Professional Documents
Culture Documents
RDSO - Rail - Bridges - Jan 2014
RDSO - Rail - Bridges - Jan 2014
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
Agenda Of
Eighty Second Meeting Of
Bridge & Structures Standards Committee
(30th & 31st January - 2014)
At Bangalore
SUBJECT INDEX
1042 Periodicity of changing of oil in oil bath for roller bearing. 33-34
1047 Formulae for the estimation of scour depth at bridge piers. 67-86
**********
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039
NOTES BY SECRETARY
1. There is growing interest with in the reinforced concrete industry in using higher
strength reinforcing steel. This interest is primarily driven by truncated production
of good quality Fe 415 grade bars by the manufacturers and increasing
production of Fe 500/Fe 500D and higher grade bars(TMT bars). Various Zonal
Railways have been requesting RDSO for adoption of Fe 500 and higher grade
bars also in standard drawings of RCC bridge structures issued by RDSO.
2. Specification of HSD steel bars and wires for concrete reinforcement are covered
in IS:1786.
Important codal provisions along with relevant clauses of IS, IRC & IRS CBC are
as below:
(a) IS:1786-2008 : High strength deformed steel bars and wires for
concrete reinforcement –Specification
Clauses which deals with chemical and physical properties have been
discussed below:-
Carbon 0.30 0.25 0.25 0.30 0.25 0.25 0.30 0.25 0.30
Sulphur 0.060 0.045 0.045 0.055 0.040 0.040 0.055 0.040 0.040
Phosphorous 0.060 0.045 0.045 0.055 0.040 0.040 0.050 0.040 0.040
Sulphur and 0.110 0.085 0.085 0.105 0.075 0.075 0.100 0.075 0.075
Phosphorous
1
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039
1 2 3 4 5 6 7 8 9 10 11
i 0.2% proof 415 415 415 500 500 500 550 550 600
stress/yield
stresses, Min,
2
N/mm
iii TS/YS ratio, ≥1.10, ≥1.12, 1.25 ≥1.08, ≥1.10, 1.25 ≥1.06, ≥1.08, ≥1.06,
2
N/mm but TS but TS but TS but TS but TS but TS but TS
not less not less not less not less not less not less not less
than 485 than than 545 than than 585 than 600 than 660
2 2 2 2 2
N/mm 500 N/mm 565 N/mm N/mm N/mm
2 2
N/mm N/mm
iv Elongation, 14.5 18 20 12 16 18 10 14.5 10
percent, Min.
v Total -- 5 10 -- 5 8 -- 5 --
elongation at
max. force,
percent, Min.
2
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039
(d) IRC: 18-2000, Design criteria for Pre-stressed Concrete Road Bridges
(Post Tensioned Concrete)
Clause 14.1.4 restricts the value of yield strength of shear bars to 415
N/mm2.
(e) IRS: CBC-1997, Indian Railway standard code of practice for Plain,
Reinforced & Prestressed concrete for general Bridge Construction
(i) Clause No. 15.4.3.2 specifies that characteristic strength of stirrup
reinforcement should not be greater than 415 N/mm2.Clause 15.4.4.4
specifies similar provision for torsional reinforcement.
(ii) Clause No. 15.9.4.1 and 15.9.4.2 specifies minimum areas of main and
secondary reinforcement in terms of cross-sectional area for Fe415
and Fe250 grade of steel.
(iii) Clause No. 15.9.9 specifies similar provisions for shrinkage and
temperature reinforcement.
(iv) However Clause No. 15.4.2.2 accounts for higher grade of steel for
calculation of ultimate moment of resistance.
(v) Clause No. 15.9.6.2 specifies ultimate anchorage bond stress for plain
bars in compression and tension. For deformed bars, it is increased by
40% than that of plain bars.
3
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039
6. Adoption of provisions in IRS Concrete Bridge Code for use of Fe 500 and
higher grade steel rebars
(a) It is noted that industry and manufactures are increasing production of Fe
500 and higher grade HSD bars and D & S grade rebars have increased
ductility to suit seismic design requirements. Further, IS & IRC codes have
already been modified/revised to incorporate provisions for use of higher
grade HSD steel rebars.
4
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039
**********
5
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
Existing Provisions of IRS Concrete Bridge Code affected by Grade of Steel and
Proposed Provisions
IRSCBC Exiting provision of IRS CBC Proposed provision of IRS CBC
Clause
No.
4.5.1 The reinforcement shall be any of The reinforcement shall be any of
the following : the following :
a) Grade-I mild steel and medium
a) Grade-I mild steel and medium
tensile steel bars conforming to
tensile steel bars conforming to
IS:432 (Part-I)
IS:432 (Part-I)
b) High strength deformed steel
b) High strength deformed steel bars conforming to IS: 1786.
bars conforming to IS:1786. c) Thermo-mechanically Treated
c) Thermo-mechanically Treated (TMT) Bars satisfying
(TMT) Bars satisfying requirements of IS: 1786.
requirements of IS:1786. d) Rolled steel made from structural
steel conforming to IS: 2062 Gr.
d) Rolled steel made from A and Gr. B.
structural steel conforming to Note: For seismic zones III, IV & V;
IS:2062 Gr.A and Gr. B. HYSD steel bars having minimum
elongation of 14.5 percent and
confirming to other requirements of
IS: 1786 shall be used.
Discussion:
As per clause 5.3 of IS:13920-1993, ductile detailing of reinforced
concrete structures subjected to seismic force-Code of Practice
applicable for seismic zone III, IV and V, Steel reinforcements of grade
Fe 415 (see I S 1 7 8 6 : 1 9 8 5 ) o r l e s s o n l y s h a l l b e u s e d .
However, high strength deformed steel bars, produced by the thermo-
mechanical treatment process, of grades Fe500 and Fe550,
having elongation more than 14.5 percent and conforming to other
requirements of I S 1 7 8 6 : 1 9 8 5 m a y a l s o b e u s e d f o r t h e
reinforcement.
As per Note to clause 18.2.3 of IRC 112: 2011
Notes: (1) Elongation on a gauge length of 5.65√A, where A is the cross
sectional area of the test piece, when tested in accordance with IS 1608-
1995.
(2) For seismic zones III, IV & V; HYSD steel bars having minimum
elongation of 14.5 percent and confirming to other requirements of IS
1786 shall be used.
6
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
7
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
8
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
Discussion:
As per Clark’s commentary on concrete bridge design to BS 5400
(page 67), this value is restricted to 425 N/mm2. This is because the
data considered by the shear study group indicated that the yield stress
of shear reinforcement should not exceed about 480 N/mm2 in order
that it could be guaranteed that the shear reinforcement would yield at
collapse prior to crushing of concrete.
As per Clause 39.4 of SP: 24-1983, the reasons for limiting fy value to
415 N/mm2 for shear reinforcement are as follows-
- The code is concerned with crack width limitations as crack width and
grade of steel is interrelated.
- It becomes difficult to bend higher strength steel bars and sharp edges
may get damaged during bending.
15.4.4.4 Treatment of various cross No change.
sections :
a) Box sections- The torsional
shear stress shall be calculated as :
T
vt ……. (equation-9)
2hwo Ao
where,
hwo is the wall thickness where the
stress is determined;
Ao is the area enclosed by the
median wall line.
Torsion reinforcement shall be
provided such that:
A st T
……(equation 10)
Sv 2A o (0.87f yv )
A sL A st f yv
……(equation 11)
SL Sv f yL
where,
T is the torsional moment due to
the ultimate loads;
Ast is the area of one leg of a
closed stirrup of a section;
9
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
10
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
11
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
reinforcement. reinforcement.
For a box, T or I section ba shall be For a box, T or I section ba shall be
taken as the average breadth of the taken as the average breadth of the
concrete below the upper flange. concrete below the upper flange.
The minimum number of longitudinal The minimum number of longitudinal
bars provided in a column shall be bars provided in a column shall be
four in rectangular columns and six four in rectangular columns and six in
in circular columns and their size circular columns and their size shall
shall not be less than 12mm. In a not be less than 12mm. In a helically
helically reinforced column, the reinforced column, the longitudinal
longitudinal bars shall be in contact bars shall be in contact with the helical
with the helical reinforcement and reinforcement and equidistant around
equidistant around its inner its inner circumference. Spacing of
circumference. Spacing of longitudinal bars measured along the
longitudinal bars measured along periphery of the columns shall not
the periphery of the columns shall exceed 300mm. The total cross
not exceed 300mm. The total cross sectional area of these bars shall not
sectional area of these bars shall not be less than 1 % of the cross sections
be less than 1 % of the cross of the column or 0.15P/fy, whichever is
sections of the column or 0.15P/fy, the lesser, where P is the ultimate
whichever is the lesser, where P is axial load and fy is the characteristic
the ultimate axial load and fy is the strength of the reinforcement.
characteristic strength of the
A wall cannot be considered as a
reinforcement.
reinforced concrete wall unless the
A wall cannot be considered as a percentage of vertical reinforcement
reinforced concrete wall unless the provided is at least 0.4%. This vertical
percentage of vertical reinforcement reinforcement may be in one or two
provided is at least 0.4%. This layers.
vertical reinforcement may be in one
or two layers.
Discussion:
As per clause 26.5.1.1 of IS 456:2000 for beams. The minimum area
of tension reinforcement shall be not less than that given by the
following:
As/ bd =0.85/fy
Where,
AS = minimum area of tension reinforcement,
b = breadth of beam or the breadth of the web of T-beam,
d = effective depth, and
fy, =characteristic strength of reinforcement in N/mm2
12
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
13
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
Discussion:
As per clause 26.5.2.1 of IS 456:2000,the mild steel reinforcement in either
direction in slabs shall not be less than 0.15 percent of the total cross
sectional area. However, this value can be reduced to 0.12 percent when
high strength deformed bars or welded wire fabric are used.
