Professional Documents
Culture Documents
Analysis and Design of Optional Double Deck Girder Bridge
Analysis and Design of Optional Double Deck Girder Bridge
Elias Fekadu
Page i
DECLARATION
I, the undersigned, declare that the Project comprises my own work. In compliance with
internationally accepted practices, I have acknowledged and refereed all materials used in this
work. I understand that non-adherence to the principles of academic honesty and integrity,
misrepresentation/ fabrication of any idea/data/fact/source will constitute sufficient ground for
disciplinary action by the University and can also evoke penal action from the sources which
have not been properly cited or acknowledged.
This Project has been submitted for examination with my approval as a university advisor.
Page ii
Acknowledgement
The work presented in this Project has been carried out at the Department of Civil Engineering,
Bahir-dar University Institute of technology.
My deepest gratitude and thank go to Mr. Alemayehu Gola (advisor of the Project) for
inspiring me to do the project on this fascinating topic and advising me on works.
My greatest appreciation is to the staff of Digital & Electronics Library, AAiT and Google , for
kindly updated with latest, relevant and valuable books and journals.
I would like to express my warmest gratitude to my colleagues for their support with sharing
materials and ideas during the preparation of this Project work.
At last and most, my deeper gratitude extends to Mr. Daniel and other work colleagues for
allowing me to work with enough time and motivation.
Page iii
ABSTRACT
With the aim of developing combined highway and Railway crossing over Abay river, which
enables its connections with the South city Part called Abay Mado, this proposed bridge over
the River was designed. whose sought to integrate elegance and efficiency rather than super
imposed one on the other on the same single lane.
With a current population of 300,000 and Continuous rising, Bahir-dar will become one of
the largest cities in Ethiopia and in Africa also. Its two metropolitan (In the near future) Abay-
mado and other city area is bisected by Major River called Abay River, in recent years,
because of the rising population growth and urbanization, proposing of additional bridge over
existing Girder bridge is required and there, proposed construction of new bridge.
Despite the effort made to relieve congestion by building a new bridge, the rapid growth of
the City will continue to outpace transportation planners’ traffic projections and the existing
bridge is not sufficient to handle the ever-increasing traffic. In response to this problem, the
city is planning to build about 380 m of transit tracks to reduce pressure on city roads, but in
addition to erecting another bridge in the future during a demand of rapid transit and flow
without conflicting with vehicular and pedestrian traffic, for modern traffic distribution nature
it is better to consider a bridge with train crossing.
This combined highway and railway bridge which is, Extradosed Double deck box girder
bridge draws half of its support to be from box girders and half from a cable stayed system
that can rely on shorter towers, the bridge uses a box cross section where the box girder is
trussed in the elevation. The box girder is 8 m high and 7.2 m clear inside width according to
AREMA clearance requirement, pedestrian walkway cantilevered from the top of box girder
making the top deck width of 21m.
This bridge will be the Second Crossing of Abay River in bahir dar with a total length of 380
m.
So, in this project work, design of double deck partially cable stayed with the need of future
train crossing consideration for the increasing need of transportation for population and
commodity for the countries on the way to Gondor and Debretabor is made.
This bridge will have four lanes of highway traffic as well as pedestrian path on their upper
deck and it will carry single track of rail transit on their lower deck.
Page iv
The girders are steel truss structures with orthotropic plates and the towers are made of
concrete.
Table of Contents
ABSTRACT ......................................................................................................................................... iv
Acknowledgement ............................................................................................................................... iii
List of Symbols .................................................................................................................................. viii
List of abbreviations ............................................................................................................................ ix
List of Table ......................................................................................................................................... xi
List of figures ...................................................................................................................................... xii
Chapter 1 ............................................................................................................................................... 2
INTRODUCTION ................................................................................................................................ 2
1.1 Background ..................................................................................................................................... 2
1.2 Problem Statement .......................................................................................................................... 3
1.3 Objective ......................................................................................................................................... 4
General Objective ................................................................................................................................. 4
Specific objective .................................................................................................................................. 4
1.4 Methodology .............................................................................................................................. 4
1.5 Scope ............................................................................................................................................... 5
Chapter 2 ............................................................................................................................................... 6
Literature Review.................................................................................................................................. 6
2.1 Definition....................................................................................................................................... 6
2.2 General characteristics of a cable-stayed bridge ........................................................................... 6
2.3 Main Components of partially Cable Stayed Girder Bridge, ........................................................ 6
Deck:.............................................................................................................................................. 6
Truss girder; ................................................................................................................................... 6
Pylon; ............................................................................................................................................. 6
Cables: ........................................................................................................................................... 7
Cables arrangement ....................................................................................................................... 7
2.4 Optimum design formulation of cable stayed bridge .................................................................... 9
2.5 Types of Bridges for Railway ......................................................................................................... 9
2.5.1 Spacing Of Trusses, Girders, And Stringers (1995) R(2008)............................................. 10
2.5.2 Deflection (2001)1 R (2010) .............................................................................................. 10
2.5.3 Clearances (1995)1 R (2008).............................................................................................. 11
2.6 Bridge Type Selection................................................................................................................... 11
2.7 Loads on Bridge ............................................................................................................................ 16
Page v
2.7.1 Permanent loads ....................................................................................................................... 16
Highway bridges .......................................................................................................................... 16
Railway bridges ........................................................................................................................... 16
2.7.2 Live Load (1995)1 R (2008) .................................................................................................... 17
Highway bridges .......................................................................................................................... 17
Railway bridges ........................................................................................................................... 19
Distribution Of Live Load (1993)1 R(2008) ..................................................................................... 20
Ballasted Deck Structures............................................................................................................ 20
2.7.3 Dynamic loads .......................................................................................................................... 21
Highway Bridge [1] ................................................................................................................. 21
Rail way bridges .......................................................................................................................... 21
2.7.4 Braking Force: BR.................................................................................................................... 23
High Way Bridge ......................................................................................................................... 23
Railway bridges; .......................................................................................................................... 23
2.7.5 Wind forces on bridges............................................................................................................. 24
Highway Bridge ........................................................................................................................... 24
Wind Pressure on Structures........................................................................................................ 25
Wind Pressure on Vehicles:. ........................................................................................................ 25
Vertical Wind Pressure (effect of overturning) ........................................................................... 26
Railway Bridge ............................................................................................................................ 26
Chapter 3 ............................................................................................................................................. 28
Load Combinations ............................................................................................................................. 28
Highway bridges................................................................................................................................ 28
Load Factors and Load Combinations ......................................................................................... 28
Service Limit State ...................................................................................................................... 28
Fatigue and Fracture Limit State ................................................................................................. 28
Strength Limit state. .................................................................................................................... 29
Extreme Event Limit State .......................................................................................................... 29
Railway Bridge .................................................................................................................................. 30
Load combinations for steel bridges ................................................................................................. 30
High way Loadings input for the software ........................................................................................ 31
Dead load ................................................................................................................................. 31
Rail way Loadings input for the software ......................................................................................... 32
Dead load ................................................................................................................................. 32
Live load .................................................................................................................................. 32
Page vi
Impact load ........................................................................................................................... 33
Rocking effect (ch.15, 1.3.5 d) ............................................................................................. 33
Check for fatigue...................................................................................................................... 35
Applicable load combinations ..................................................................................................... 37
Chapter 4 ............................................................................................................................................. 38
Analysis and Design Section .............................................................................................................. 38
4.1 Functional Requirements .............................................................................................................. 38
Bridge Layout .............................................................................................................................. 38
Bridge Components ..................................................................................................................... 39
Pylon ........................................................................................................................................ 41
Deck ......................................................................................................................................... 42
Cables....................................................................................................................................... 44
Lateral Beams .......................................................................................................................... 44
4.2 Modeling Steps (Using SAP 2000 V. 20 Bridge Program) ......................................................... 45
After using cables with pre-tension force .................................................................................... 47
Deflection Limits ..................................................................................................................... 56
Final Design of cable:........................................................................................................................ 57
Design of pylon: ................................................................................................................................ 58
Design of composite section top Flange........................................................................................... 70
Recommendation for Better Results: ................................................................................................ 75
Reference ............................................................................................................................................ 76
Page vii
List of Symbols
Symbols Descriptions
A Detail category constant, cross-section area, axle load
As Area of steel
A The length of uniform deceleration(highway bridge braking force)
be Exterior effective width of composite section
bf Flange width
bt Width of tension flange
D Web depth, Degree of curve (Degrees based on 30 m chord)
Dcp depth of the web in compression at the plastic moment
DT Total depth of the composite section
do Transverse stiffener spacing (mm)
d Effective slab depth
E Modulus of elasticity of steel (MPa)
Distance between the centers of gravity of the basic beam and deck
eg
(mm)
W Wheel load
Ф Bar diameter, Resistance factors
Φf Resistance factor for flexure
Φv Resistance factor for shear
ηi Load modifier
ηD Ductility load modifier
ηR Redundancy load modifier
Page viii
Highway bridge load designations
List of abbreviations
AREMA = American Railway Engineering Maintenance of Way Association.
