA INFO F:08/06/24
according to the dimensions. INFO

1|Page

Sensitivity: Internal
OFFICES AND TEMPORARY STORAGE NA OPEN S:13/05/24
BA requests to NA to add more workers to speed works of office installation, as at F:17/05/24
this moment only the HSE engineer on site and no condition for other team and
expert to work on site.
3 Offices to be installing, to finalize by this week. To include AC, power sockets,
1.1.5. window facing the construction site, door with locker, Table & Chair and
bookshelves.
NA is working on ongoing works and offices will be ready by Saturday morning. F: 25/05/24
BA already moved to the office by this morning. Request to NA to provide more 2 27/05/24
desks.
NA is able to delivery two more desk by this afternoon F:03/06/24
The table is ready Close F: 05/06/24
SITE CLEARING NA OPEN S:13/05/24
Works ongoing S:27/05/24
1.1.6 F:04/06/24
Pending due to EDTL works.
Works ongoing and will be finish tomorrow
F: 05/06/24
DEMOLISH OF EXISTING DRAINAGE NA OPEN 13/05/24
NA to provide start date
1.1.7 Still pending due to EDTL works S:01/06/24
This work was completed yesterday. CLOSED S:02/06/24
Excavation of land for drainage has been installed, but is hampered by the erosion of
tree roots, causing the new channel to be eroded. F:04/06/24

TEMPORARY FENCE FOR SECURITY NA OPEN S:12/05/24


Installation ongoing
1.1.8
Still pending due to EDTL
Will be done before the excavation works OPEN F:04/06/24
Finish F:06/06/24

MEASURING AND INSTALLATION BATTER BOARD NA OPEN 13/05/24


NA to provide start date
1.1.9
The work ongoing S:03/06/24
ongoing F:06/06/24
WATER FOR WORK NA OPEN 13/05/24
NA to provide installation and information for the storage and supply of water. NA
1.1.10
NA to provide and move the water tank on a temporary location by tomorrow. NA S:23/05/24
Still pending INFO 03/06/24
Due to problems with vibrations in water drilling, this work cannot be
done yet.
MOBILIZATION AND DEMOBILIZATION CONTRACTOR´S EQUIPMENT AND PLANT NA OPEN 13/05/24
NA to submit layout plan of construction site. NA
1.1.11 NA to submit layout mobilization plan revision. NA 23/05/24
Mobilization ongoing. NA F:?
Mobilization ongoing.
Heavy equipment mobilization work was carried out on Friday 05/31/24 and F: 08/06/24
excavation work has been carried out and transportation of the excavation from
the excavation site

1.2. STRUCTURAL WORKS


1.2.1 GROUND WORKS
EXCAVATION WORKS NA OPEN S:07/05/24
Dates provided from Schedule of Works F:23/05/24
Dates provided from revised Schedule of Works S:28/05/24
1.2.1.1 F:12/06/24
All works are still pending due to EDTL intervention. S:01/06/24
NA to start this work by tomorrow morning. BA requests some improvement of S:04/06/24
work to reduce the delay. F:20/06/24
Finish F: 08/06/24
SOIL IMPROVEMENT FILL (SELECTED MATERIAL) NA OPEN S:24/05/24
Dates provided from Schedule of Works F:08/06/24
1.2.1.2
Dates provided from revised Schedule of Works S:12/06/24
All works are still pending due to EDTL intervention. F:27/06/24
This work will be carried out after there is a solution to the results of the soil
conditions where the watery soil conditions do not find a hard ground surface to
place the Footplate Foundation
EXCAVATION FOR RAMP NA OPEN S:24/05/24
Dates provided from Schedule of Works F:29/05/24
Dates provided from revised Schedule of Works S:31/05/24
1.2.1.3 F:04/06/24
S:01/06/24
This work will be done after structural basement done, NA to revise the Schedule S:?
of Work. F:?
INFO