15.9.9 Shrinkage and temperature Shrinkage and temperature
reinforcement - To prevent reinforcement - To prevent excessive
excessive cracking due to shrinkage cracking due to shrinkage and thermal
and thermal movement, movement, reinforcement shall be
reinforcement shall be provided in provided in the direction of any
the direction of any restraint to such restraint to such movements. In the
movements. In the absence of any absence of any more accurate
more accurate determination, the determination, the area of
14
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
15
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
where,
As is the area of effectively
anchored longitudinal tensile
reinforcement (see 15.9.7)
and prestressing tendons
(excluding debonded
tendons);
fy is the characteristic strength
of the longitudinal
reinforcement and
16
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1039 (Annexure)
Discussion:
Same as in clause 15.4.3.3 and 15.4.4.4 above.
16.4.5.2 Stresses and Reinforcement – No change
Calculations for torsion are only
required for the ultimate limit state
and the torsional shear stresses
shall be calculated assuming a
plastic shear distribution.
Calculations for torsion shall be in
accordance with 15.4.4 with the
following modifications. When
prestressing steel is used as
transverse torsional steel, in
accordance with equations 10 and
10(a) or as longitudinal steel, in
accordance with equation 11, the
stress assumed in design shall be
the lesser of 415 N/mm2 or (0.87fpu –
fpe).
The compressive stress in the
concrete due to prestress shall be
taken into account separately in
accordance with 15.4.4.5
In calculating (v +vt), for comparison
with vtu in Table 17, v shall be
calculated from equation 8,
regardless of whether 16.4.4.2 or
16.4.4.3 is critical in shear.
For concrete grades above M40 the
values of vtu given in Table 17 may
be increased to 0.75 fck but not
more than 5.8 N/mm2.
Discussion:
Same as in clause 15.4.3.3 and 15.4.4.4 above.
********
17
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1040
NOTES BY SECRETARY
1. Central Railway vide their letter No. W.133.BR.109 dated 28.01.2013 have raised
the issue of standardization of box pushing technique for construction of Road
Under Bridges (RUBs). It is stated that there is lot of emphasis on closure of level
crossings gates by construction of RUB/ROB and diversion. Generally following
methods are adopted for construction of RUBs:
i) Box Pushing
ii) Cut and cover
iii) In-situ construction by insertion of RH Girders.
Now a days in-situ construction by insertion of RH Girders is not generally
preferred as it involves multiple traffic blocks as well as speed restriction for
longer durations. Tightening of fixtures is also required to be carried out daily in
this method. Cut and Cover method is faster and effective but requires traffic
block of 4 to 7 hours depending on bank height and size of the box. At several
locations, it is very difficult to provide such long duration traffic blocks and in such
cases Box Pushing method comes as a rescue.
The Box Pushing method is very effective as in this method no traffic blocks are
required. Even though the method is used very commonly in Indian Railways but
no clear cut technical guidelines are available to field engineers regarding
minimum cushion, suitable soil type, jacking equipment, cutter shield and design
stresses etc. As such technical guidelines for Box Pushing method are required
to be framed. Draft technical guidelines proposed by Central Railway are
enclosed as Annexure-1.
2. RDSO has issued the standard drawings of RCC boxes for in-situ as well as
segmental construction (using cut and cover method) for various spans/heights
and earth fill depths to facilitate construction of RUB/Limited Height Subway
(LHS).The Box Pushing method is site specific and entire scheme has to be
designed and developed on case to case basis depending on site conditions e.g.
bank height, size of the box, type of the soil etc. cutter shield, thrust bed and
jacking requirements have to be suitably designed. RDSO has not been involved
18
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1040
**********
19
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1040 (Annexure)
1.0 Pre-requisites -
1.1 Soil investigation should be done in advance to ascertain the type of strata
to minimize the problem/difficulty during execution.
1.2 Box pushing should be done in good soil and soft/weathered rock only.
1.3 Pushing in hard rock or clay strata should be avoided.
1.4 Thrust bed and jacking pocket should be properly designed to withstand
the pressure.
1.5 There should be minimum 1.5 m. earth cushion available above top
surface of box.
1.6 There should be proper arrangement/detailing for provision of drag sheet
for smooth operation without snapping/tearing of sheet during operation.
2.0 Safety precaution –
2.1 Before execution –
2.1.1 CRS sanction and proper DCN should be in place.
2.1.2 All the temporary caution boards should be provided and protection
arrangement should be done.
2.1.3 Necessary protection equipment should be in place and in working order.
2.1.4 Adequate lighting and communication arrangement should be ensured.
2.1.5 Sufficient sand bag/filling material should be ready for emergency.
2.1.6 Availability of sufficient number of manpower and supervision should be
ensured.
2.2 During execution –
2.2.1 Pushing should be done under traffic block with proper block protection.
2.2.2 Cutting edge should always be buried in the earth.
2.2.3 Alignment and level should be checked before and after every operation of
jacking and necessary corrections should be applied.
2.2.4 Smooth operation and rolling of drag sheet should be ensured.
2.2.5 Sufficient No. and capacity of jack should be available so that jacking
should be done with 50% of rated capacity of jack.
2.2.6 Track parameters should always be kept under watch and necessary
corrective action should be taken, throughout during operation.
20
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1040 (Annexure)
**********
21
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
NOTES BY SECRETARY
E.C. Railway has raised the issue of Mechanization of Painting of Bridge Girders
and for including painting by airless spray method in Para 217 sub Para 4 (h) of IRBM
vide their letter no. W-3/365/09/Br.SSC/P-II/1828 dated 24/31-12-2013. The issue was
examined and deliberated in RDSO. Painting over Bridges is normally done in three
coats i.e. Initial Coat, Inter-mediate Coat & Final Coat as per the conventional painting
system. As painting was done departmentally and work ethics was high, system went
smoothly for decades in which quality of coats was judged subjectively. However with
advent of spray method and getting painting on contract basis, quality issues have
become important. Minimum DFT is best objective criteria to judge conventional
painting system, whether same is done manually or by spray method. DFT criteria is
already prescribed for epoxy based, metalizing etc. but is not provided in the
conventional Painting System. Hence there is need to provide DFT criteria in
Conventional Painting System so as to replace the old subjective criteria. Therefore,
Minimum DFT (Dry Film Thickness) have been proposed to be incorporated in Para No.
39 of IRS: BI-2001 and Para No. 217,218,615 of IRBM (Indian Railway Bridge Manual).
There proposed changes have been vetted by M&C Directorate.
22
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
23
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
24
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
25
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
26
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
27
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
finishing coat should be generally coats of paint to IS: 13607 with with 20 μ
matching with the Smoke Grey 20 μ minimum dry film minimum dry
thickness (DFT) in each coat film thickness
colour/Shade No. ISC 692 (DFT) in each
with colour/shade to be
28
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
29
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
30
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
Each coat of paint shall be left to Each coat of paint shall be left to
dry till it sufficiently hardens dry till it sufficiently hardens
before the subsequent coat is before the subsequent coat is
applied. applied.
7. Para 218.1 (iv) (a) After the Para 218.1 (iv) (a) After the
metallising, any oil, grease etc. metallising, any oil, grease etc.
should be removed by thorough should be removed by thorough
wash with a suitable thinner and wash with a suitable thinner and
allowed to dry for 15 minutes. allowed to dry for 15 minutes.
The painting may be applied by The painting may be applied by
brush or by spray. The first coat brush or by airless spray. The airless added
shall be wash primer to first coat shall be wash primer to
with 8-10 μ
SSPCPT-353T or Etch primer to SSPCPT-353T or Etch primer to minimum dry
IS: 5666. IS: 5666 with 8-10 μ minimum film thickness
Para 218.1 (iv) (b) The second dry film thickness (DFT).
(DFT) added
coat shall be zinc chromate Para 218.1 (iv) (b) The second
primer to IS : 104. The zinc coat shall be zinc chromate with 20 μ
chrome should confirm to type 2 primer to IS : 104 with 20 μ minimum dry
of IS : 51. The 3rd and 4th coats minimum dry film thickness film thickness
(DFT) added
shall be aluminium paint to IS : (DFT). The zinc chrome should
31
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1041
*********
32
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1042
NOTES BY SECRETARY
33
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1042
recommended that the oil shall be invariably replaced after a service life
of 20 years. (Even if Oil appears to be usable)
**********
34
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1043
NOTES BY SECRETARY
CBE, North Central Railway vide letter No. 136-W/Br/BSC Pt-III dated
17.12.2013 has raised the following issue:
At present RDSO has issued drawing no. B-11040 for 20.4m RH girder with total
girder height of 940mm. Standard design of RH girder may further be reviewed for
lesser height. Total height including rail & sleeper should be ideally limited to 700mm.
For this an arrangement may be designed, probably with coupled girders where rail can
directly be laid on the girder without use of sleepers. With reduced height RH girders,
RCC Box can be laid without removing the RH girder and hence will help in reducing the
block time.
RDSO has studied the issue and the following is brought out:-
1) Steel Reduced Height girders also called RH girders are used as temporary
girders for restoration of traffic in the event of washouts etc. or for passing trains
over temporary works for bridge construction, crossings, etc. RDSO has issued
drawings for three spans, details of which are given below:
2) All the above drawings are for two single leaves so that sleepers are provided
across the girders as shown below:
35
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1043
3) CBE, NC Railway vide his letter no. 136-W/Br/BSC Pt-III dated 17.12.2013
has asked for reduction of height of 20.4m RH girder including rails and sleepers
to 700mm and has suggested use of “couple” (Duplicated) girders where rail can
directly be laid on girder without use of sleepers. The benefit of this arrangement
is that the RCC box can be laid without removing the RH girder and hence will
help in reducing the block time. The general arrangement of such girders is
shown in sketch below:
36
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1043
4) The matter has been examined at RDSO and the following points require
consideration:
37
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1043
(iv) Maintenance of Track: The track on existing RH girder shall be just like
any other bridge and standard sleepers like steel channel sleepers,
composite sleepers, wooden sleepers, etc. with standard fittings can be
used. The adjustment of gauge/alignment etc. can be done conveniently. For
duplicated girders, canted bearing plate of steel channel sleepers will have to
be incorporated in the girders. The space available for tightening of fittings is
less and the adjustment of gauge/ alignment/ cross levels is not easily
possible.