DL = Dead load.
EBCS = Ethiopian building code standard.
LL = Live load.
LRT= Light rail transit.
PSC = Pre-stressed concrete.
RC = Reinforced concrete.
SDL= Superimposed dead load.
ULS = Ultimate limits state.
ACI = American concrete institute.
Page ix
Railway bridge notations
A Axle load
AS Area of steel reinforcement
Aw Area of web
A The transverse beam span(railway bridge load distribution )
c Distance from extreme fiber to neutral axis, (mm)
Ffat Allowable fatigue stress
Fy Specified yield strength of reinforcement, (MPa)
fs
Tensile stress in reinforcement at service loads, (MPa).
ff Stress range in steel reinforcement, (MPa).
fV Shear stress
fr Modulus of rupture of concrete, (MPa).
f‘c Specified compressive strength of concrete, (MPa)
Extreme fiber compressive stress in concrete at service loads, (MPa), allowable service load Extrem
fc stress in compression fc = 0.40 f ‗c
Total maximum stress on cross-section
fb
Page x
List of Table
Page xi
List of figures
Page xii
Chapter 1
INTRODUCTION
1.1Background
With a current population of 300,000 and Continuous rapid rising, Bahir-dar will become one of the
largest cities in Ethiopia and in Africa also. Its two metropolitan (In the near future) Abaymado and
other city area will bisect by Major River called Abay River, and It is the main way of transport for
Bahirdar to Gondor and other big City of the country. In recent years, because of the rising
population growth and urbanization, Additional bridge beside the existing Girder bridge is required
and there, proposed construction of new bridge. Despite the effort made to relieve congestion by
building a new bridge, the rapid growth of the Country will continue to outpace transportation
planners‘ traffic projection and the existing bridge is not sufficient to handle the ever-increasing
traffic for population and imported commercial commodity.
In response to this problem, the city is planning to build about 380 m of transit tracks to reduce
pressure on the city road, but in addition to erecting another bridge in the future during a need of
extra bridge and train crossing, it is better to consider a bridge with Train crossing. So, in this project
work the need of future train crossing bridge is considered for the increasing need of transportation
for population and Commodity to Bahir-dar - Gondor Road.
This Double deck exradosed Bridge is designed as a Steel Girder Cable stayed bridge with a center
span of 180 m and two side spans measuring 100 m (Figure 4). The main girder (Figure 5) is designed
as a steel truss structure with double decks. The upper and lower decks each accommodate four lanes
of highway traffic as well as pedestrian path on their upper deck and it will carry Rail transit on the
lower deck. The girders are steel truss structures with orthotropic plates and the towers are made of
concrete.
Page 2
Figure 0.1.1 Proposed Bridge site
Page 3
1.3 Objective
General Objective
The general objective of this project is Design of optional crossing over Abay Bridge with enough
current and future traffic consideration and rail line consideration.
Specific objective
To give a clue of cable stayed bridges and Partially Cable stayed Girder Bridge concepts,
To assess the point of consideration to state the bridge type.
double deck Extradosed Girder Bridge Modeling, Design and analysis,
Designs of structural Components of the bridge, i.e. Cables, Steel Girders, Pylon and other.
1.4 Methodology
The methodologies carried out for this project work started with Reviewing of different journals from
Internet, AA electronic library, and some bridge and highway design references that has been accessed
on internet, American Association of State Highway and Transportation Officials ASHTO, American
Railway Engineering and Maintenance-of-Way Association AREMA and many others, After critical
assessments of proper bridge type and parameters, trial section components setting out and modeling
has been made on SAP V. 19.
Dead load components of both highway and rail way bridge is automatically considered except parts
of the super structure like guard and curbstones which has been defined manually.
Live load components have been defined automatically based on ASHTO and AREMA load and
combination recommendations for both highway and railways respectively.
After definition of material properties, section properties, loading properties and combinations, the
modeling has been run for analysis only with dead load, the deflection requirement has been checked,
parts of sections that are not adequate to support the dead components has been enhanced in property
for stiffness.
The model is set to consider the staged construction process in cantilevering of each 10m deck
components in both the right and left parts of the pylon at a time, so, at this part the initial stressing
force that has to be installed on the cable has been obtained on trial and Error.
Page 4
Finally, after installation of all components, analysis and Design, the sections that are not adequate for
supporting the applied load are modified and the sections that are over considered and thought to be un
economical has been set to be economical and the sections approved after many trial and Error in
analysis, design, section modification, considerations and estimation to make deflection and other
design requirements in workable estimation. section check design feature of the software is used.
This project basically focused on developing analysis and design of combined highway and railway
crossing over abay river with span length of 380 m, which have double decked feature with both girder
action of the steel and cable stayed action load resisting mechanism. Called Double deck Extradosed
girder bridge.
1.5Scope
The Scope of this project has been limited to give General Design of Double deck Cable stayed steel
girder bridge, and it is only limited to obtaining reaction load and stress‘s on the bridge components,
design of sections, i.e. truss girder section, composite deck section, pylon, cable requirements.
It didn‘t consider design of connections, Earth quake consideration, design of foundation requirement,
design of staged construction for cable stayed bridge, the preferred cable type selection, optimum
structural components design, and cable anchor mechanism.
Page 5
Chapter 2
Literature Review
2.1 Definition
The cable-stayed bridges consist a deck (superstructure) supported by straight and inclined cables
which are connected to one or two towers. So the structural system is composed by these three main
elements: the deck and the stiffening girder, the cables and the towers. In general, the design of these
elements is closely related to the other so we will detail it and how they relate to each other.
The length of a side span comes about 30-40 % of the main span.
Cables formed from high strength steel wires with certain flexibility supporting the
whole structure.
Two towers, which can be made by metal or reinforced concrete, situated between the
central span and the two lateral spans providing a support to the cables. Optimizations
indicate that towers heights are about 1/5 of the main span.
Page 6
pylon, Twin pylon, A-frame pylon, and Single pylon. They are chosen based on the structure of the
cable stayed bridge (for different cable arrangements), aesthetics, length, and other environmental
parameters.
The first cable-stayed bridges used are steel towers. Since, towers are mainly loaded by
compression, concrete towers are more economical, therefore, concrete towers are mainly used
today. bad foundation conditions would require very long piles so in order to decrease the dead
weight of tower lighter steel towers are used in some bad foundation condition scenarios.
Cables: Cables are one of the main parts of a cable-stayed bridge. They transfer the dead weight of the
deck to the pylons. These cables are usually post- tensioned based on the weight of the deck. The cables
post-tensioned forces are selected in a way to minimize both the vertical deflection of the deck and
lateral deflection of the pylons. There are four major types of stay cables including, parallel-bar,
parallel-wire, standard, and locked- coil cables. The choice of these cables depends mainly on the
mechanical Properties, structural properties and economic criteria.
Cables arrangement
We will classify cable-stayed bridges according to the cable disposition in the longitudinal and
transversal direction. As it happens in suspension bridges the economical factor will be very important
so we don‘t have to be careful only with the design of the cables in terms of structural performance.
Thus, our layout will pretend to cover all the requirements (site conditions, aesthetic appearance…)
with the best possible design.
