Professional Documents
Culture Documents
PGCM 44 Special Construction Method and Technology Final PDF
PGCM 44 Special Construction Method and Technology Final PDF
PGCM 44 Special Construction Method and Technology Final PDF
PGP-CM-MODULE-14
ASSIGNMENT NO: 02
COURSE TITLE:
P a g e 2 | 17
ASSIGNMENT
P a g e 3 | 17
Answer :
What is Soil stabilization? What are the various
methods of stabilization? Explain these briefly.
1. Mechanical stabilization:
Mechanical stabilization is accomplished by mixing or blending
soils of two or more gradations to obtain a material meeting the
required specification. The soil blending may take place at the
construction site, at a central plant, or at a borrow area. The blended
material is then spread and compacted to required densities by
conventional means.
P a g e 4 | 17
On Travelling plant construction, the process is similar to that
described above, except that a single pass of specialized moving
equipment is all that is necessary to dry mix the soils, admix water,
and spread the moist material to a uniform depth, prior to
compaction.
2. Cement Stabilization:
P a g e 5 | 17
enough is used with the right amount of water and proper
compaction and curing.
The dry soil is to be mixed with the cement and the required water
added. The mixture then needs to be formed and left in a 100%
humidity environment within 30 to 45 minutes of mixing the cement
and soil with the water. This is to ensure that the cement has
sufficient water to hydrate and also that the mixture is not
manipulated again after the critical time.
Curing of the mixture takes several weeks, but the green strength of
the material must be sufficient to remove the formed material, handle
it and perhaps even directly place it into a structure. Multi-stage
curing may be possible, but the re-application of moisture may cause
surface cracking and the extent of this needs to be further
investigated.
P a g e 6 | 17
3. Lime stabilization
When lime and water are added to a clay soil, chemical reactions
begin to occur almost immediately.
P a g e 7 | 17
layer with significant load bearing capacity. The process begins
within hours and can continue for years in a properly designed
system.
Fly ash is the most commonly used pozzolan. It is the finely divided
residue that results from the combustion of pulverized coal in power
plant boilers, which is transported from the combustion chamber by
exhaust gases.
Construction steps:
After the soil has been brought to line and grade, the subgrade
can be scarified to the specified depth and width and then partially
pulverized. It is desirable to remove non-soil materials larger than
75mm, such as stumps, roots, turf, and aggregates.
2. Lime Spreading:
i. Quicklime
P a g e 8 | 17
There are two ways that dry quicklime can be applied.
First, self- unloading trucks or trailers can distribute
quicklime pneumatically or mechanically the full width of
the truck. Because granular and pebble quicklime flow is
more controllable than hydrated lime, it is a common
practice to use trucks with built in aggregate-type
spreaders.
3. Slurry
6. Mellowing Period
P a g e 9 | 17
The lime-soil mixture should mellow sufficiently to allow the
chemical reaction to change (break down) the material. The
duration of this mellowing period should be based on engineering
judgment and is dependent on soil type. The mellowing period is
typically 1 to 7 days. After mellowing, the soil should be remixed
before compaction. For low Plasticity Index soils, or when drying
or modification is the goal, mellowing is often not necessary.
8. Compaction
9. Final Curing
Before placing the next layer of subbase (or base course), the
compacted subgrade (or subbase) should be allowed to harden
until loaded dump trucks can operate without rutting the surface.
P a g e 10 | 17
During this time, the surface of the lime treated soil should be
kept moist to aid in strength gain. This is called “curing” and can
be done in two ways: (a) moist curing, which consists of
maintaining the surface in a moist condition by light sprinkling
and rolling when necessary, and (b) membrane curing, which
involves sealing the compacted layer with a bituminous prime
coat emulsion.
4. Bituminous stabilization
2. Sand bitumen: Loose sand particles cemented with bitumen. The sad
can
P a g e 11 | 17
4. Oiled earth: A soil surface consisting of silt-clay materials is
stabilized by spraying slow or medium curing bitumen cutbacks
or emulsions. The main purpose of oiled earth is to produce a
water and abrasion resistant surface.
These are the four major kind of soil stabilization on road works, there are
many other kind of soil stabilization methods are in practice for building
construction sectors.
Answer :
1) CHECKLIST - FORMWORK
✓ Safe working areas and safe passageways provided to and from the
work areas— this means: safe working scaffolds, ladders, runways,
ramps and crossings.
✓ Amount of work space for each worker checked for adequacy without
crowding.
P a g e 12 | 17
orientation for unskilled workers or new employees.
✓ All loose material stored on open upper floors tied down or otherwise
secured.
✓ Exposed form ties projecting into the work area bent or removed.
P a g e 13 | 17
Checklist - Wall Form Safety
✓ All wall ties checked for proper strength, spacing and length.
✓ Resistance provided against uplift for top forms with sloping faces.
✓ Wales checked for proper spacing, with joints staggered from one tier to the
next.
✓ Suitability of mud sill sizes for shore loads and bearing value of soil;
working drawings checked for guidance.
✓ Soil firmly compacted under mud sills and proper drainage provided to
prevent ponding of water in the area.
P a g e 14 | 17
✓ Soil, if unstable, removed and replaced with stabilized material under
the sills; mudsills not supported on frozen ground.
✓ Individual shores laced both ways with continuous runners, and shoring
system braced laterally.
✓ On sloping slab or beam forms, extra bracing added to resist lateral forces.
✓ Columns poured at least one day ahead of slabs for added lateral stability
P a g e 15 | 17
✓ High drops from concrete buckets prevented, and ponding of concrete
on supported forms prohibited.
2) CHECKLIST - REINFROCEMENT
P a g e 16 | 17
Bibliography / References
Text book of NICMAR Construction Technology.
Websites.
P a g e 17 | 17