(v)Fabrication of Girders: Proper welding/riveting of the brackets for rail seat
is not possible because of less space available. Extra care required to ensure
that the final track parameters like gauge and alignment are achieved.
38
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1043
**********
39
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044
NOTES BY SECRETARY
1. Elastomeric Bearings are design based on UIC 772-2R. Elastomeric Bearings for
ROB are designed as per IRC-83 Part-II Code. For reference purpose BS 5400: Sec.
9.2 is also used in the design. These bearings are in use over Indian Railway since last
more than 2 decades.
40
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044
Note:- For Elastomeric Bearings, there has to be minimum vertical stress which shall be
not less than 2 MPa, whereas mean vertical stress is from 10 to 12 MPa.
Therefore where contribution of Dead Load is less, these bearings are not used
as same may lead to slip condition.
4. Life of Elastomeric Bearings is not defined in any of the Codes and Manuals.
However life of Elastomeric Bearings depends upon following factors:-
(i) Stress Range & Stress Cycles.
(ii) Shear Stress & Cycles.
(iii) Shape Factor.
(iv) Translational & Rotational Movements.
(v) Temperature Variations. (Ideal operating temperature is 20 + 50C)
(vi) Moisture Variations.
(vii) Other Environmental Condition like severe, Extreme Environment,
Exposure to chloride.
(viii) Exposure to Ozone.
(ix) Exposure to Ultraviolet Rays.
(x) Exposure to Dirt, Debris.
(xi) Physical Damage, if any during service period.
(xii) Damage to cover & exposure of Steel Plates to corrosion.
(xiii) Vulcanizing Conditions (Uniform or Non Uniform). Age from date of
Vulcanization (Age Hardening).
41
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044
(xiv) Homogeneity of Elastomer through the surface & body of the bearings.
(xv) Variation by 20% more than in stiffness of bearings w.r.t. mean value of
lot.
5. Preliminary Literature Survey was done by RDSO and following important points
were noted:-
Outer Rubber/Elastomer Cover of 6 – 12 mm is kept for environmental
protection.
7. Another option can be that bearings of different ages be taken out from the
bridge and tested for their properties vis-a-vis original properties.
**********
42
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure A)
43
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure A)
44
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure A)
45
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure B)
46
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure B)
47
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure B)
48
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure B)
49
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure C)
50
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1044 (Annexure C)
51
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045
NOTES BY SECRETARY
CBE, South Western Railway vide letter No. SWR/W.81/BSC Meeting dated 26th
Dec., 2013 has raised the following issue:
RDSO standard drawings for ROB are available for the spans of 18m, 24m, 30m
and 36m only. Many of the proposed ROBs crossing the yards and multiple lines are
proposed with spans more than 36m. Also many times due to the constraints in altering
alignment of roads, ROBs are proposed with skew angle as high as 45 degrees.
Proposals for construction of ROBs in lieu of level crossings are coming up. In view of
this, RDSO can introduce spans larger than 36.0m and also standardize the already
existing spans with different skew angles.
RDSO has studied the issue and the following is brought out:-
RDSO has undertaken the design of 50 m span BOW string arch girder road over
bridges and the drawings are expected to be issued shortly.
1. The issue of “Skew effect on bridges and their implications” was previously
discussed as Item no. 900 in 75th and 76th meetings of Bridge and Structures Standards
Committee. In 75th meeting, analysis and design of concrete skew slabs was
discussed and the analysis procedure/ detailing etc were discussed. It was bought out
that:
b. Correspondingly, the deflection and the reaction is reduced towards the acute
angled corner.
52
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045
e. The discussion also brought out that for spans upto 200, the design is done as
spanning along center line of the traffic. The reinforcement thus obtained is
multiplied by secant of the skew angle.
f. For skew angles between 200 and 500, the slab is designed perpendicular to
support and the reinforcement thus obtained is multiplied by secant of the skew
angle.
h. For skew angles upto 300, the main reinforcement shall be parallel and
perpendicular to supports.
k. Railway Board Orders on 76th BSC: The item may be closed. (It is mentioned
that specialized software for carrying out the analysis is not available)
2. The Road Over Bridge spans designed by RDSO are having longitudinal girders
which support the deck slab. When the design was undertaken in 2010-11, the issue of
effect of skew was taken into consideration. From the literature survey conducted at the
time, the following was noted:
(a) IRC-24-2001 para 507.9 mentions that for skew bridges the detailed
analysis of forces shall be required. However, if the angle of skew is within
150, such detailed analysis may not be necessary. (Annexure 1)
(b) From the paper “Effect of bending moment and torsion in T-beam skew
bridge decks” by Trilok Gupta, Anurag Mishra and Ravi K Sharma, the
effect of skew is considerable for skew angles beyond 200.The paper also
mentions that the effect of skew on bending moment gets pronounced
beyond 400 and for spans beyond 24 m. On the other hand, the torsion
starts increasing to considerable levels at skew angles as low as 100.
(Annexure 2)
(c) Documents guiding design of skew bridges as per AASHTO LFRD bridge
design specifications were studied and it was found that these provide for
special reinforcement to be provided beyond skew angle of 250.
(d) Drawings collected from internet showing reinforcement details of bridges
designed as per New York Department of Transportation show
53
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045
reinforcement provided in the skew direction for spans with skew angle
less than 300, and in square direction for higher skew angles.
3. Based on above literature survey, it was decided that girders with skew angles
upto 200, can be designed by rule of thumb and the standard square designs can be
adopted with some modifications. Based on this reasoning, earlier drawing no RDSO/B-
11759 was issued in 2011.
4. At the time of review of the design in 2012-13, the matter was examined afresh in
view of item taken up during CBE’s conference held in IRICEN on 20th/21st September
2012 and computerized grillage analysis was got done again. The analysis gave some
variations in bending moments, however, the torsional moment mentioned in the
literature was not observed. Efforts were made to seek guidance from designers in
zonal railways and outside, but satisfactory guidance was not received, so the revised
drawing no RDSO/B-11759/R was issued for skew angles upto 200 only.
5. The following issues are expected if we go in for design of girders with higher
skew angles:
(a) The standard girders cannot be used as the extra bending moment at the
obtuse corners will require fresh design.
(b) Multiple Designs: It might not be possible to use same configuration for a
wide range of skew angles as the torsion and bending moment both increase
substantially for small change in skew angles.
(c) Seismic performance of the skew spans is not as good as the square spans.
(d) For torsional loads, the design of shear connectors has to be reviewed.
(e) The effect of torsion on the slabs is not clear. The shear reinforcement may
have to be provided in slabs, which is not the normal practice.
6. RDSO is of the opinion that the higher skew angles are not a satisfactory
arrangement. The analysis as well as fabrication are quite difficult for such girders.
Efforts shall be made to provide girders square or with low skew angles as far as
possible. Some measures which can be taken to reduce the skew angle are
enumerated at Annexure-3.
7. Committee may deliberate and make recommendations.
**********
54
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 2)
55
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 2)
56
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 2)
57
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Providing ROBs where road crosses at skew angle to the railway alignment:
Methods for reducing the skew angle of girders.
1. Introduction: Lots of demands for design of skew girder Road Over Bridges are
faced by the railways, especially for national highways where owing to higher speeds,
road authorities are reluctant to introduce any curves in the road alignment. Demands
for skew angles as high as 700 have been provided. Skew girders have the supports
quite away from the natural line of transfer of loads and as a result the girders are
subjected to high torsional loads as well as extra bending moments on the obtuse
corner. The acute corners are subjected to uplift as a result of the asymmetry of the
load due to the skew girders.
Railway
C.L. of Land
road boundary
ROB
Girder
58
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Railway
C.L. of Land
road boundary
ROB
Girder
59
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Railway Railway
C.L. of Land Land
road boundary boundary
ROB
ROB
Girder
Girder
Figure 3 On left: Normally provided skew girder; On right: Skew sub structure
constructed to reduce skew angle (without change in span)
Constraints:
The piers are not parallel to railway land boundary. So if the piers are being built
in railway land, the width of land rendered unusable for future is increased.
The skew piers can violate the Schedule of Dimensions of existing or future
tracks. This needs to be checked.
3.3 Constructing Skew bed block: Land is a precious resource and at lots of
locations, railways might require the entire railway land boundary for its current and
future operations and the land on approaches might also not be available. In this
situation, both the options a) and b) discussed above will not be feasible. Option b)
might not be desirable if the standard girder design is not available for the longer length
contemplated. In such situations, an option can be to construct the foundation and the
sub structure parallel to railway land boundary occupying minimum width, but to reduce
the skew angle of the girder, the bed block can be made in skew. In this approach, the
land is not wasted and the extra width in bed block is provided above the Schedule of
Dimensions so that maximum space is useable, without affecting the train operations.