Harp system: The cables are parallel to each other and are connected to the tower at different heights
making the aesthetic of this kind of configuration very pleasant. However, with this system the towers
should be higher and have more inclination, which increases the stiffness of the system. Therefore, the
compression in the girder is very high and in terms of safety, this system is less efficient than the fan
arrangement because the inclination of the cables is less pronounced.
Semi-harp system: This system works almost as the fan configuration where all the cables are
connected to the tower at convenient distances without being parallel. We achieve the maximum
inclination of the cables rising then the maximum vertical force and consequently reducing the amount
of material required in the girder.
Fan system: the cables are anchored at the top of the towers, from the same point, which involves
problems in the details of the anchorages because of the cable congestion and therefore in the
construction and maintenance process which turns out to be complicated.
In the transversal direction we will classify them according to the plane where the cables are disposed:
Page 7
single central plane system, two lateral plane system and three plane system.
- Single central plane system: This type of system has only one vertical plane of stay cables along the
middle longitudinal axis of the superstructure thus the space is used by the traffic. However the
torsional forces are very significant in this layout conditioning the design of the girder and in this case
his stiffness.
- Two lateral plane system: This arrangement has two planes situated in the lateral borders of the
bridge and depending on the shape of the tower the layout can be vertical or inclined.
- Three plane system: This last layout is a combination of the two previous models. On the one hand
we will achieve higher stiffness but on the other hand the economic cost of construction will be higher
too.
Page 8
Figure 2.3.2 Single lateral plane system, two lateral plane system and three plane system
Longitudinal Cable arrangement of cable stayed bridge
The design parameters that affect the optimum design cost of cable-stayed bridges are considered as
design variables in the proposed numerical design model. The vector of design variables x includes
the number of stay cables, geometric configuration, and cross-sectional dimensions of bridge
elements. Those are
Page 9
b) Pin connected trusses may be used for unusual conditions, but special provisions applicable
to their design and construction shall be prepared and furnished by the Engineer.
So, bolted trusses has been preferred for this Design of partially Cable stayed double deck steel
girder bridge over Abay river with span length of 100 m.
a. The distance between centers of outside trusses or girders shall be sufficient to prevent
overturning by the specified lateral loads. In no case shall it be less than 1/20 of the span for
through spans, nor 1/15 of the span for deck spans.
b. Where the track is supported by a pair of deck girders or stringers, the distance center to center
shall be not less than 6-6. If multiple girders or stringers are used, they shall be arranged as
nearly as possible to distribute the track load uniformly to all members.
a) The deflection of the structure shall be computed for the live loading plus impact loading condition
producing the maximum bending moment at mid-span for simple spans. The computation of
component stiffness shall be based on the following assumed behavior:
• For flexural members use the gross moment of inertia.
• For truss members without perforated cover plates use the gross area.
• For truss members with perforated cover plates use the effective area.
The effective area shall be the gross area reduced by the area determined by dividing the volume of
a perforation by the distance center to center of perforations.
b) The structure shall be so designed that the computed deflection shall not exceed 1/640 of the span
length center to center of bearings for simple spans.
c) Lateral deflection of spans shall be limited to 3/8 inch (10 mm) for tangent track as measured on a
62 foot (19 meter) chord. On curved track, lateral deflection shall be limited to 1/4 inch (6 mm) as
measured on a 31 foot (9.5 meter) chord. Allowable lateral deflection for spans shall be calculated
based on these limits taken in squared proportion to the span length under consideration.
The lateral deflection calculated is to be the maximum lateral deflection at track level due to all
applicable lateral forces and loads specified in Section 1.3 excepting those due to earthquake
(seismic) or wind on unloaded bridges. The maximum lateral deflection at track level shall be
referenced to the point on a vertical plane below which lateral deflection is restrained (i.e. base of
structure, span bearings, bottom flange of girder; depending on the lateral deflection being
considered).
Page 10
2.5.3 Clearances (1995)1 R (2008)
a) The clearances on straight track shall be not less than those shown in Figure 15-1-1. On curved
track, the lateral clearance each side of track centerline shall be increased 1-1/2 inches per
degree of curvature. When the fixed obstruction is on tangent track, but the track is curved
within 80 feet of the obstruction, the lateral clearance each side of track centerline shall be
increased as shown in Table 15-1-4.
b) Where legal requirements specify greater clearances, such requirements shall govern.
c) The super elevation of the outer rail shall be specified by the Engineer. The distance from the
top of rail to the top of tie shall be assumed as 8 inches, unless otherwise specified by the
Engineer.
d) Where there are plans for electrification, the minimum vertical clearance shall be increased to
Page 11
To increase the transparency of the bridges.
Why Cable stayed selected? This kind of bridge is selected because of the surrounding nature of
proposed bridge site and span length requirement.
Why Double deck is preferred? Why not Simple span together with the train crossing?
Foundation condition (requirement), despite the cost of steel, the member and joint action of
truss members of box girders, box girder mechanism of the bridge decreases the amount of load
transmitted to the foundation.
Load distribution and construction mechanism, a cantilever method construction is assumed to
be applied, and hence we require a high strength material.
Aesthetically The rail and truck together on the same single deck demands too long pylons with
too short span and too wide section, which is not interesting. The tower shape of a double-deck
bridge is better than that of a single-deck bridge. Thus, the double-deck cable stayed box girder
bridge is preferred.
Page 12
Even for live loads the bending moments of the beam elastically supported by the stay cables remain
small.
Large compression forces in the beam are caused by the horizontal components of the inclined stay
cables. The normal forces in the main and side span equal one another so that only uplift forces have to
be anchored in the abutments which act as hold-down piers.
Page 13
Figure 2.5.4 General Layout of Main Bridge, Super Structure and Truss Girder
Page 14
Page 15
2.7 Loads on Bridge
Permanent loads are those that remain on the bridge for an extended period of time, perhaps
for the entire service life such loads include:[11]
Railway bridges
Superstructure dead load consists of the weight of the superstructure itself ,track, deck(open ballasted),
utilities(conduits ,pipes and cables),walk ways(some engineers also include walk way live load as a
component of super structure dead load.),permanent formwork, snow ,ice and anticipated future dead
loads( e.g. larger deck ties, increases in ballast depth, and
additional utilities).
Open-deck through-plate girder, through-truss, and some deck truss spans usually contain floor systems
comprised of longitudinal stringers and transverse floor beams (Fig 3.1 (a)).
Ballasted-deck through-plate girder spans generally have the concrete or steel plate decks supported on
closely spaced transverse floor beams framing into the main girder (Fig 3.1 (b)).
In some cases, such as through-truss spans, stringers with less closely spaced transverse floor beams are
used.
In general Bridges shall be proportioned for the following load cases:
1. Dead load.
2. Live load.
3. Impact load.
4. Wind forces.
Page 16
5. Centrifugal force.
6. Forces from continuous welded rail – See Part 8, Miscellaneous; Section 8.3, Anchorage
of Decks and Rails on Steel Bridges on AREMA.
7. Other lateral forces.
8. Longitudinal forces.
9. Earthquake forces.
a. In estimating the weight for the purpose of computing dead load stresses, the unit weights found
in Table 15-1-5 shall be used.
b. The track rails, inside guard rails, and their rail fastenings shall be assumed to weigh 200 lb per
linear foot for each track.
AASHTO LRFD specification recommends Vehicular live loading on the highways of bridges or
incidental structures, designated HL-93, consist of a combination of the:[11]
❑ Design truck
❑ Design tandem
❑ Design lane
Page 17
Design truck
The design truck (shown in fig 3-2) is a model load that consists of front axle weighs 35 kN, and the
drive axle of 145 KN is located 4.3 m behind, and the rear trailer axle is also 145 kN and is positioned at a
variable distance ranging between 4.3 and 9 m.
Design tandem
The second configuration is the design tandem and consists of two axles weighing 110 KN each spaced at
1.2 m.