2|Page

Sensitivity: Internal
SAND FILL FOR SHEAR WALL NA OPEN S:24/05/24
Dates provided from Schedule of Works F:04/06/24
Dates provided from revised Schedule of Works S:12/06/24
1.2.1.4
F:22/06/24
NA to revised the Schedule of Work. S:?
Info Schedule Work F:?
STONE FOUNDATION FOR EXTERNAL RAMP (1PC:3SN) NA OPEN S:30/05/24
Dates provided from Schedule of Works F:10/06/24
Dates provided from revised Schedule of Works S:22/06/24
1.2.1.5 F:03/07/24
NA to revised the Schedule of Work S:?
Info Schedule Work F:?
1.2.2 CONCRETE

1.2.2.1 RAFT FOUNDATION

1.2.2.1. GEOTEXTILE MEMBRANE NA OPEN S:11/06/24


1 Dates provided from Schedule of Works F:13/06/24
Schedule has been revised according to conditions
1.2.2.1. REINFORCEMENT BARS NA OPEN S:14/06/24
2 Dates provided from Schedule of Works F:25/06/24
Schedule has been revised according to conditions

1.2.2.1. FORMWORK NA OPEN S:14/06/24


3 Dates provided from Schedule of Works F:19/06/24
Schedule has been revised according to conditions
2. DOCUMENTATION
SCHEDULE OF WORK NA OPEN 13/05/24
NA needs to provide an updated schedule of work on Microsoft Project
NA needs to provide an updated schedule of work using Microsoft Project and
2.1 submit the editable file – REV.01
NA submitted a revision today before meeting. INFO 27/05/24
Under Review BA OPEN 07/05/24
BA replied, waiting for NA to submit revision. NA OPEN INPUT
QUALITY MANAGEMENT INFO
As a general note, NA needs to submit DAILY REPORT by the next day of work,
WEEKLY REPORT by the next Monday and MONTHLY REPORT by the next week. As
Consultant also need to include their reports and submit to CNC.
2.2
NA still didn’t submit any Daily report and Weekly report. NA to submit by this NA OPEN 27/05/24
afternoon.
NA submitted Daily report until 30/05 – under review BA OPEN 08/06/24
NA to submit missing weekly report and Monthly report NA OPEN INPUT
daily, weekly and monthly reports have been provided for example
3. PROGRESS
ACTUAL vs PLAN CUMULATE PROGRESS COMPARATION OPEN
First week of work from NA, start by the second week of May, 06/05/24
3.1 Full team 5 persons move to site office to work on it. BA INFO 27/05/24
INFORMATION OF LABOR
3.2. 1 Site Engineer, 1 Skill worker and 5 Helper NA INFO 03/06/24
4. MATERIAL & EQUIPMENT
4.1 INFORMATION RELATED TO MATERIAL PROCUREMENT
NA to submit AFS and MS by this afternoon NA INFO 27/05/24
INFO 06/06/24
4.2 MATERIALS APPROVAL - AFS
4.2.1 NA to submit AFS of raw material (gravel, sand, stone, cement, water) NA OPEN 27/05/24
NA to submit AFS of equipment and material needed for cutting the tree. 03/06/24
NA to submit AFS by this afternoon. NA INFO 06/06/24
NA to submit AFS NA
4.2.1.1. REINFORCEMENT BARS – AC.AFS.001.2024 OPEN
NA submitted NA 27/05/24
Under Review – Not Approved BA 29/05/24
NA to submit REV 001 NA 03/06/24

3|Page

Sensitivity: Internal
4.3. METHOD OF STATEMENT – MS
4.3.1 NA to submit MS Excavation Works NA OPEN 21/05/24
NA to submit MS Removal of Tree
NA to submit MS Mobilization
NA to submit MS Layout Plan NA 27/05/24
NA to submit MS by this afternoon. INFO 04/06/24
4.3.1.1 LAYOUT PLAN – AC.MS.001.2024 OPEN
NA submitted MS 001 NA 10/05/24
Under Review – Not Approved BA 10/05/24
NA to submit REV 001 NA 15/05/24
INPUT
4.3.1.2 CUTTING TREE – AC.MS.002.2024 OPEN
NA submitted MS 002 NA 27/05/24
Under review – Not Approved BA 29/05/24
NA to submit REV 001 NA 03/06/24
F:04/06/24
4.3.1.3. EXCAVATION WORKS – AC.MS.003.2024 OPEN
NA submitted MS 003 NFO 27/05/24
Under Review – Not Approved 01/06/24
NA to submit REV 001 06/06/24
INFO 05/06/24