60
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Railway
Land
boundary
ROB
Girder
Pier Cap
Pier and
foundation
61
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
62
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Railway
Land
boundary
Pier and
foundation
Railway
Land
boundary
Bearing
Portal
Beam
Pier and
foundation
GL
63
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1045 (Annexure 3)
Railway
Land
boundary
View of girders
Piers for
supported on web of
other
girders Girder over
portal beam
railway
line
oo Girder
oo
oo
oo
oo
**********
64
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
The provision of Para 222 sub para 2(a) of Indian Railways Bridge Manual 1998
is as follows:
“2. Maintenance of sliding and roller & rocker bearings:
a) All bearings should be generally cleaned and greased once in three years.”
The provision of Para 4.5.7.1 (ii) (e) of Manual Of Instructions On Long Welded
Rails 1996 (LWR Manual) is as follows:
“4.5.7.1 ii) Bridges provided with rail-free fastenings and partly box-anchored
(with single span not exceeding 30.5 metre and having sliding bearings at both
ends)
Overall length of the bridge should not exceed the maximum as provided in
Table-1 with following stipulations:-
e) The sliding bearings shall be inspected during the months of March and
October each year and cleared of all foreign materials. Lubrication of the
bearings shall be done once in two years.”
The provisions in the two manuals are different and in case the LWR is continued
on the bridge with sliding bearings, the frequency of oiling and greasing shall be two
years instead of once in three years as mentioned in IRBM.
Track dte of RDSO was approached regarding the background of para 4.5.7.1 (ii)
(e) of Manual Of Instructions On Long Welded Rails 1996 (LWR Manual) and vide letter
65
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
no CT/IM/LWR Dated 08.01.2014, they have indicated that the provisions of LWR
Manual were introduced with the following background:
1. Manual for instructions on long welded rails (Provisional)-1970 was framed as per
order of Railway Board on item no. 649 of 46th TSC held in 1970.
2. As per order of Railway Board on item no. 727 of 54th TSC held in 1978, a sub
committee consisting of the Chief Engineers of Northern, South Eastern and
Southern Railway, CTE of Central Railway, Principal, IRIATT Pune and Director
STDs.(Civil). RDSO as convener was formed to study various aspects of revision
of LWR Manual (provisional)-1970 and make recommendations for approval by
Board.
3. Accordingly the letters to various Railways were sent and suggestions of the
Railways were invited on the provisions of Manual for instructions on long welded
rails (Provisional)-1970.
4. In response to RDSO letter no. CT/IM/LWR dated 27.11.1978, Central Railway
vide their letter no. 1.735.T67/54.TSC dated 15/20.12.1978 had suggested some
connections in Annexure VIII of LWR Manual (Provisional)-1970. In para II(e) of
the suggestion it was recommended that “The sliding bearings shall be inspected
during the months of March and October each year and cleared of all foreign
material. Lubrication of the bearings shall be done once in two years”.
**********
66
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
NOTES BY SECRETARY
2. Indian Railway (IR) uses Lacey’s equation for estimation of scour depth at bridge
piers, developed about seven decades ago for alluvial river beds, in IRS Bridge
Substructure and Foundation Code. Lacey’s equation uses two parameters i.e.
discharge and silt factor only in estimating the scour depth.
3. An accurate prediction of scour depth at bridge piers is essential for the safe
design of the foundation because underestimation may lead to bridge failure and
over estimation will lead to unnecessary construction cost. Numerous formulae
for estimating maximum local scour at pier site have been developed by many
researchers. The use of these formulae in design is uncertain because of the
difference between site and laboratory conditions. Validation of the various
formulae using both the laboratory as well as the field data is very necessary in
order to improve the prediction of maximum local scour depth at bridge piers.
The report prepared by IIT/KGP documents and compares measurements of
pier-scour depth with pier-scour predicted by use of nine equations. The logic of
67
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
4. Rivers in Indian plains have normally alluvial soil beds. However, river beds in
hilly terrains are commonly composed of a mixture of different sizes of sands and
gravels. Under the varied stream flow velocities, a process of armoring on the
riverbed commences, resulting in an exposure of coarser particles due to
washing out of the finer fraction. The armor layers of concern to estimate scour
depth at bridge piers are those where the pier is embedded in sand –bed overlain
by a layer of gravel. A larger scour depth develops at a pier embedded in an
armored bed than if the pier were embedded in a bed of uniform sediments. In
the absence of a rational formula, the present tendency is to apply the same
formula as applicable for alluvial bed with a judicious choice.
Surface
Roller
Down-
flow
Wake
Vortices
Horseshoe
Vortex
68
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
5.2 Flow running at a particular velocity, when approaches the pier comes to
complete rest which results in increase of pressure at the water surface near
pier. The velocity of the flow gradually decreases from top to bottom and
consequently the pressure also decreases from top to bottom. This creates a
downward pressure gradient that forces the flow to move downward like a
vertical jet of water. This vertical jet when strikes the bed makes a hole in the
immediate vicinity of the pier base. The strength of the down flow reaches
maximum just below the bed level. The down flow rolls up as it continuous to
create a hole and through the interaction with incoming flow converts into a
complex vortex system of horseshoe shape and hence called horseshoe
vortex. The horseshoe vortex is very effective at transporting the dislodged
particles away past the pier.
5.3 The separation of flow at the pier sides produces wake vortex. These vortices are
not stable and shed alternatively from one side of pier and then other. As
shown in the figure, wake vortices rotate about vertical axis. Wake vortices also
erode sediment from pier base. The wake vortex system somewhat acts like a
vacuum cleaner that sucks the material and carries away. The intensity of wake
vortices drastically reduces with distance in downstream direction, such that
sediment deposition generally takes place immediately downstream of pier. The
horseshoe and wake vortices both work at the same time to scour around pier.
69
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
ρs is sediment density
Vc is critical mean approach velocity
6.2 The functional relationship between the depth of local scour ds and its dependent
parameters is -
Ds = f (ρ, υ, V, D, G, g, d50, σg, ρs, vc, B, S, θ)
6.3 Non-dimensionally functional relationship between the depth of local scour ds and
its dependent parameters is -
ds V D B Vt V
=f [ , , ,σg,S, θ,G, , ]
B Vc B d 50 B gB
Effect of these various parameters (e.g. flow intensity; flow shallowness; size,
shape and orientation of pier; relative sediment size etc.) on local scour has
been discussed in the report of IIT/KGP.
70
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
Shape Ks ----
Ks Circular 1.0
Round Nosed 1.0
Square Nosed 1.1
Sharp Nosed 0.9
71
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
Where,
Θc is critical Shields parameter
ρs/ρ = s is relative density of sediment particles
(b) Θc is given by van Rijn (1984) as -
c d* 4 0.24 d*
(b) Find critical velocity for armour peak, Vca as per procedure given in para
2.1 above by using d50a in place of d50
72
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
7.1.1.3 Approach flow velocity V may be calculated from design foundation discharge
Qf
Qf i.e. V
WD
Where, W is approach channel width
7.2 Based on the validation results from experimental data and his experience in the
field of scour, IIT/KGP has suggested the following best suitable equation for
predicting the equilibrium scour depth at bridge piers when a layer of gravels
exists above sand bed:
d s dˆ sa B
0 . 78 ~ 1 . 07 ˆ 0 . 6 ~ . 0 . 95
Where, dˆ sa 0 . 16 K s F ca b h d
7.3 Scour in cohesive material revealed that depending upon antecedent soil
moisture and drainage conditions prevailing in cohesive soils, the scour in them
can be less, equal or even more than that in cohesionless material under
similar flow and pier conditions. The results showed that although the rates of
73
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
scour were much slower in clay than in sand, equilibrium scour in clay was
about the same as in sand.
7.4 Formulae given in para 7.1 above may be adopted for calculating the scour
depth for design of foundations of abutments also.
0.857
B1
d s h1 1.58 1
B2
B x B2
L
(a)
1 2
z
h1
h2
x
ds Bed sediment
1 2
(b)
In contracted bridge sites –
Total scour depth = Pier scour depth (Melville formula) + Contraction scour depth
(Gill formula)
8. Non-uniform Piers and Equivalent Uniform Width, Be
The four cases of local scour at non-uniform piers, where the pier is founded on a
wider element (caissons, slab footings and pile caps), are shown in figure below.
For Case- I, the local scour is estimated using the pier width B.
For Case- II, a procedure given by Melville and Raudkivi (1996) to estimate the
size of an equivalent uniform pier can be applied. The equivalent uniform pier
induces (at least) the same scour as the non-uniform pier. The procedure is
therefore conservative. Melville and Raudkivi (1996), who measured scour
74
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
depths at a circular pier founded on a larger concentric circular caisson, gave the
following relation:
*
D Y * B Y
Be B B
D B* B* D
Where Be = width of an equivalent uniform pier; and B* = caisson width.
The above equation is restricted to the range defined by Y B* and –Y D.
The relation for Be can be used for Case-II non-uniform piers that are
geometrically similar to the caisson foundation shown in Figure below, including
piers founded on slab footings and piled foundation, unless the footing or the pile
cap is undermined by the scour.
B B
B B D B D
-Y B
ds Y *
d
B B B*
* * B
Slab *
Footing Caisson Piled
Foundation Foundation
Caisson Piled
CASE III
Foundatio Foundation
CASE I
B B
D
B -Y B
B D B *
Y ds
ds B
*
B B Caisson Piled
B * *
Slab Foundatio Foundation
*
Footing
Caisson Piled
Foundation Foundation CASE IV
CASE II
75
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
ds/B (ds/B*)uniform
Case IV III II I
:
-D/B 0 ds/B Y/B
Y/B 0.5
(varies)
For Case-III, above equation also applies to Case-III caisson foundations and
may be used to give conservative scour estimates for Case-III piled foundations.
For Case IV, for caisson foundations, the local scour is estimated using the
caisson width B*. This approach would also give a conservative estimate of
Case-IV local scour at a piled foundation.