Design lane
The third load is the design lane load that consists of a uniformly distributed load of 9.3 N/mm and is
assumed to occupy a region 3000 mm transversely. This load is the same as a uniform pressure of 3.1 KPa
Page 18
For both negative moment (tension on top) between points of contra-flexure under a
uniform load on all spans, and reaction at interior supports, 90 percent of the effect of
two design trucks spaced a minimum of 15 000 mm between the lead axle of one truck
and the rear axle of the other truck, combined with 90 percent of the effect of the
design lane load. The distance between the 145-KN axles of each truck shall be taken
as 4300 mm.
Railway bridges
A. The recommended live load in lb per axle and uniform trailing load for each track is the
Cooper E 80 load shown in Figure 15-1-2 or the Alternate Live Load on 4 axles spaced as
shown in Figure 15-1-3, whichever produces the greater stresses.
B. The Engineer shall specify the live load to be used, and such load shall be proportional to the
recommended load, with the same axle spacing.
C. For bridges on curves, provision shall be made for the increased proportion carried by any
truss, girder, or stringer due to the eccentricity of the load.
d. For members receiving load from more than one track, the design live load on the tracks
shall be as follows:
Page 19
For three tracks, full live load on two tracks and one-half on the other track, For four
tracks, full live load on two tracks, one-half on one track, and one-quarter on the
remaining one.
For more than four tracks, as specified by the Engineer.
The selection of the tracks for these loads shall be such as will produce the greatest
live load stress in the member.
Page 20
2.7.3 Dynamic loads
Highway Bridge [1]
The dynamic load allowance (IM) is an increment to be applied to the static wheel load to account
for wheel load impact from moving vehicles. Dynamic effects due to moving vehicles may be
attributed to two sources:
Hammering effect is the dynamic response of the wheel assembly to riding surface
discontinuities, such as deck joints, cracks, potholes, and delimitations, and
Dynamic response of the bridge as a whole to passing vehicles, which may be due to
long undulations in the roadway pavement, such as those caused by settlement of
fill, or to resonant excitation as a result of similar frequencies of vibration between
All other components in Table 3.2 include girders, beams, bearings (except elastomeric bearings), and
columns. These factors are to be applied to the static load as,
UL+I = UL (1 + IM)
Where UL+I is the live-load effect plus allowance for dynamic loading, UL is the live-load effect of
live load, and IM is the fraction given in the Table 2.7.3.
Impact load
Page 21
a) Impact load, due to the sum of vertical effects (Paragraph c) and rocking effect (Paragraph d)
created by passage of locomotives and train loads, shall be determined by taking a percentage
of the live load specified in Article 1.3.3 and shall be applied vertically at top of each rail.
b) For open deck bridges the percentage of live load to be used shall be determined in
accordance with Paragraph c and Paragraph d below. For ballasted deck bridges the impact
load to be used shall be 90% of that specified for open deck bridges. These formulas do not
cover direct fixation decks.
c) Impact load due to vertical effects, expressed as a percentage of live load applied at each rail,
shall be determined by the applicable formula below:
(1) Percentage of live load for rolling equipment without hammer blow (freight and
passenger cars, and locomotives other than steam):
d) Impact load due to rocking effect, RE, is created by the transfer of load from the wheels on
one side of a car or locomotive to the other side from periodic lateral rocking of the
equipment. RE shall be calculated from loads applied as a vertical force couple, each being
20 percent of the wheel load without impact, acting downward on one rail and upward on the
other. The couple shall be applied on each track in the direction that will produce the greatest
force in the member under consideration.
The impact factor for railway bridge comprises the effects due to vehicle rocking, RE, and the
vertical effects due to superstructure –vehicle interaction, Iv, or
If = RE + Iv (Vertical effect)
Vertical effects
Superstructure vibration is induced by the moving load (locomotives and cars) suspension systems
as the loads traverse a railway bridge with surface irregularities. AREMA (2010) recommended
impact due to vertical effects for simply supported open deck steel bridges as
Percentage of live load for rolling equipment without hammer blow (freight and
passenger cars, and Locomotives other than steam):
Page 22
For L 24m or more:
The impact load for ballasted deck steel bridges may be reduced to 90% of the total impact
load determined for open deck bridges. Design impact load is the sum of the impact load due
to rocking and vertical effects.
Based on energy principles, and assuming uniform deceleration, the braking force determined as a
fraction of vehicle weight is:
Where a is the length of uniform deceleration and b is the fraction. Calculations using a braking length
of 122 m and a speed of 90 km/hr. (25 d sec.) yield b = 0.26 for a horizontal force that will act for a
period of about 10 seconds.
The factor b applies to all lanes in one direction because all vehicles may have reacted within this
time frame. The braking force shall be taken as the greater of:
o 25% percent of the axle weights of the design truck or design tandem or,
o 5% percent of the design truck plus lane load or 5 percent of the design tandem plus
lane load, These forces shall be assumed to act horizontally at a distance of 1800 mm
above the roadway surface in either longitudinal direction to cause extreme force effects.
Railway bridges;
Longitudinal forces, due to train braking (acting at the center of gravity of the live load) and
locomotive tractive effort (acting at the freight equipment draw bars or couplers), are considerable
Page 23
for modern railway freight equipment, the longitudinal force for E-80 loading shall be taken as the
larger of:
o Force due to braking, as prescribed by the following equation, acting 2500 mm above
top of rail:
o Longitudinal braking force (KN) = 200 + 17.5 L
Force due to traction, as prescribed by the following equation, acting 900 mm above top of rail:
Longitudinal traction force (kN) = 200 √L
Where:
L is length in meters of the portion of the bridge under consideration. For design loads other than
EM-360, these forces shall be scaled proportionally. The points of force application shall not be
changed.
The distribution of longitudinal forces for the design of span bracing ,bearings, substructures, and
foundations need careful consideration .the distribution and path of longitudinal forces between their
point of application and the bridge supports depend on the arrangement ,orientation, and relative
stiffness of
Bridge members in the load path
Bearing type
Substructure characteristics.
Wind loading offers a complicated set of loading conditions which must be idealized in order to
provide a workable design. Although the problem of modeling wind forces is a dynamic one, with
winds acting over a given time interval, these forces can be approximated as a static load being
uniformly distributed over the exposed regions of a bridge.
The loading on a bridge due to wind forces is specified by AASHTO based on an assumed wind
velocity of 160 Km/h. With regard to the superstructure, wind forces are applied in a transverse and
longitudinal direction at the center of gravity of the exposed region of the superstructure. AASHTO
LRFD offers a set of wind loading values for truss and girder bridges based on the angle of attack
(skew angle) of wind forces. Conventional slab on stringer bridges, however, with span lengths less
than or equal to 38.1 m can utilize the following basic loading,
Page 24
Wind Pressure on Structures: WS [1]
Transverse Loading
The total wind loading shall not be taken less than 4.4 N/mm in the plane of a windward chord and 2.2
N/mm in the plane of a leeward chord on truss and arch components, and not less than 4.4 N/mm on
beam or girder spans.
Page 25
Longitudinal loading=0.58 KN/m2
The transverse and longitudinal loads are to be placed simultaneously for both the
structure and live load.
To account for the effect of overturning, AASHTO specifies A vertical upward wind force of
-4
9. 6 *10 MPa times the width of the deck, including parapets and sidewalks, shall be considered to
be a longitudinal line load. This force shall be applied only for limit states that do not involve wind
on live load, and only when the direction of wind is taken to be perpendicular to the longitudinal axis
of the bridge. This lineal force shall be applied at the windward quarter-point of the deck width in
conjunction with the horizontal wind loads. This load may govern where overturning of the bridge is
investigated.
Railway Bridge
As a minimum, the bridge shall be designed for laterally and longitudinally applied wind forces
acting independently as follows:
On the train, the lateral wind force shall be taken at 1.33 KN per linear meter applied
normal to the train on one track at a distance of 2.4m above top of rail.
On the bridge, lateral wind pressure shall be taken at 1.48KN/m2 (The AREMA (2010))
design recommendations for wind load on a loaded steel railway bridge superstructure
assume that the maximum wind velocity at which trains can safely operate (to avoid
Page 26
overturning of empty cars) will produce a wind pressure of 1.48KN/m2 normal to the
following surfaces:
A. For girder spans, 1.5 times the vertical projection of the span. (in order to account
for the effects of paired or multiple girders, these wind pressures are to be applied to
a surface 50% greater than the projected surface area of a girder span.)
