PORT ACCESS ELEVATED HIGHWAY PROJECT

SECTION 1 FROM STA.0+000 TO STA.5+270


Contract No: RDA/ADB/OCB/PAEH/CW/01
EMPLOYER :
Weather Sunny
ROAD DEVELOPMENT AUTHORITY
ENGINEER:
Sedalia Associates, Inc. Joint Venture With Roughton International Ltd And MG Consultants (Pvt.) Date: 2-May-2024
Limited
CONTRACTOR:
Day Not Holiday
CCECC-HPRB-HNRBI JV

DAILY WORK SCHEDULE PLAN


Work Time
No: Category Section Work Description Officer In Charge Contact No: Inspection Time Planned Work Ending time
07:30-18:30 18:30-07:30

1 Pier 23-27 Duct outer backfilling. Mr. Rifky (077) 796 8479 ● till 18:00

2 Utility Pier 83 Buildings modifications Mr. Rifky (077) 796 8479 ● till 18:00

3 Excavations for additional duct to finance department Mr. Rifky (077) 796 8479 ● till 18:00

4 Pier 03-04 RHS: Parapet wall Outer wall concrete work Mr.Isuru (075) 901 6207 ● ● 10:30 till 20:00

5 Pier 04-05 RHS: Parapet wall Outer wall formwork fixing. Mr.Isuru (075) 901 6207 ● ● till 20:00

6 Pier 04-05 : Parapet wall Center medium bottom parapet concrete work Mr.Isuru (075) 901 6207 ● ● 14:30 till 20:00

7 Pier 06-07 : Parapet wall Center parapet wall rebar work Mr.Isuru (075) 901 6207 ● ● till 20:00

8 Pier 106-107 : Parapet wall Center combine parapet wall balance re-bar work Mr.Chinthaka (071) 437 1854 ● ● till 20:00

9 Pier 111-113 RHS : Parapet wall Main line combine parapet wall re-bar work. Mr.Chinthaka (071) 437 1854 ● ● till 02:00

10 Pier 91-92 RHS (4+171.5-4+189): Parapet wall Form work erection and concrete pouring Mr.Pasan (077) 948 4556 ● ● 18:00 till 20:00

11 Pier 90-91 RHS: Parapet wall Inner parapet formwork Mr.Ruwan (070) 463 1428 ● ● till 20:00

12 Pier 98-99 RHS: Parapet wall Outer parapet concrete Mr.Ruwan (070) 463 1428 ● ● 10:30 till 20:00

13 Pier 100-101 : Parapet wall Combine parapet wall Concrete Mr.Ruwan (070) 463 1428 ● ● 15:00 till 20:00

14 Pier 101-102 RHS : Parapet wall Inner wall concrete Mr.Ruwan (070) 463 1428 ● ● 16:00 till 20:00

15 Pier 102-103 LHS : Parapet wall Inner parapet concrete Mr.Ruwan (070) 463 1428 ● ● 12:00 till 20:00

Elevated Bridge
16 Pier 104-105 RHS : Parapet wall Inner wall concrete Mr.Ruwan (070) 463 1428 ● ● 11:30 till 20:00
Construction

17 Pier 105-106 LHS : Parapet wall Inner wall concrete Mr.Ruwan (070) 463 1428 ● ● 14:30 till 20:00

18 Pier 108-109 LHS: LC-L144 : Parapet wall Light post concrete Mr.Ruwan (070) 463 1428 ● ● 9:30 till 20:00

19 Pier 108-109 LHS: LC-L145 : Parapet wall Light post concrete Mr.Ruwan (070) 463 1428 ● ● 9:00 till 20:00

20 Pier 112-113 : Parapet wall Main line RHS combine parapet formwork Mr.Ruwan (070) 463 1428 ● ● till 20:00

21 0+400 to 0+560 LHS/RHS: Ramp 03 Cutting of the existing asphalt layer Mr.Shashi (071) 886 8722 ● ● till 20:00

22 0+400 to 0+560 LHS/RHS: Ramp 03 Excavation of the MSE base Mr.Shashi (071) 886 8722 ● ● till 20:00

23 Pier 79 RHS: Pile cap Excavation work Mr.Kumara (077) 518 0838 ● ● till 20:00

24 Pier 80: Capping beam Supporting structure work Mr.Sanjeewa (077) 482 3509 ● ● till 20:00

25 Pier 81: Capping beam Rebar work. Mr.Lakshan (076) 685 9238 ● ● till 20:00

26 Pier 78: Capping beam End sealing rebar work and form work fixed and concrete pouring. Mr.Chanaka (077) 846 8115 ● ● till 20:00

27 Pier 62-63 (Launcher 01) Launcher moving to backwards Mr.Sadaruwan (071) 439 1705 ● ● till 02:00

28 Pier 85-86 : Launching Span tendon stressing Mr.Sadaruwan (071) 439 1705 ● ● till 02:00

Prepared By Checked and Approved By:

Planning Engineer - H.M.G.J.Bandaranayake Deputy Technical Manager: Zhao Hong Hui