76
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047
9.2 Scour Depth Estimation of New Bridge No. 531 on Sone River in EC
Railway
9.2.1 East Central Railway is constructing a new Railway Bridge No. 531 across
river Sone between Sone Nagar and Dehri-on-Sone stations. The bridge
consists of 91 spans of 32.926m and 2 spans of 32.266m. The foundation of
bridge consists of 1.25m diameter bored cast in situ RCC piles. The
substructure consists of RCC piers of 1.40 m thickness. The super structure
consists of pre cast PSC box girders.
9.2.2 TAG in 2001 had originally fixed a scour level of 77.274 m RL based on
calculations as per Lacey’s formula prescribed in IRS Bridge Substructure
and Foundation Code. When analyzing for seismic forces, a scour level of
81.254 m RL was mandated.
9.2.3 Subsequently, the issue was taken up by TAG again in September 2004,
when bridge construction had already begun and some abutment/pier piles
had been casted. It was decided to adopt scour estimation formula suggested
by Melville & Coleman on account of heterogeneous nature of soil strata at
bridge site. Based on calculations using Melville & Coleman formula, the
design scour level was revised from 77.274m to 82.75 m RL (scour depth
reduced by 5.476m). This scour level was finalized for normal as well as
seismic design scenario.
10. Draft Revisions proposed to IRS Bridge Substructures and Foundation Code
are given in Annexure-I.
************
77
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
Annexure-1
Proposed Draft Amendments to IRS Bridge Substructures and
Foundation Code
Clause Existing provision Proposed Draft provision
No.
4.6 Depth Of Scour
4.6.1 The probable maximum depth of scour No change.
for design of foundations and training
and protection works shall be estimated
considering local conditions.
4.6.2 Wherever possible and especially for No change.
flashy rivers and those with beds of
gravel or boulders, soundings for
purpose of determining the depth of
scour shall be taken in the vicinity of the
site proposed for the bridge. Such
soundings are best taken during or
immediately after a flood before the
scour holes have had time to silt up
appreciably. In calculating design depth
of scour, allowance shall be made in the
observed depth for increased scour
resulting from:
(i) The design discharge being greater
than the flood discharge observed.
(ii) The increase in velocity due to the
constriction of waterway caused by
construction of the bridge.
(iii) The increase in scour in the
proximity of piers and abutments.
4.6.3 In the case of natural channels flowing in No change.
alluvial beds where the width of
waterway provided is not less than
Lacey’s regime width, the normal depth
or Scour (D) below the foundation design
discharge (Qf) level may be estimated
from Lacey’s formula as indicated below
1/3
Q
D = 0.473 f
f
where D is depth in metres, Qf is in
cumecs and ‘f‘ is Lacey’s silt factor for
representative sample of bed material
obtained from scour zone.
4.6.4 Where due to constriction of waterway, No change.
the width is less than Lacey’s regime
78
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
79
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
4.6.8 - $
4.6.9 - Scour in cohesive material
depends upon antecedent soil
moisture and drainage conditions
prevailing in cohesive soils; the
scour in them can be less, equal
or even more than that in
cohesion less material under
similar flow and pier conditions.
Though the rates of scour is much
slower in clay than in sand,
however equilibrium scour in clay
is about the same as in sand and
may be estimated by using
formula given in clause 4.6.7. In
case of clayey beds, wherever
80
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
Where,
KDB, is flow depth- pier size factor.
KI, is flow intensity factor.
Kd is sediment size factor.
Ks is pier shape factor.
Kθ is pier alignment factor.
d s dˆ sa B
0 . 78 ~ 1 . 07 ˆ 0 . 6 ~ . 0 . 95
Where, dˆ sa 0 . 16 K s F ca b h d
Vca
Fca (excess pier Froude number) =
gB
Vca is critical velocity for armoring gravel which may be estimated by procedure
given in para 2 of Appendix-VI by using dg in place d50.
81
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
b = B/dg
D
hˆ
B
d =dg/d50
0.857
B1
d s h1 1.58 1
B2
Total scour depth should be estimated by adding Pier scour depth (Melville formula) and
Contraction scour depth (Gill formula).
***********
82
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
Appendix-VI
(Clause 4.6.7 & 4.6.8)
1. Estimation of various factors/parameters of Melville (1997) formulae given in clause
4.6.7 shall be estimated as given below:
Shape Ks ----
Ks Circular 1.0
Round Nosed 1.0
Square Nosed 1.1
Sharp Nosed 0.9
83
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
84
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
B B
B B D B
D
-Y B
ds Y *
d
B B
B *
*
*
B
Slab *
Footing
Caisson Piled
Foundation Foundation
Caisson Piled
Foundation Foundation CASE III
CASE I
B
B
D
-Y B
B B B *
D
Y d
s
ds B
*
B B Caisson Piled
* *
B Foundation Foundation
* Slab
Footing
Caisson Piled
Foundation Foundation
CASE IV
CASE II
85
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1047 (Annexure 1)
ds/B (ds/B*)uniform
form
Typical curve for
caisson foundation
(ds/B)uniform
Case: IV III II I
For Case- I, the local scour is estimated using the pier width B.
For Case- II, a procedure given by Melville and Raudkivi (1996) to estimate the size
of an equivalent uniform pier can be applied. The equivalent uniform pier induces (at
least) the same scour as the non-uniform pier. The procedure is therefore
conservative. Melville and Raudkivi (1996), who measured scour depths at a circular
pier founded on a larger concentric circular caisson, gave the following relation:
*
D Y * B Y
Be B B
D B* B* D
Where Be = width of an equivalent uniform pier; and B* = caisson width.
The above equation is restricted to the range defined by Y B* and –Y D.
The relation for Be can be used for Case-II non-uniform piers that are geometrically
similar to the caisson foundation shown in the Figure, including piers founded on
slab footings and piled foundation, unless the footing or the pile cap is undermined
by the scour.
For Case-III, above equation also applies to Case-III caisson foundations and may
be used to give conservative scour estimates for Case-III piled foundations.
For Case IV, for caisson foundations, the local scour is estimated using the caisson
width B*. This approach would also give a conservative estimate of Case-IV local
scour at a piled foundation.
*********
86
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048
NOTES BY SECRETARY
The provisions for derailment loads were included in IRS Bridge Rules vide
discussions held against item no 767 in 64th BSC (For BG loading) in April 1988 and
item no 860, discussed in Extraordinary BSC held in year 2000 (For HM loading).
The derailment loads for 25T loading 2008 and DFC loading were included in bridge
rules in 2008. The basis for including the derailment loads in the Bridge Rules was
circulated to all railways vide RDSO letter no CBS/PBR Dated 23.10.2008 (Annexure
1). The current derailment provisions in IRS Bridge Rules given in various annexures
for different loadings are discussed as follows (The text is same except for the
highlighted part which is changing for the different loadings):
87
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048
Discussions:
o The serviceability criteria for the HM, 25T and DFC loadings appears to
be on lower side to the loads specified earlier.
o In case of ballastless track, with no ballast to distribute the load, the
slab design will be very difficult to meet the crack width and other
serviceability criteria.
o Derailment load is a rare load and shall be considered as an ultimate
load case rather than a serviceability load case. There shall be no
need to design the structure in serviceability aspects for this load.
Checking in ultimate load condition and stability conditions shall
suffice.
o If it is considered that serviceability is to be checked, the loads
specified for checking shall be commensurate with the probability of
the vehicle load which is going to derail on the bridge along with the
probability of damage it is going to cause.
o If it is considered that serviceability check is not required to be done,
the implicit assumption will be that in the event of derailment on
bridge, the slab/ girder must be inspected for damage and trains
88
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048
allowed only after necessary repairs etc are done to ensure the safe
operations of trains.
2. CHECK IN ULTIMATE CONDITION:
BG Bridges HM Loading 25 T loading 2008 DFC Loading
Appendix IX Appendix XIV Appendix XXVIII Appendix XXIX
Max. Axle Load: 22.9 T, 7.67 T/m Max. Axle Load: 30 T, Max. Axle Load: 25 Max. Axle Load: 32.5
12 T/m T, 9.33 T/m T, 12.13 T/m
Sl. Condition and Bridges with Bridges without Bridges Bridges Bridges Bridges Bridges Bridges
No. approach guard rails guard rails with without with without with without
guard guard guard guard guard guard
rails rails rails rails rails rails
2. Ultimate – a) Two vertical a) Two vertical a) … a) … a) … a) … a) … a) …
The load at line loads of 50 line loads of 100 100 75 75 100 100
which a kN/m (5t/m) 50 kN/m (5 kN/m kN/m kN/m kN/m kN/m kN/m
derailed each 1.6m t/m) each (10 (10 (7.5 (7.5 (10 (10
vehicle shall apart parallel 1.6m apart t/m) t/m) t/m) t/m) t/m) t/m)
not cause to the track in parallel to the each… each… each each… each… each…
collapse of the most track in the …
any major unfavourable most
element. position inside unfavourable
an area of position inside
1.3m on either an area of
side of track 2.25m on
centre line. either side of
track centre
line.
b) A single b) A single b) … b) … b) … b) … b) … b) …
load of 200 kN load of 200 kN 240 kN 240 kN 200 200 kN 260 kN 260 kN
(20t) acting on (20t) acting on (24t) (24t) kN (20t) (26t) (26t)
an area of an area of … … (20t) … … …
1.3m on either 2.25m on …
side of track either side of
centre line in track centre
the most line in the
unfavourable most
position. unfavourable
position.
89
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048
Discussions:
o The line load was increased substantially for HM loading which is
logical as the axle load has gone up from 22.9t for loco only in BGML
to 30t for locos as well as wagons in HM Loading. Subsequently, the
load has slightly been reduced slightly as a proportion to trailing load
intensity in 25T loading 2008 and DFC loading.
o For smaller spans, the actual load intensity is much higher than the
trailing load. But in this case, the individual axle loads becomes
critical.
o The provisions for ultimate check in current loadings provide for 80% of
the actual loads.
o The impact is likely to be very high for first bogie and then reduce.