B. For truss spans, the vertical projection of the span plus any portion of leeward
trusses not shielded by the floor system.
C. For viaduct towers and bents, the vertical projection of all windward and leeward
columns and bracing.
The lateral wind force on girder and truss spans, however, shall not be taken as less than
0.89 KN/m for the loaded chord or flange and 0.665KN/m for the unloaded chord or
flange, neglecting the wind force on the floor system.
Page 27
Chapter 3
Load Combinations
Every component of substructure and superstructure should be proportioned to resist all combinations of
forces applicable to the type of bridge and its site. Members subjected to stresses from dead, live, impact,
and centrifugal loads should be designed for the basic allowable unit stress or the allowable fatigue stress,
whichever governs.
Highway bridges
The load factors for various load combinations and permanent loads are given in Tables 3.1 and 3.2,
respectively. Explanations of the different limit states are given in the sections as follow,
The service limit state refers to restrictions on stresses, deflections, and crack widths of bridge
components that occur under regular service conditions [A1.3.2.2]. For the service limit state, the
resistance factors φ = 1, and nearly all of the load factors γi are equal to 1.0. There are four different
service limit state load combinations given in Table 3.2 to address different design situations
[A3.4.1].
The fatigue and fracture limit state refers to a set of restrictions on stress range caused by a design
truck. The restrictions depend on the number of stress-range excursions expected to occur during the
design life of the bridge [A1.3.2.3]. They are intended to limit crack growth under repetitive loads
and to prevent fracture due to cumulative stress effects in steel elements, components, and
connections. For the fatigue and fracture limit state, φ = 10.
Page 28
Strength Limit state
The strength limit state refers to providing sufficient strength or resistance to satisfy the inequality of
Eq. 2.1 for the statistically significant load combinations that a bridge is expected to experience in its
design life [A1.3.2.4]. Strength limit states include the evaluation of resistance to bending, shear,
torsion, and axial load. The statistically determined resistance factor φ will usually be less than 1.0
and will have different values for different materials and strength limit states.
The extreme event limit state refers to the structural survival of a bridge during a major earthquake
or flood or when collided by a vessel, vehicle, or ice floe [A1.3.2.5]. The probability of these events
occurring simultaneously is extremely low; therefore, they are specified to be applied separately. The
recurrence interval of extreme events may be significantly greater than the design life of the bridge
[C1.3.2.5].
Under these extreme conditions, the structure is expected to undergo considerable inelastic
Page 29
deformation by which locked-in force effects due to TU, TG, CR, SH, and SE are expected.
Railway Bridge
Load combinations for steel bridges
Every component of substructure and superstructure should be proportioned to resist all combinations
of forces applicable to the type of bridge and its site. Members subjected to stresses from dead, live,
impact, and centrifugal loads should be designed for the basic allowable unit stress or the allowable
fatigue stress, whichever governs.
With the exception of floor beam hangers, members subjected to stresses from other lateral or
longitudinal forces, as well as to dead, live, impact, and centrifugal loads, may be proportioned for
125% of the basic allowable unit stresses, without regard for fatigue. However, the section should not
be smaller than that required to satisfy basic unit stresses or the allowable fatigue stress range when
those lateral or longitudinal forces are not present.
Components subject to stresses from wind loads only should be designed for the basic allowable
stresses. Also, no increase in the basic allowable stresses in high-strength bolts should be taken for
connections of members covered in this article. Elastic analysis procedures are usually used for steel
Page 30
railroad bridges.
Table 3.2 load combination for steel railway bridge Super structure design
Chap. 15 of the AREMA MRE provides recommendations for allowable stress design. The design
service life of railroad bridges is generally considered to be about 80 years.
AREMA MRE does not provide explicit load combinations but incorporates combinations in various
design recommendations (Sorgenfrei and Marianos, 2000). Table 6 outlines load combinations that
apply to steel superstructure design found in various recommendations of AREMA.
D3 =barriers dead load (assumed to be distributed on the girders as normal line load and
moment actions.) (Density of concrete 2500 Kg/m3)
Moment applied on girder by Internal Barrier 1 anti-clockwise moment
( (( ) ( )) )
Finally, (11.808+15.303)-8.093= 19.018 KNm/m of anti-clockwise moment will apply on both girders.
Page 31
These moments are made to act as clockwisely and anti clockwisely on the girders on their
corresponding load Direction and are defined on the software.
The dead component of structure has been considered automatically in the software.
A. Design of Reinforced Concrete Deck
Taking 1m Strip
Load computations
Dead load of ballast +tie +track
=170mm*19Kg/m3 (density of ballast including tie ch.15, 1.3.2a)*9.81m/s2
= 3.168KN/m+0.64KN/m (allowance for track weight)
=3.8KN/m
Concrete slab dead load
=300mm*2400Kg/m3 (density of concrete)*9.81m/s2
=7KN/m Curb dead load (treated as concentrated load)
=300mm*680mm*2400Kg/m3*9.81m/s2 = 4.8KN
Live load
According to (ch.15, 1.7.9.2b) and (Ch. 15, 1.15.1), the governing live load is that of cooper E80
(EM360). The maximum axel load to be used for design of slab is 360KN which distributed
according to (Ch. 15,1.3.4.2.2) to a length of L tie+ L bottom of tie to top of girder = 2.934m to
yield 123KN/m laterally distributed load.
(ch.15, 1.3.3 ), Analysis of load effects (taking 1m wide slab), is computed on SAP V.19.
DL M max +ve=1.36KNm
DL M max -ve=-5.26 KNm(along with the LL Mmax –ve ),
&-1.55KNm (at face of support)
LL M max +ve=82.65 KNm
LL Mmax –ve=-32.6 KNm
Page 32
Figure 3.1 Cross Section of Train Way
Impact load
According to (ch.15, 1.7.9.2 b), the impact load is applied that of steel bridges, for L<53m full impact
for double track. Vertical effects (ch.15, 1.3.5 c) The train is assumed to be modern railroad equipment
(diesel locomotives and modern freight cars)
for L>80ft (24.38) , which is 328.08ft (180m).
Page 33
Combination 1 is Applicable
Group 1 D + L + I + CF + E + B + SF
Load combination applicable for design of concrete slab (ch.8, 2.2.4b), Group loading
and Can be reduced to group 1 D+L+I
Design moment (DL+LL+IM) +VE=110KNm+1.36KNm
=111.36KNm
Design moment (DL+LL+IM) –VE =-43.4KNm-1.55KNm
=-45KNm
Concrete slab thickness = 300mm
Width of slab = 1000mm
d=300mm-40(8, 2.6.1 minimum cover)-10(use Ф20)
=250mm
( )
√ √ , db =231mm<d=250mm
Use d=250mm
√ √
√ √ , which is 3140mm2
[ch.8, 2.7a] states that at any section of a flexural member where tension reinforcement is required by
analysis, the reinforcement provided shall be adequate to develop a design moment strength ФMn at
least 1.2 times the cracking moment calculated on the basis of the modulus of rupture for normal
weight concrete [ch.8,2.26.1a].
Mcr=Snc*fr= (bh/6 )*0.62√f‘c
= (1*0.32/6 )*0.62 √30 =51KNm
Page 34
1.2 Mcr=61.1KNm<Mn=117.3KNm …………………..OK
Mn=AS (fs*j*d) =3140mm2*(170MPa*0.879*.25m)
=117.3KNm
Check for fatigue
Mean Impact load for fatigue (ch.15, 1.3.13) is taken as 35% of the impact load computed, which is,
Fatigue IM = 35 %( 33%) =11.55%
Fatigue LL + IM M max +ve =82.65 KNm*1.1155
=92.2KNm
The fatigue stress limit according to (ch.8, 2.26.2 b) is
( ) , fmin =0 for this case.
r/h =0.3,
( ) ( )
Taking the quarter span section of the bridge with a length of 100m.