5. OTHER BUSSINESS
SAFETY NA OPEN 13/05/24
Fire Extinguisher missing
PPE to add works and who supply gloves for each utility
5.1.
Still missing. NA to supply by this afternoon. 27/05/24
Fire Extinguisher already on site but PPE for workers still missing. 03/06/24
NA to deliver complete PPE. F 04/06/24
Complete
DELAY ACCUMULATION
Accumulation of delay compared to the first Work Plan submitted after Notice of
Proceed
5.3. At this time, NA has an estimated accumulated delay of 25 days. BA INFO 27/05/24
At this time, NA has an estimated accumulated delay of 45 days. BA INFO 03/06/24
BA requests to NA to improve Schedule o Works, to increase workers on site by
provide additional hours or Night shift.
For the excavation work that was supposed to be completed on 20/06/24, we
were able to complete it on 08/06/24 and we will work extra hard to catch up
on this delay.
CONTRACTOR TEAM ON SITE
5.4. BA requests NA to present the complete team on site this week. NA INFO 03/06/24
INFO 10/06/24

Prepared by: Bernabad Arquitectura SLP Date: 13/MAY/2024

BA CNC MOP NA
-Engº Christophe Nortier - Engº Augusto Napoleão Fernandes - Engº Rofinos Marcal

- Engº José Apolinário - Engº Fatinho

- Engaº Rosita Maria

- Engº Elizário Maria

- Engaº Marzinha Noronha

Copies: Participants:
☒ BA
☒ CNC
☒ MOP
☒ NA
* Dates in red are the ones presented in previous MoM that have been modified and/or exceeded or postponed

* Words in italic are after notes meeting

* Comments in Green are updated items introduced this week for clarify
4|Page

Sensitivity: Internal
ANNEX Nº1
PROGRESS REPORT FOR AFS & MS

5|Page

Sensitivity: Internal
NEW CONSTRUCTION NATIONAL CENTRE
ARCHIEVE FOR CENTRO NACIONAL
CHEGA
PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE FOR CENTRO NACIONAL CHEGA DATE 5-Jun-24

LIST OF APPROVAL FORMS SHEET

APPROVAL REQUESTS SUBMISSION SUPERVISION REVIEW


REVISIO ANALYSIS REVISION
ISSUED BY REF NO. (NEW) DESIGNATION N
SUBMISSION DATE DEADLINE DATE RESPONSIBLE BY
DATE
STATUS
SUBMISSION
REMARKS
NUMBER DATE
Check comments
27-05-2024 AC.AFS.001.2024 Reinforcement Bars 0 27-05-2024 11-06-2024 NA&QC 29-05-2024 Not Approved 03-06-2024
and submit revision

07-06-2025 AC.AFS.002.2024 Excavation 0 07-06-2025 22-06-2025 NA&QC


Soil filling
Concrete 25 Mpa
Reinforcement Bars
Stone
Formwork
Geotextile Membrane
Waterproof Paint
Lean Concrete 17 Mpa
Anchor Bars
Trusses
WF 200x100x5.5x8 mm (including Welding Rod + bolt
and nut)
Bolts, washer and nuts Ø16
Embedded anchor 4Ø16, length 450 mm
Embedded steel plate 300x300x12 mm
Purlin CNP 100x50x20x2 mm (including, welding rods, bolts
and nuts)
Steel Angle 50x50x6 mm
Rod Bracing for Purling Ø 5
5% bolts, nuts and washer
Equal Angle Steel 100x100x7mm
Equal Angle Steel 50x50x5mm
Bolts, washer and nuts Ø12
Rod Bracing for Truss Ø 12
Concrete 17.5 Mpa
Reinforcement
Formwork
Brick Wall 1 pc :4 Sn [Concrete Block]
Plastering 1 cement : 2 sn [Sand]
Paint
CANOPY HANGER
1/8inx 5 ft.Stainless Steel Vinyl Coated Wire Rope w/looped
ends for Rectangle sun shade sails
Embedded anchor Ø10, length 250 mm
BASEMENT

WALL WORKS

Wall Block (10x20x40cm) Installing (1 Pc : 3 Sn) [Concrete


Block]

Plastering (1 Pc : 3 Sn)