Discussions:
o The length of line load is 20m only. This means that only one/two
vehicles are considered derailed on a span.
o The stability check is being done for the trailing load intensity in
HM/25T loading 2008 and DFC loadings.
90
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048
o For smaller spans, the actual load intensity is much higher than the
trailing load, as given in table below:
SPAN LOAD INTENSITY (SHEAR) LOAD INTENSITY (SHEAR)
25 T LOADING 2008 DFC LOADING
o The condition for stability check is for line load placed at the edge of
the slab. In practice, the situations are likely to be different:
There are two line loads and the other load will also cause
contribute to overturning of the structure if the slab width inside
parapets is more than 3.5 m.
Parapet width (min 200 mm) is neglected in these computations,
so the load is considered at more distance than actual derailed
vehicle.
The actual derailed train is likely to be zig-zag/ oblique to the
structure, especially if the number of vehicles derailed is more.
On bridge in curve, the entire train is likely to come to rest on
one side after derailment.
4. General: The provisions are in line with UIC code. The other details are in
order, only the load intensity and length need to address the reasonable
probability of occurrence during the life of bridge and the damage railway is
prepared to accept in such a case.
*********
91
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048 (Appendix 1)
Appendix 1 of Item No
1048
92
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048 (Appendix 1)
93
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048 (Appendix 1)
94
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048 (Appendix 1)
95
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1048 (Appendix 1)
96
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1049
NOTES BY SECRETARY
EDCE/B & S Railway Board has raised the issue that there is no provision in the
Indian Railway manuals for provision of guard rails in track under the bridges
spanning across track such as Foot Over Bridges and Road Over Bridges.
This issue has been studied by RDSO and the following is brought out:
2. The wider issue involved in the matter raised is that the bridges are subject to
impact from various sources:
a. In Foot Over Bridges/ Road Over Bridges/ flyovers, the sub structure can
be hit by derailed train vehicles.
b. In Road Under Bridges, the sub structure can be hit by road vehicles.
c. In bridges across rivers which are used for navigation can be hit by barges/
ships.
3. This is an important issue as the impact of vehicles can cause the pier to
collapse, or cause the girder to topple over and can lead to derailment/ falling
off of the vehicles on the bridge at that moment. This can cause the bridge to
fall on the vehicles underneath and cause damage there also.
4. The loads for such impact are shall be covered by provisions laid down by
IRC/ MOST for roads and the authorities controlling navigational channels.
But the loads for derailed railway vehicle shall be specified by the IRS codes
only.
5. Instructions for provision of guard rails under the FOBs and ROBs are there is
some old Railway Board circular, but the same could not be located. This
issue was discussed a number of times in IRICEN discussion forum including
under topic id 3758. The instructions for the provision of guard rail exist as
engineering standing order no 9 dated 03.09.1999 of SC Rly and instructions
also exist on other railways. This is also mentioned at item no 11 of check list
for application for obtaining CRS sanction.
97
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1049
6. However, there are some questions left unanswered in the existing guidelines:
7. The following issues are required to be addressed in this respect for the
derailed railway vehicle:
a. Upto what distance shall the bridge sub structure be considered
vulnerable to impact from the derailed train.
b. What measures (such as guard rails, sacrificial columns etc) can be
taken to safeguard the structures from impact of derailed trains.
c. Detailed specifications of measures to be taken.
d. What load shall be considered in design of the structure if other
methods of protection are not possible (due to presence of points and
crossings/ space constraints etc).
8. The design methodology to be followed for design of the structures for any
accidental impact load whether from derailed trains, impact from road vehicles
or water-borne vehicles need to be specified, including:
a. Factor of safety against damage and over turning of the bridge.
b. Other loads like train loads, water current forces, etc occurring
simultaneously with the impact load.
9. The committee may deliberate and decide further course of action.
98
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1049
*********
NOTES BY SECRETARY
1.0 CBE/SCR proposed this item in CBE seminar held on 8th & 9th November
2011 at IRICEN, Pune and wanted it to be adopted in long term interest of
track maintenance. The proposal was supported by all CBEs. ED/B&S/RDSO
also appreciated the point raised and asked for time to study the proposal.
The issue was further discussed in CBE seminar held on 20th & 21st
September 2012 as item no -3(c). Issues in the agenda were as below:
99
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1050
300mm).
d) Foldable lifting hooks with an arrangement that after placing the slabs in
position shall be folded and kept that no part is projected above the top
surface of the slab.
e) Definite policy of passing the cables through the bridge, provision of duct
beyond minimum specified width for BCM working
The issue should be deliberated in next BSC. RDSO to prepare detailed note
for deliberation in next BSC.
2.0 83rd TSC:- This item was also deliberated as item no. 1222 in 83rd TSC
meeting (held at Bhubaneswar on 17th to 19th December,2012) as per the item
proposed by South Eastern Railway(Ref-RDSO FILE: TM/GL/70).
In TSC, it was proposed that width of deck slab for BCM working should be
5800mm (5400mm between inside face of ballast retainer).
The basis of proposing 5800mm slab width By TSC is as following:-
i. The outer width of chain guide = 4280mm(for cutter size 2150)
(2150+531x2+58x2+476x2=4280mm)
2150mm=Size of cutter bar
531mm=Size of elbow
58mm=Wall thickness of trough
476mm= Size of trough
100
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1050
200 mm approx.
4280+1000=5280mm
5280+200+200=5680mm
a. Deck width:- (i) RDSO approved drawing for PSC slabs/girders /box culvert
have a deck width between inside faces of the ballast retainer/barrel length of
4500 mm as per A&C No. 5 (dated 19.11.2001) of IRS: CBC-1997(clause
16.9.6.4).
101
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1050
102
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1050
4. Repercussions
i. There will be substantial increase in cost due to increase in width of
substructure & superstructure
ii. There will be encouragement to trespassing, if more width is provided than
the required for ballast. Hence, the safety aspect may be compromised.
iii. The Drawings (45 no’s approximately at Annexure-I), designed recently shall
need to be revised. Further it is to be noted that with limited resources in
design unit of RDSO it shall take considerable time to revise these
design/drawings.
5. Issue to be deliberated:-
i. The working load of BCM & other associated machines need to be verified
that they are coming within the loading envelope of the corresponding design
loads of IRS: Bridge Rules for respective spans .The effect of vibration load
(For Machines like DTS) need also to be studied especially the bridges resting
on bearings.
ii.Length of BCM machines over buffers is 31.8m approx. Hence, working of
BCM, on bridges upto 12.2m, may be managed with width of 4500mm inside
of ballast retainer.
iii.For bridges more 12.2 m a space of 300mm on both side is sufficient for
movement & observations during working of BCM. So, required Width of
Deck slab is 4900mm (4280+300+300=4880) between inside face of ballast
retainer or Work on Bridges having length more than 12.2m should be done
with cutter bar of 1900mm.
iv.Bridges provided with footpath on one side, the footpath may be utilized for
the purpose of movement / observation during working of BCM. Therefore,
avoiding the need for increasing the deck width.
v. Disposal of muck should be taken care of to avoid detrimental effect on
waterway, while running the BCM.
**************
103
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1050 (Annexure 1)
Annexure-I
List of Drawings
2 Pier/Abutments 4
3 PSC Slabs 5
104
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1051
NOTES BY SECRETARY
1. Prior to 1998 the speed certificate were being issued by RDSO with banning
all those standard spans which were not clearing the criteria of Tractive Effort
even after considering dispersion of longitudinal forces as per clause 2.8.3.1
of IRS Bridge Rule. For the first time Speed Certificate of 2WAG7 (double
headed) locomotive was issued on 26/30-03-1998 as amendment to the
Speed Certificate issued on 25-11-1992 which was having tractive effort
limiting device. The clauses under bridge were as under:-
Bridge Clauses:-
“a) The maximum tractive effort of the coupled locos shall be limited
to 60t (i.e. traction motor current in each locomotive will be
limited to 970 amps) while running over the bridges with spans
(clear) of 24.4m and above. List of such bridges where drivers of
coupled WAG7 locomotives will be required to limit the tractive
effort to 60t (for coupled locos) should be notified by Railway
and incorporated in the working time table so that all operating
staff are aware of this instruction.”
2. After passage of time and development in day to day working at present the
Speed Certificate for locomotive having tractive effort limiting device has been
105
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1051
modified and clauses under bridges and general are modified. The clauses
under bridge of Speed Certificate for WDG4D (twin cab) issued vide RDSO’s
letter No. SD.WDG4D.11 dated 23-08-2013 having tractive effort limiting
device are as under:-
106
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1051
107
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1051
a. On one of the bridges of SCR, the board for tractive effort limiting
switch has been provided like.
LIMIT TE TO
30T PER LOCO
b. Some Railways have put an indicator board near such bridges where
tractive effort for the locomotive is to be limited to 30t per loco
indicating:-
********
108
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1051 (Annexure)
109
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
110
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
111
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
112
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
PRESENT STATUS:
(i) Schematic sketch for indicative arrangements on PSC Slab & PSC
Girders has been issued vide letter no CBS/Service Cable dated
23/25.07.13, for plate/composite girders vide letter no. CBS/Service
Cable dated 15.01.2014, for open web girder vide letter no. CBS/WBG
dated 15.01.2014.
(ii) These Sketches have been uploaded on rail net site 10.100.2.19 for
Comments and suggestion. Feedback is awaited.
(iii) Note has been sent to Electrical and S&T directorate and feedback is
awaited.