From (ch.15, 1.15.1, Table ch.15-1-15) Cooper E80 governs for L=100m (328 ft)
(wheel load per rail, per girder in this case). And the effects are,
Page 35
Table 2.4 Table for Live loads Determination with corresponding Span length
Page 36
=47492.5 KNm
Load combinations uses for girder design are A1, B1 and C, the rest applies for design of
cross-frames.
WL (wind load on live load) =4.4KN/m wind on live load acting @2.45m above the rail
(ch.15, 1.3.7a). Vertical distributed load on exterior girder can be calculated as
Longitudinal wind load (which produce shear force and longitudinal horizontal force)
Page 37
For loaded bridge =50% of lateral wind force for truss span (0.00144MPa) (ch.15, 1.3.7d)
Longitudinal wind=0 .50*8.635KN/m
=4.312KN/m acting @ 2.45m above rail
Shear force = (additive with shear force computed Shear
from WV to compare with the shear force for unloaded longitudinal calculated below)
Total wind shear force on the truss =10.32KN+21KN (governs) =31.3KN
Combination B1
V=3499.97 + 84.28+31.3=3615.55 KN
Chapter 4
Analysis and Design Section
4.1 Functional Requirements
Bridge Layout
Bridge Components
1) Pylon
2) Deck
3) Cables
4) Truss Girder
5) Lateral Beam
Page 39
Figure 4.1 3DModel
Page 40
Pylon
The Pylon is the main support of cable-stayed bridges. Cables link the deck to the pylon, so it
can carry the deck safely. Our pylon is a Reinforced Concrete A-Shaped Column. The section
Figure 4.2 The section detail of top and bottom section of pylon.
Page 41
Figure 4.3 Pylon and Lateral Support Mechanism
Deck
Deck Properties: -
Top Deck Property; - 20.00-meter width (Consists of 4 lanes of highway traffic- 2 lanes in each
direction, 2 sidewalks of width equals 2.0 m, one in each side, and an island of width equals 1.5
meters on the median)
Bottom Steel Girder property; - 6.6 m width between the steel girders for one-way train crossing for
Assumed Cooper E80 load,
Providing 170mm thick ballast and a standard tie 2.45m long and 205mm wide spaced at
610mm (ch.15,1.3.4.2.1).
providing concrete deck thickness of 300mm (ch.15,1.3.4.2.2) Use f’c= 30 MPa and M270
Grade 345 steel.
Page 42
Figure 4.4 Rail way section
Material Properties for Pylon and Deck: concrete has a specified compressive strength equals 400MPa,
Page 43
Figure 4.6 Cables Arrangement Model
Cables
In this bridge we have 8 cables lied in each side of A shaped pylon on the median plan of the deck. The
distance between the cables and 2 meters at its link to the pylon on the top.
Fu = 17.7 T/Cm^2
Fy= .89* 17.7 = 15.7 T/Cm^2
E = 1950 T/Cm^2
Diameter = 15.7 mm
Diameter of the first two cables 7cm, the second three cables 10 cm and the
rest three cables are 12 cm from the pylon side to outside sequence
Lateral Beams
In this bridge two lateral beams exists, that connects the two pylon columns with the pylons
concrete nature and designed reinforcement requirement.
Page 44
4.2 Modeling Steps (Using SAP 2000 V. 20 Bridge Program)
1) Drawing the layout Grid lines of the bridge.
2) Defining the bridge and Girder sections, first assumed and then designed.
3) Drawing the bridge and other sections with previously defined sections.
4) Defining and drawing the pylon.
5) Defining and drawing the rigid links to link the deck sec. to cables as one unit.
6) Defining springs and releases.
7) Analysis of the model to get the deformation due to dead load.
8) Defining the cables (Diameter & Pretension Force) which achieve deformation equals to zero.
9) Defining the design vehicle and vehicle class.
10) Defining All Cases of Moving Load.
11) Solving due to moving load and getting deformation.
12) Defining the wind loads, the Earth quake force is not considered hence Bahir-dar is located in Zone
III.
13) Defining load combinations.
14) Design the bridge for applied load cases i.e traffic loads, wind loads, impact loads, lane loads, to
make within the deflection requirement limit.
15) Checking and verifying the assumed bridge structural components, with trial and error iterations.
16) Design of cables and final Pylon Design as a concrete column.
Page 45
Philosophy of Analysis:
1-Find the value of cable tension that will give optimum deck profile for
final model.
2- Stage construction analysis to find cable force during erection.
3- Final checks with Wind and other effects
The Program Outputs: Deformation due to Dead Load only (Without Cables) Joints Labels These joints
are at the center of the deck.
Table 4.1 Mid spans maximum joint deflection withought cable supports
Page 46
Thus from the table: - The max deflection is at P1557, P1558 and P1560 which are at the mid span
joints, and equals to 0.808 m. the other displacement results has been attached on the attached
appendix.
After troublesome trial and error checking of pretension forces estimation that produces the deflection
requirement with in the allowable limit and staged construction consideration,
Final pretension requirement of cables has been classified in to three groups according to estimated
requirements.
Page 47
The 2nd group consists of the next 3 cables. This group has cables of diameter equals to 10.00 cm,
and a tension force of 450 ton of its end, which is linked to the pylon.
Figure 4.9 Second Group of Cable with 450 ton pre tension Force
The 3rd group consists of the next 3 cables. This group has cables of diameter equals to 12.00 cm,
Page 48
and a tension force of 620 tons of its end, which linked to the pylon.
Figure 4.10 Second Group of Cable with 620 ton pre tension Force
Almost no deformation … The output values are due to the combination between Target and Dead
Load.
Page 49
Table 4.2 Mid span Deflection after pre tension Force
The max Deflection at P437 & P438 equals to 3.2 cm.
Page 50
Page 51
Figure 4.13 Moment Diagram, Axial force and Shear Force Diagram by Self Weight
Moving Loads:
The Bridge consists of
Page 52
The lane width equals to 3.90 meters.
Moving Load Model (1): Consists of concentrated and distributed load. Truck 60ton,
Truck40ton and Truck 20ton. Uniform 0.25t/m^2 for The rest of road width Uniform 0.5t/m^2 for
Page 53
Figure 4.15 Joint Displacement After Moving Loads Installation
Page 54
TABLE: Joint Displacements
Joint OutputCase
CaseType StepType U1 U2 U3
Text Text Text Text m m m
162 COMB A1 Combination Min 8.02E-06 0.001101 -0.00566
163 DEAD NonStatic Max 2.91E-06 0.00043 0
163 DEAD NonStatic Min 0 0 -0.00227
163 COMB A1 CombinationMax 8.72E-06 0.001289 -0.00455
163 COMB A1 Combination Min 5.82E-06 0.000859 -0.00682
190 DEAD NonStatic Max 2.84E-06 0.000407 0
190 DEAD NonStatic Min 0 0 -0.00683
190 COMB A1 CombinationMax 8.51E-06 0.00122 -0.01367
190 COMB A1 Combination Min 5.67E-06 0.000813 -0.0205
191 DEAD NonStatic Max 2.77E-06 0.000409 0
191 DEAD NonStatic Min 0 0 -0.008
191 COMB A1 CombinationMax 8.32E-06 0.001228 -0.01601
191 COMB A1 Combination Min 5.54E-06 0.000819 -0.02401
192 DEAD NonStatic Max 2.7E-06 0.000422 0
192 DEAD NonStatic Min 0 0 -0.00709
192 COMB A1 CombinationMax 8.11E-06 0.001266 -0.01417
192 COMB A1 Combination Min 5.4E-06 0.000844 -0.02125
193 DEAD NonStatic Max 2.63E-06 0.00043 0
193 DEAD NonStatic Min 0 0 -0.00768
193 COMB A1 CombinationMax 7.88E-06 0.001289 -0.01536
193 COMB A1 Combination Min 5.26E-06 0.000859 -0.02304
194 DEAD NonStatic Max 2.55E-06 0.000439 0
194 DEAD NonStatic Min 0 0 -0.00688
194 COMB A1 CombinationMax 7.65E-06 0.001316 -0.01375
194 COMB A1 Combination Min 5.1E-06 0.000877 -0.02063
195 DEAD NonStatic Max 2.47E-06 0.000449 0
195 DEAD NonStatic Min 0 0 -0.00758
195 COMB A1 CombinationMax 7.4E-06 0.001346 -0.01516
195 COMB A1 Combination Min 4.94E-06 0.000897 -0.02275
196 DEAD NonStatic Max 2.38E-06 0.000455 0
196 DEAD NonStatic Min 0 0 -0.00682
196 COMB A1 CombinationMax 7.15E-06 0.001366 -0.01364
196 COMB A1 Combination Min 4.76E-06 0.00091 -0.02046
197 DEAD NonStatic Max 2.29E-06 0.000465 0
197 DEAD NonStatic Min 0 0 -0.00753
197 COMB A1 CombinationMax 6.88E-06 0.001396 -0.01506
197 COMB A1 Combination Min 4.59E-06 0.000931 -0.02259
198 DEAD NonStatic Max 2.2E-06 0.00047 0
Table 4.3 Mid span Deflection after application of all forces.
