1.

Integrating Activities do not include

Ans- PERFORMING ACTIVITIES TO PRODUCE PROJEC

2.What could be the best approach to engage your stakeholders falling in the category

Ans-MANAGE CLOSELY

3.Project information has been distributed according to the communications management plan. Some
project deliveral One stakeholder expressed surprise to the project manager upon being informed of a
previously published change to of the change. What should the project manager do?

Ans-REIVIEW THE COMMUNICATIONS PLAN AND MAKE RI

4.You have four projects from which to choose one. Project A is being done over a six-year perod and
has a Net Present ' of $30,000. Project C is being done over a five- year period and has an NPV of
$40,000. Project D is being done over?

Ans- PROJECT A

5.One of the problems with projects has been that the knowledge gained by the project teams are lost
when they go aw the Integration Knowledge Area of the PMs framework. A k

Ans-RISK REGISTER

6.Select The appropriate description of Bus

Ans-DESCRIBES THE NECCESARY INFORMATION FROM BUISNESS STAND POINT TO DETERM

7. The process Close Project or Phase does r

Ans-QUALITY VERIFICATIONS

8. The Project Selection Committee of Trent International Inc. has decided the following criteria for
project selection. Use points given to projects for the four projects under discussion are as follows:
Project Alphe- New Technology-5 High StHigh Standards = 2, Attract Young people=- 3. Cost effective=5
Project Gam- New Technology= 1, High Standards -Standerds - 1 Attract Young people - 1, Cost effective
=2 What i

Ans- 67

9.If in a software development project Probability of Design issue is 10% with an associated cost of
$5000, the Probal resource issues is 30% with an associated cost of $10 000 What is the

Ans-4500

10-Which one of the following can be included as a purpose of Pr

Ans- MAKING CHOICES ABOUT RESOURCE ALL

11. Select The appropnate description of

Ans-DESCRIBES THE ORGANISATION'S PLACE


12.A large, one-year telecommunications project is about hallway done when you take the place of the
previous project nwould like to see the project's communications requiroments and what technology is
being used to

Ans-COMMUNICATIONS MANAGEMENT

13. Typically, in an I project environment, the body responsible for approving

Ans- CHANGE CONTROL BOARD

14.Which of the following is not included in a pi

Ans-THE BUISNESS NEED FOR THE PRO

15.Integration Management Processes do n

Ans-DEVELOP COMMUNICATION PLI

16.Documents business needs, current understanding of the customer's needs, and ne

Ans-DEVELOP PROJECT CHARTER

17.What is not correct about the Project

Ans-CONTAINS HIGH LEVEL INFORMAT

18.Select the approprate output from the process called

Ans-FINAL PRODUCT, SERVICE OR RESULT TR

What is not correct about the identification of th

19.You want to prepare a chart showing the current status of your key stakeholders and the status y

Ans-STAKEHOLDER ENGAGMENT ASSESME

20.What is not correct about Strategic Ob

Ans-DESCRIBES MEASURES OF ACHEIVEI

21.It provides lessons learned and the release of organizational re

Ans-CLOSE PROJECT OR PHASE

22.What Is not correct about Flow Down O

Ans-PROJECT MANAGERS ARE RESPONSIBLE FOR PREPARING


23.As per our learning during this course what are the two

Ans-EXPLICIT AND TACIT

24.About midway through the project, the project manager learns that most members of the project
team do

Ans-REVISE THE COMMUNICATION PLAN APPROPRIATELY TO MEET INFO

25.What could be the best approach to engage your stakeholders falling in the categor

Ans-KEEP MONITORING

26.Project managers spend of their time communicating with team members and other project stak

Ans-90%

27.Which of the following is not a stakel

Ans-THE EMPLOYEE'S ATTORNEY

28.Select the appropriate output from the process called 'N

Ans-LESSON LEARNED REGISTER

29.Selert The approprate description of "Stater

Ans-NARRATIVE DESCRIPTION OF PRODUCTS, SERVICES, OR RESULT!

30.The Project Selection Committee of Trent International Inc. has decided the 1

Ans-ALPHA

31.Your manager gives you the project charter that includes the high-level project requirements anc

Ans-IDENTIFY THE STAKEHOLDER TO MAKE SURE THEIR REQUIREMENTS ARE

32.Select the appropnate output from the process called "Dire

Ans-WORK PERFOR,AMCE DATA

33.It allows for documented changes within the project to be considered in an integrated fashion while
reducing project objectives or plans?

Ans-PERFORM INTEGRATED CHANE CON

34.What could be the best approach to engage your stakeholders falling in the categor

Ans-KEEP SATISFIED

35.Select the appropnate output from the process called 'Deve

Ans-PROJECT MANAGEMENT PLAN


36.You are the project manager for Spade International. Since you don't sleep much, you get a lot of
project work done $25,000 per quarter for the first two years and then $75,000 per quarte

Ans-39 MONTHS

37.The process of leading and performing the work defined in the project management plan and implem

Ans-DIRECT AND MANAGE PROJECT W

38.A medical doctor who has volunteered to actively participate in a project relating to the use of
intormatio

Ans-LEADING STAKEHOLDER

39.You have to create a new project in MS Project. If in your opinion you can start a project Today you
need 6 month:Information Menu

Ans-SELECT THE DATE AS TODAY'S DATE AND DURATION OI

40.You want to display on your wall a graphic scheme showing the importance of your key stakeholders
witl

Ans-POWER/ INTEREST GRID