(iv) Members are requested to send feedback to RDSO.
(v) Committee may deliberate and decide.
113
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
114
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
“As per correction slip no 18 of IRS Steel Bridge Code, permissible stress
in fatigue are to be calculated based on certain factors λ1, λ2, λ3 and λ4
which cover train loads, traffic density, design life of bridge, no of tracks on
a bridge. Considering above factors, section required for different
components of bridges are coming out to much higher as compared to the
old criteria. Earlier as per Steel Bridge Code, Appendix G, actual fatigue
stresses permitted were between 11 to 12 kg/mm2, whereas now this
permitted stress as per correction slip no 18 comes out to be much less,
justifying higher section especially in members subjected to tension and
bending. Sample calculations for through girder bridges span 33.53 m in
Jabalpur division of WCR is enclosed. This needs to be addresses
because for new construction, taking higher sections is not a problem but if
adequacy of old bridge girders is to be checked then most of the girders
will fail in fatigue criteria. Therefore, it is felt necessary to review the
criteria. Alternatively, instructions should be issued not to implement these
instructions for checking the adequacy of old bridges.”
In view of this, the correction slip no 18 has been examined again and
following comments are offered:
1. The old fatigue provisions were based on stress ratio concept and had
several limitations as far as fatigue design was concerned. As a result
of this, there were so many failures in fatigue critical members like
small spans, stringers etc. Therefore, the method was taken up for
review and replaced by more rational new method which is based on
stress range concept.
2. RDSO has designed a 30.5 m underslung girder for 25T loading and it
was seen that the weight of girder has increased from 43T in MBG to
70 T. The reason for the increase in weight is the new fatigue
provisions. The comparative chart of Girder members for MBG loading
with old fatigue provisions and 25 Ton loading with new fatigue
provisions is enclosed as Annexure 1.
3. On close analysis of the design, it was seen that the increase in weight
is not only in members which are identified as fatigue critical but also in
115
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
bottom chord (~110% increase). The experience with the old girders
indicates that this increase is not warranted. Further, the percentage
increase in Diagonal Members is 147% which is also not desirable.
5. A problem has been reported by DFC that the design for 100 years and
50 GMT might not suffice for heavy density route like DFC.
6. Further it has been represented to RDSO from several sources that the
new provisions are difficult to understand.
In view of above, RDSO is of the view that the following shall be done:
MBG
RIVETED 25T WELDED
with new fatigue
Members LENGTH AREA WEIGHT AREA WEIGHT NATURE %INCREASE
(CM) (CM^2) (TON) (CM^2) %INCREASE
B.C
U0-U1 319 209.86 0.5258 216 0.5412 COMPR. 2.926
U1-U2 319 209.86 0.5258 216 0.5412 COMPR. 2.926
U2-U3 319 209.86 0.5258 292 0.7316 COMPR. 39.140
U3-U4 319 209.86 0.5258 292 0.7316 COMPR. 39.140
U4-U5 319 209.86 0.5258 292 0.7316 COMPR. 39.140
T.C 0.0000
L1-L2 319 109.69 0.2748 230.4 0.5773 TENSION 110.046
L2-L3 319 109.69 0.2748 230.4 0.5773 TENSION 110.046
L3-L4 319 156.89 0.3931 338.92 0.8491 TENSION 116.024
L4-L5 319 156.89 0.3931 338.92 0.8491 TENSION 116.024
116
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
E.R 0.0000
U0-L1 559.79 109.69 0.4823 242.4 1.0657 TENSION 120.986
DIAGONAL 0.0000
L1-U2 559.79 91.28 0.4013 125.86 0.5534 COMPR. 37.883
U2-L3 559.79 76.99 0.3385 182.01 0.8002 TENSION 136.407
0.0000 0.0000 COMPR.
L3-U4 559.79 77.34 0.3400 166.11 0.7303 COMPR. 114.779
117
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
118
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
Railway Board’s orders are not required in terms of Board’s letter No.
2005/CE-I/BR-II/8 dated 04-08-2009. RDSO should review and issue
necessary alteration expeditiously.
PRESENT STATUS:
No problem has been reported in 24.4m span welded plate girders. The
drawing has been reviewed, including checking with the new fatigue
provisions and the girders have been found fit. Hence no changes are
required from design point of view.
No feedback on the drawing has been received. The drawing may be
approved. The committee may deliberate and decide.
(a) This item was discussed in the 78th BSC/2009 based on the reference of
Southern Railway and as per recommendations on item No. 5(c) of CBEs
seminar 2008. Southern Railway had proposed that since provisions are
not available in IRS codes as well as in IS-2911. However, provisions are
available in IRC:78-2000 which can be adopted for IRS codes.
(b) Literature study and provisions of IRC:78-2000 were discussed in 79th
BSC and It was decided that provisions of IRC:78-2000 can be followed
and new para 2.4.3.3 in ‘Manual on Design of Well and Pile Foundations’
as recommended should be added.
119
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
(c) Accordingly, draft A&C Slip No. 3 to ‘Manual on Design of Well and Pile
Foundations’ was prepared and send to Railway Board for approval in
July’2010. Railway Board in November’2010 directed RDSO that-
RDSO should incorporate the factors to be considered for deciding
the values of Ksp. RDSO should also incorporate, how the value of qc
has to be adopted.
RDSO should also study certain real cases involving rocks on Indian
Railways to firm up Correction Slip No.3.
(d) Accordingly, CAOs & CBEs of Zonal Railways were requested to provide
the design details and parameters adopted in design for bridges provided
with pile foundations on rocks in their Railways.
(e) Meanwhile, provisions in IRC:78-2000 for assessing the load carrying
capacity of piles founded on rocks were modified and comprehensive
provisions were incorporated in the code by Notification No. 68 dated
28.02.2011. It was also noted that IS-2911 (Part-1) was revised in 2010
and provisions for piles founded on rocks were incorporated in the code.
Guidelines for deriving load carrying capacity of piles socketed in rocks are
also available in IS:14593-1998 (reaffirmed-2003) which have referencing
to clauses of IS-2911 part-1 & part-4. Modified provisions of IRC:78-2000
and IS-2911 were deliberated in 81st BSC meeting.
(f) In view of availability of detailed provisions for assessing the load carrying
capacity of piles founded on rocks in IRC:78 and IS-2911 (Part-1), 81st
BSC recommended that there is no need of any change in provisions of
IRS codes. Since the experience of recently introduced provisions of IRC
and IS codes was not available, it was not considered appropriate at that
stage to revise IRS code based on provisions of IRC code. Therefore, the
item was recommended for closure by 81st BSC.
(ii) In view of Railway Board’s Orders on 81st BSC recommendations, Zonal
Railways (CBE & CAO offices) were requested again to submit design
details and parameters adopted in design for socket resistance of piles
anchored in rocks vide RDSO’s letter No. CBS/DWF dated 15/20.11.2012
and reminder dated 7/11.06.2013.
(iii) No additional input/information has been provided by Zonal Railways.
(iv) Earlier information provided by CR, ER, NR, SR, SER, SECR and NFR
has already been deliberated in 81st BSC Meeting and same is reproduced
below for appreciation:
Railway Description Railway’s Remark
CR Pile capacity through socket IS:14593 along with IS:2911 may be
resistance referred.
ER (i) Minimum depth of (i) As per Table-1 of IS : 14593 – 1998
socketing (ii) As per Appendix V, Section– 9 of
(ii) Load carrying capacity of IRC – 78- 2000
piles (iii) As per IS – 2911 Pt.4
(iii) Load testing (iv) iv) Clause No. 9.2 and 9.3 of IS –
(iv) iv) Limiting values of 14593 - 1998
120
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
(v) It can be seen from above that Zonal Railways were using provisions of
IRC-78:2000 and Guidelines given in IS:14593-1998 for deriving load
carrying capacity of piles socketed in rocks.
BSC may deliberate on relevance of continuing this item.
121
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
The correction slips prepared till date on the existing codes are very few and
quite insignificant as far as Design of bridges are concerned. It is mostly
covering “post-earthquake measures” and “Anti-dislodging devices” etc which
do not affect the design of the bridge at all. The correction slip on the ductile
detailing cannot be issued in isolation because it involves calculation of ductile
reinforcements based upon the plastic moment capacities and on Response
reduction factor R of the new method.
As such it is proposed that all the correction slips to the Bridge Rules and
Concrete bridge codes etc be approved by the BSC at once only. The Seismic
guidelines needs correction itself because there are many clauses which
needs rephrasing or replacement altogether. The adoption of new seismic
guidelines needs to be done through recommendations of an Expert
Committee specifically formed for this purpose only. It is proposed that the
122
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
123
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
124
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
PRESENT STATUS:
(i) Drawing issued vide letter no CBS/DPS dated 21/03/12.
(ii) Drawing has been uploaded on rail net web site
www.rdso.railnet.gov.in for trial adoption and comments.
(i) Feedback has been received from East Coast Railway (Vide letter no.
DCE/C/II/VSKP/JDB-KRDL doubling/370 dated 24/25-06-3013) where
it was requested to examine the possibility of altering the ordinate of
the Ist row of strands in the latest standard drawing(RDSO/B-10257/R)
for 6.1m PSC slab from 105mm to 95mm at the end so as to facilitate
manufacturing all the four types (i.e 3.05, 3.66, 4.57, and 6.1m) of PSC
slabs with single pre-stressing arrangement.
The possibility of altering the ordinate of the Ist row of strands in the
latest drawing no. RDSO/B-10257/R for 6.1m PSC slab from 105mm to
95mm (at the end section) was examined and it was observed that it is
possible to make alteration by changing the camber provided at the
mid. However this will lead to revision in drawing, RDSO will take up
the revision of drawing in 2014-15.