The maximum deflections have been highlighted on the above table and all are in the margin of
allowable deflection. The max deflection equals to 2.4 cm.
Page 55
Chapter 5
Result and Discussion
This chapter of the paper includes the design result output from the software, separate design
verifications to check output result of the software and general results obtained that makes the bridge
functional.
Deflection Limits
The maximum allowable live load deflaction ot center of the main span should be, maximum of the
deflection requirement of the highway and rail way, so for the median span of 180m.
Highway deflection limit 1/500 of the main span, which is 100,000/500, 200 mm which is
measured along the centerline of the bridge.
Railway Deflection Limit, 1/680 of the main span, which is 100,000/680, 147.7mm which is
measures along the centerline of the bridge,
So, the deflection requirement will governed bey the railway is greater than the design output
of the software.
Page 56
Final Design of cable: Subjected to Tension with Small Compression Values:
Page 57
Design of pylon: pylons designed as Columns subjected to Axial Force and Biaxial
Moments.
Page 58
147 COMB B1 Combination -5516.24 0 0 0 147-1
147 COMB B1 Combination 13790.6 2.45E-12 0 6.12E-12 147-2
147 COMB B1 Combination 11032.48 1.96E-12 0 2.82E-12 147-2
147 COMB B1 Combination -6895.3 -1.2E-12 0 6.12E-12 147-2
147 COMB B1 Combination 5516.241 0 0 0 147-1
147 COMB B1 Combination -11032.5 0 0 0 147-1
147 COMB B1 Combination 6895.301 1.23E-12 0 3.06E-12 147-2
147 COMB B1 Combination 5516.241 9.8E-13 0 1.41E-12 147-2
147 COMB B1 Combination -13790.6 -2.5E-12 0 3.06E-12 147-2
147 COMB A1 Combination 8825.985 0 0 0 147-1
147 COMB A1 Combination -4412.99 0 0 0 147-1
147 COMB A1 Combination 11032.48 1.96E-12 0 4.9E-12 147-2
147 COMB A1 Combination 8825.985 1.57E-12 0 2.25E-12 147-2
147 COMB A1 Combination -5516.24 -9.8E-13 0 4.9E-12 147-2
147 COMB A1 Combination 4412.993 0 0 0 147-1
147 COMB A1 Combination -8825.99 0 0 0 147-1
147 COMB A1 Combination 5516.241 9.8E-13 0 2.45E-12 147-2
147 COMB A1 Combination 4412.993 7.84E-13 0 1.13E-12 147-2
147 COMB A1 Combination -11032.5 -2E-12 0 2.45E-12 147-2
Page 59
TABLE: Concrete Design 1 - Column Summary Data - Euro code 2-2004
Rainforcement NO. of
Frame DesignSect DesignOpt PMMCombo ErrMsg WarnMsg
area required Dia. 32
rebar’s
Text Text Text Text m2 used Text Text
145 Pyl. top Design DCON3 0.16 199 No Messages No Messages
145 Pyl. top Design DCON3 0.16 199 No Messages No Messages
145 Pyl. top Design DCON3 0.16 199 No Messages No Messages
146 Pylon bott Design DCON3 0.3 373 No Messages No Messages
146 Pylon bott Design DCON3 0.3 373 No Messages No Messages
146 Pylon bott Design DCON3 0.3 373 No Messages No Messages
146 Pylon bott Design DCON3 0.3 373 No Messages No Messages
146 Pylon bott Design DCON3 0.3 373 No Messages No Messages
147 Pylon bott Design DCON3 0.3 373 No Messages No Messages
147 Pylon bott Design DCON3 0.3 373 No Messages No Messages
147 Pylon bott Design DCON3 0.3 373 No Messages No Messages
147 Pylon bott Design DCON3 0.3 373 No Messages No Messages
147 Pylon bott Design DCON3 0.3 373 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
163 Pyl. top Design DCON3 0.16 199 No Messages No Messages
229 Pyl. top Design DCON3 0.16 199 No Messages No Messages
229 Pyl. top Design DCON3 0.16 199 No Messages No Messages
229 Pyl. top Design DCON3 0.16 199 No Messages No Messages
Design of Concrete beams: pylons designed as Columns subjected to Axial Force and
Biaxial Moments.
Page 60
Verified truss sections
1. Stringers; - are longitudinal beams that receives a load directly from composite section of the
top flange and transfer to cross beams, these stringers lied beneath both the highway and rail
way slab of the bridge.
Page 61
2. cross beam;- these are lateral steel beams
3. Top bracing
4. Top chord;- the top truss member of the bridge which acts as the
Page 62
5. Diagonals
6. Bottom chord
Page 63
7. Floor Beams
Page 64
8. Bottom bracing
9.
Page 65
Page 66
pylon Bottom
- Column Design According to EBCS 2 - 1995.
Lc2
Ib1 1
Lb1
Lc1
b
Ib3
2
Lc3
column
cross-section column elevation
Material Properties
Concrete - Grade C-40 Steel - Grade S500
Fck 40,000 kpa [EBCS 2 Table 2.3] Fy k 500,000 kpa
Fctk 1,500 kpa [EBCS 2 Table 2.4] PSF 1.15
PSF 1.5 [EBCS 2 Table 3.1] Fy d 434,783 kpa
Fcd 22666.67 kpa Es 200,000 kpa
Fctd 1,000 kpa As(min) 0.24 [EBCS-2 7.2.4.2]
Ecm 28,000 kpa [EBCS 2 Table 2.5] As (max) 2.4 [EBCS-2 7.2.4.2]
Page 67
Limits of Slenderness:
æ M1 ö
l £ 50 - 25çç ÷÷ EBCS - 2, 4.4.6
è M2 ø
M 1
M 1
= 1.252 = -1.005
M 2
M 2
l£ 18.707 l£ 75.125
I c1 L c1 + I c 2 L c 2
a + 0.4 a1 =
Le = m L ³ 0.7 L I b1 L b1 + I b 2 L b 2
a m + 0.8
a1 + a 2 I c1 L c1 + I c 3 L c 3
a2 =
am = I b3 Lb3 + I b 4 Lb 4
2
Le = 19.990 Le = 19.986
- Slenderness ratio:
Design Actions:
Calculate Eccentricities in the x-x Direction Calculate Eccentricities in the y-y Direction
Page 68
ee = max of 0.6e 02 + 0.4e 01 ee = max of 0.6e 02 + 0.4e 01
0.4e 02 0.4e 02
e e = 0.0190 e e = -0.0433
Le Le
ea = ³ 200mm ea = ³ 200mm
300 300
= 0.066633777 = 0.066618362
e 2 = 0.00 e 2 = 0.00
Nsd = 397070.830 kn
Msd x-x = 34004.685 kn-m
Msd y-y = 9250.368 kn-m
Reinforcement Calculation:
wAc fcd
As,tot =
f yd
2
As,tot = 0.240000 m
Page 69
1. Composite Section Top Flange Design 26.752 Gpa (Modulus Elasticity of concrete) 0
Design
1. Typicalof composite section top Flange
Section 175
1.1. Deck Thickness > 175mm >
- Minimum recommended thickness of the slab, to control deflection is t smin =175 mm [AASHTO Art. 5.14.1.3.1a] mm
Or (Gs +3000)/30 =340mm > 175mm 340 340
- h tf > 1/20
- htf
of >clear
1/20span
of clear
between
span between
fillets fillets =1/20(7.2*1000-500-2*50)= 330mm 330.00 330 330 =1/20(7.2*1000-500-2*50)= 330mm
- h tf > 1/18
- htf
of>effective
1/18 of effective
length oflength
flangeof flange =1/18(7.2*1000-500)= 372.22mm 372.22 370 380 =1/18(7.2*1000-500)= 372.22mm
Use ts= 380 mm 380 340
1.2. Web Thickness No. of bars in a row 3
Minimum thickness of the web, b min =200 mm without prestressing duct. [AASHTO Art. 5.14.1.3.1c] bmin
bars in one
3 barsrow
in require
one rowa require
beam width
a beamof: width of: 10 Φ
bmin= 3Φ+2(1.5Φ)+2*cover =242mm [b min = 300mm, AASHTO Art. 5.10.3.1.1] 240 242
Use b= 500 mm 500
Actual bar spacing= 99mm 99 Dw
1.3. Girder Depth 8620 180.4
Structure depth, Dw = 7m Minimum clear opening for the rail. AREMA Art. 1.2.6a 180400
Who= 9.06
Wcb= 5.89 KN/m
Ws= 8.95 KN-m/m
Who+Wcb= 14.95 182.17
Ws'=Who+Wcb-Ws= 6.00
7.2
57.605 57.605
Me = Ws(Cx+Cw)^2/2+Ws'*Cw(Cw/2+Cx) 46.30333333 58.97 Influence segment coeff.