RENDERS, with semen putih tiga roda + semen tonasa +


lem rajawali (agr, 1 sak "40kg" : 3 sendok : 1 bungkus)
Cementing Layer
NEW CONSTRUCTION NATIONAL CENTRE
ARCHIEVE FOR CENTRO NACIONAL CHEGA

PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE FOR CENTRO NACIONAL CHEGA DATE 5-Jun-24

LIST OF METHOD STATEMENT APPROVAL FORMS

APPROVAL REQUESTS SUBMISSION SUPERVISION REVIEW

REVISION ANALYSI REVISION


ISSUED BY REF NO. (NEW) DESIGNATION SUBMISSION DATE DEADLINE DATE RESPONSIBLE BY STATUS REMARKS
NUMBER S DATE SUBMISSION
DATE
Check comments
10/5/2024 AC.MS.001.2024 Lay Out 0 05-10-2024 20-5-2024 NA&QC 01-06-2024 Not Approved 06-06-2024
and submit revision

Check comments
27/05/2024 AC.MS.002.2024 Method work Cut Tree 0 27-5-2024 07-06-2024 NA&QC 29-05-2024 Not Approved 03-06-2024
and submit revision

Check comments
27/05/2024 AC.MS.003.2024 Implementation Method Basement Excavation 0 27-5-2024 07-06-2024 NA&QC 01-06-2024 Not Approved 06-06-2024
and submit revision

AC.MS.004.2024 Dewatering Works


Soil Improvement Fill (Selected Material)
AC.MS.005.2024 Excavation for Ramp
AC.MS.006.2024 Sand Fill for Shear Wall
AC.MS.007.2024 Stone Foundation for external Ramp
AC.MS.008.2024 RAFT FOUNDATION
AC.MS.009.2024 SHEAR WALL
AC.MS.010.2024 RETAINING WALL
AC.MS.011.2024 COLOUMN
AC.MS.012.2024 'BEAM
AC.MS.013.2024 RAMP
AC.MS.014.2024 STAIRS
AC.MS.015.2024 CANOPY (RAMP, TERRACE, LANDSCAPE)
AC.MS.016.2024 TRUSS AND STEEL WORKS
AC.MS.017.2024 CANOPY HANGER
AC.MS.018.2024 WALL WORKS (BASEMENT)
AC.MS.019.2024 TILE WORKS AND FLOOR
AC.MS.020.2024 CEILING WORK
AC.MS.021.2024 CUSHION, DOOR AND WINDOW WORKS
AC.MS.022.2024 PAINTING WORK
AC.MS.023.2024 SANITARY
AC.MS.024.2024 BENCH
AC.MS.025.2024 STAGE
AC.MS.026.2024 WALL WORKS (GROUND FLOOR)
AC.MS.027.2024 TILE WORKS AND FLOOR
AC.MS.028.2024 CEILING WORKS
AC.MS.029.2024 CUSHION, DOOR AND WINDOW WORKS
AC.MS.030.2024 PAINTING WORKS
AC.MS.031.2024 ROOFING WORKS
AC.MS.032.2024 INFORMATION BOARD
AC.MS.033.2024 Eletrical works
PLUMBING WORKS (Clean Water, Waste
AC.MS.034.2024
Water, Sewage Water, Rain Water)
AC.MS.035.2024 [TOWER (Galvanize Tank)] Tower Framing Work
AC.MS.036.2024 Concrete Foundation Work
Acsesories FITTINGS USED FOR OUTLET,
AC.MS.037.2024
INLET, OVERFLOW
AC.MS.038.2024 'TANK
AC.MS.039.2024 Pipe supply, install, testing and commissioning, etc
AC.MS.040.2024 Piping works, fitting and valve, etc
ANNEX Nº2
PHOTOGRAPHIC REPORT

6|Page

Sensitivity: Internal
On Thursday, the contractor put the soil in sacks to try to prevent
erosion, but with the condition of the ground water it was continuously
pumped by 2 submersible machines and 2 diesel engines so that the water
shortage could be controlled.

Contractors provide temporary solutions to prevent soil erosion

7|Page

Sensitivity: Internal
Saturday 08/06/24 excavation work has been completed

8|Page

Sensitivity: Internal