COMMITTEE’S RECOMMENDATIONS:
(i) Para 5.5 of RDSO report No. BS-105 for ‘Guidelines on Pipeline
Crossings under Railway Track’ should be modified as under:
5.5 Accessible emergency shut off valves shall be installed within
effective distance each side of the railway as mutually agreed to
by the engineer and the pipeline company in accordance with
latest provisions given in relevant ASME codes (i.e. ASME
B31.4-2009: Pipeline Transportation System for liquid
Hydrocarbons and other Liquids; and ASME B31.8-2010: Gas
Transmission and Distribution Piping System).
5.5.1 In case of main pipelines carrying gas, Railway operations
should be considered as Location Class 4 and minimum spacing
should be kept as 8km. In case of city gas pipelines maximum
spacing should be kept to 3km (steel distribution mains) and
1km (plastic distribution mains).
5.5.2 Mainline block valves should be installed prior to crossing on the
upstream side along with block or check after pipeline crossing
carrying liquid hydrocarbons and other inflammable liquids.
5.5.3 These valves should be marked with sign for identification.
Where pipelines are provided with automatic control stations at
locations and within distances approved by the engineer, no
additional valves shall be required.
5.5.4 Valves shall not be located within the railway boundary.
125
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
126
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
Delhi. In the joint meeting the issues were deliberated and it was suggested
by the representative of Railways that PNGRB should provide their
suggestions to ED/Structures, RDSO so that the matter can be included for
discussion in the agenda of upcoming 82nd BSC meeting which is scheduled
at Bangalore towards the end of January’2014. It was also requested that
PNGRB and other concerned stakeholders may also make presentation
before BSC.
5. The proposal/suggestions of PNGRB T4S Technical Committee for Natural
Gas Pipeline submitted by PNGRB vide their letter No. M(I)/Railways/T4S/
NGPI/NGPL/1/2013 dated 23.12.2013 are placed at Annexure-II. It can be
seen that main issue is regarding consideration of Railway operations as
Location Class-4 in BS-105 where pipelines carrying gas crosses railway line
and therefore limiting the maximum spacing of shut off valves as 8km.
6. Provisions of ASME 31.8 – 2012 regarding provision of shut off valves in
transmission lines are reiterated below:
Clause 846 VALVES
Clause 846.1 Required spacing of Valves
Clause 846.1.1 Transmission Lines
Onshore block valves shall be installed in new transmission pipelines at the
time of construction for the purpose of isolating the pipelines for maintenance
and for response to operating emergencies. When determining the placement
of such valves for sectionalizing the pipelines, primary consideration shall be
given to locations that provide continuous accessibility to the valves:
(a) In determining the number and spacing of valves to be installed, the
operator shall perform an assessment that gives consideration to factors
such as
(1) the amount of gas released due to repair and maintenance blow
downs, leaks, or ruptures
(2) the time to blow down an isolated section
(3) the impact in the area of gas release (e.g., nuisance and any hazard
resulting from prolonged blow downs)
(4) continuity of service
(5) operating and maintenance flexibility of the system
(6) future development in the vicinity of the pipeline
(7) significant conditions that may adversely affect the operation and
security of the line
(b) In lieu of (a) above, the following maximum spacing between valves shall be
used:-
(1) 20 miles (32 km) in areas of predominantly Location Class 1
(2) 15 miles (24 km) in areas of predominantly Location Class 2
(3) 10 miles (16 km) in areas of predominantly Location Class 3
127
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
7. PNGRB Technical Committee (T4S) has stated and proposed the following:
(a) PNGRB does not mention any requirement for installation of emergency
shut-off valves specific to railway crossing or any other utility crossings.
However, PNGRB Regulation specify that installation of Isolation Valves
shall be as per Class Location identified across entire length of natural
gas pipeline system. However, for road/ highway/ rail crossing, casing
pipe may be provided complying with API RP-1102.
(b) ASME B-31.8 also does not identify any specific requirement for railway
crossings expect that the crossing conditions like safety factor as
indicated in Table 841.1.6-2 of ASME B-31.8, which is also based on
Class Location and as per API RP-1102.
In order to give the additional factor of safety over and above PNGRB
Regulations/ ASME B31.8 at railway crossings, the following is proposed by
Technical committee:
128
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
With the above, the stress levels on carrier pipe at railway crossings shall be
only 50% of specified minimum yield strength (SMYS) for Class-3 and 40%
SMYS for class 4.
Further, it was also proposed to extend the above higher wall thickness on
either side of railway crossing considering the risk radius length as per clause
no. 3.2 of ASME B-31.8 S 2010.
The pipeline system designs are based on overall aspects and good
engineering practices and further the Sectionalizing Valves shall be
provided for remote operation form control rooms- SCADA Master
Control Station/ Emergency Control Station (SMCS/ECS).
129
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
130
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
5.9: Clause 4.7.1.5 to The casing pipe will be protected Provisions of BS-105
4.7.1.9 shall be with Temporary Cathodic should be followed.
followed for Protection wherever the casing is
supplementing the coated.
corrosion protection
system of carrier and
casing pipeline at
crossing location with
cathodic protection
system.
5.10: For provision of
steel casing pipes, two-
component epoxy
coating for internal
surface will be used.
5.8: For steel pipes The PNGRB Regulations refers Higher strength steel
(both carrier and to API 5L which is mainly used pipes shall also be
casing) the pipes for oil and gas applications permitted. PNGRB
should be of mild steel where as IS:3589 is for water Technical and Safety
fabricated as per IS: and sewerage application. The guidelines shall be
3589 from steel plates IS:3589 pipes are having three followed for gas
conforming to IS: 2062. grades namely Fe330, Fe410 carrying pipelines.
Where screwed or and Fe450 which are based on
coupled joints are tensile strength. The line pipes
used, the joints should used as per API 5L are having
be welded, to the pipes higher strength.
at both ends along the
circumference as a Hence, it is suggested that
seal to prevent leak Railway may allow higher grade
through the threads. CARRIER pipes as per API 5L
The field welds should provided in PNGRB T4S/ASME
be tested cent percent B-31.8.
radio graphically as per
IS: 1182.
131
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
**********
132
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
133
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
134
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
135
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
136
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
137
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
138
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
(ii) The standard spans may be required for DFC and double stack
container routes also. The column height may be required to be
increased for the same.
COMMITTEE’S RECOMMENDATIONS:
RDSO may take further action on composite spans and columns for double
stack container routes.
RAILWAY BOARD ORDERS:
RDSO to issue standard drawings of FOB for double stack container routes
by modifying column height.
PRESENT STATUS:
The matter was examined and it is observed that increase of column height
does not affect the design of FOB superstructure (main girder) as it is a simply
supported structure. The same superstructure can be adopted for the DFC
routes. However, increasing of column height changes the design parameters
for column and foundations (lateral load, moments etc.). As this is a very
specific requirement only for double stack container’s and foundation design
are based upon local soil condition, D.F.C. should design the substructure
part (Column + foundation) taking into account local conditions.
139
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
140
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
2. The color shade of finish coat need not be of Red Oxide as it is similar
to the colour of rust. .
3. Provision of painting should be deleted for hot dipped galvanising from
para 12.3 of BS-45 since it does not serve any major purpose and it is
almost impossible to paint the inner side.
COMMITTEE’S RECOMMENDATIONS:
1. Correction Slip to IRBM para 217 and para 39.1 of B-1 2001 should
make a mention of IS-13607 only. Parallel M&C specification may be
deleted.
2. The color shade for finish coat may be Smoke Grey to No. 692 to IS-5.
3. Provision of painting in para 12.3 of BS-45 should be deleted, as
galvanising by hot dipping is sufficient.
RAILWAY BOARD ORDERS
1. Recommendation of BSC approved. RDSO to propose necessary
correction slips.
2. Recommendation of BSC approved. However, based on usage of
proposed colour, zonal railways should give feedback which may be
further discussed in next BSC.
3. Recommendation of BSC approved. RDSO to process necessary
correction slip.
PRESENT STATUS:
1. Correction Slip No. 26 to IRBM to all concerned issued vide Railway
Board letter No. 2011/CE-I/BR/BSC/81/Seminar dated 23-08-2013.
2. Correction Slip No. 1 to BS-45 to all concerned has been issued vide
RDSO letter No. CBS/SCS dated 12-12-2012.
3. Feedback on usage of colour Smoke Grey to No. 692 of IS:5 has been
called vide Railway Board letter No. 2011/CE-I/BR/BSC/81/Seminar
dated 23-08-2013. RDSO has also issued Reminder to call feedback
from Railways vide letter No. CBS/IRBM dated 05-12-2013. However
as usage time is less, no feedback has been received. BSC may
deliberate.
141
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
142
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
143
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
144
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
145
82nd MEETING OF BRIDGE AND STRUCTURES STANDARDS COMMITTEE
(January, 2014) Item No 1052
COMMITTEE’S OBSERVATIONS:
This is an important organizational issue. A subcommittee may be nominated
which can formulate yardstick for :-
(i) Supervisors and supporting staff to maintain bridge superstructure and
substructure including foundations.
(ii) Design staff in Bridge wing of HQ.
COMMITTEE’S RECOMMENDATIONS:
Board is requested to nominate a committee of CBEs to go into the matter.
RAILWAY BOARD ORDERS:
Approved. Orders for the committee shall be issued separately.
PRESENT STATUS:
Railway Board has nominated a committee comprising of Senior
Professor/Bridges, IRICEN as convener and ED/B & S/ RDSO, CBE/ N Rly,
CBE/ WC Rly and CBE/ SC Rly as members vide letter no 2011/CE-
I/BR/BSC/81/Seminar Dated 09.01.2014 and given four months’ time for
submission of report. The further action can be taken after committee’s report
is received.
**********
146