= 8.95*5.9^2/2+6*0.8*(0.8/2+5.1) =182.17 KN-m/m 18.13666667 18.137 -80.77 -0.125
Moment at supports Symetricall on Right and Left side 32.22 21.305 106.515 -0.25
M b =M c = 8.95*(-0.125)*7.2^2+182.17*(-0.125)= -80.77 KN-m/m 32.22 32.22 106.515
Mws= 37.117 KN-m/m Mws 37.117
A1= 57.605 KN/m B1= 18.137 KN/m RA= 106.515 KN/m
A2= 58.97 KN/m B2= 21.305 KN/m RB= 106.515 KN/m
Influence segment coefficient for moment is obtained from tables.
where:
- Me = End moment at support A (exterior girder)
- Mws= moment due to dead weight of the slab
- Mb and Mc are support moments at supports B and C respectively
- B1, B2, A1 and A2 are shear forces at the left and right of supports B and A respectively.
- RB and RA are reactions at supports B and A respectively.
Page 70
2.1.2 Wearing Surface
0.4*Gs= 2.88 m
(within the
Position of the second wheel = 0.4*Gs+1.8 = 4.68 m < 7.2 m (within the same span) same span)
Using moment distribution method, 4620
Reaction due to the above loading (maximum raection and moment at the interior girder) 4.62
Ra = 55.042 KN Rb= 100.376 KN mp 1.2
Rb1 = 89.958 KN Mmaxp = 158.52 KN-m Mp 41.174
Rb2 = 10.418 KN 26.072
M p = 1.2*158.52 KN-m/4.62m =41.174 KN-m/m
Rb = 1.2*100.376 KN/4.62m =26.072 KN/m
3.2. Maximum Interior Negative live load moment
The critical placement of live load for maximum negative moment is at the first interior support.
The width of equivalent transverse strip is E=1220+0.25*Gs
Page 71
3.3. Maximum Live Load reaction on The Girder
The maximum live load reaction on the exterior girder is obtained when the exterior wheel is placed 300mm from the curb.
The equivalent width of the strip over which the live load applied is:
E=660+0.55Gs = 3020 mm 3020
Using moment distribution method, the reactions at supports A and b becomes 3.02
Ra = 237.44 KN Rb= -102.906 KN mp 1.2
Rb1 = -92.44 KN 94.347
Rb2 = -10.467 KN -40.89
Ra = 1.2*237.44 KN/3.02m =94.347 KN-m/m
Rb = 1.2*-102.906 KN/3.02m =-40.89 KN/m 1
4. Select Resistance Factors 1 1
Strength Limit States (RC) 1 1 0.95
Flexure & Torsion Flexure & Torsion 1 i) Strength Limit State 1.00 1.05
Resistance Factor = 1 Shear & Torsion 1 ii) Service Limit State 0.90 1
Bearing on Concrete 1 0.70
5. Select Load Modifiers Concrete in strut & Tie model 0.70
i) Strength Limit State 1
i) Ductility 0.95 1.25 [Art. 1.3.3] dc 1.25
ii) Continuous 0.95 1.50 [Art. 1.3.4] dw 1.5
iii) Importancy 1.05 1.75 [Art. 1.3.5] LL 1.75
Load Modifier = 0.95 1.00 FR 0.75
1
6. Select Applicable Load Combinations 1
i) Strength Limit State U=0.95(1.25DC+1.50DW+1.75(LL+IM)+1.00(FR+TG)
9. Reinforcement
a) Positive Moment Reinforcement
dp= 347 dp=347 mm (effective depth,dp=380-16/2-25)
Mmaxp= 278.339 KN-m/m 1.000
Page 72
c) Distribution Reinforcement
The amount of distribution reinforcement at the bottom of the slab to distribute the loads may be taken as a percentage of the primary
reinforcement and a minimum spacing of 250mm.
Pe= min[67,3840/√Se] 67
Pe = Percentage of distribution reinforcement
Se = Clear spacing of geiders = Gs-bmin
Se = 7200-500 =6700 6700
Thus Pe= min [67, 3840/sqrt (6700 )] = 0.469 47% 46.91 46.91
1178.46
A s = Pe*A sp = 1178.46mm2 ( Using 12 mm diameter reinforcing bars) 0.469130666
Sdi =min(3.14 (dd)2 1000/A ti ,250] = Min (90,250 ) 95.92 9 90 90
S = 95.92 mm Provide Φ 12 c/c 90 mm at bottom, longitudinal direction.
Reinforcement :
Mpu Assume; j =0.875 and fs=0.6*Fy 2669.82
AS =
fs *j*dp 2669.82
194550000
AS = = 2669.82mm2/m (Provided reinforcement)
(0.6*400)*0.875*347
Page 73
a) Positive moment reinforcement
2
The equivalent concrete area, n*A p = 17584.000 mm
0.5*bX2 =n*Ap*(d 2 -X)+n*An*(dp-X) X= 69.48 mm 69.48 -52.752 191.716096 69.48204805 1000000000
500 1 52.752 -8493.072
Icr=(b*X3 )/3+(n*A p *(d 2 -X)2 )+(n*An*(dp-X)2 ) = 788.979 *E+06 mm4 677126550.4 111814102 38622.66559 7.89E+08
fs =(n*MPu*(d p -X))/Icr = 479.02 Mpa For bottom steel, dc= 4.79E+02
411.96 479.02
240 788.979
For bottom steel, dc=33 mm, A= 2*33*80 =5280mm2 5280 240
1/3
fsa=23000/(d c*A) = 411.96 Mpa fsa =240 Mpa 240 fsa ( =240 Mpa
where: There is a problem of Cracking.
X is the neutral axis depth from top fiber > Increase the amount of reinforcing bars provided (reduce
MPu= unfactored max positive moment 222 (Provide Φ16 c/c 80 mm)
Icr = moment of inertia of the composite transformed section
The above results show that :
Trial Δs= 0 mm (change in spacing of bars)
Try S = 80 mm As =2512 mm2 0 2512 80
Ap =2512mm2, S=80mm dp=347mm, n=Es/Ec =7, d2=68 mm, An =1256mm2, Mpu=194.55 KN-m/m
Upon substitution, the corresponding values become: 69.48 -52.752 191.716096 69.48204805 1000000000
X=69.48 mm, Icr= 788.979E+06 mm4, fs=479.02Mpa, fsa=411.96Mpa 500 1 52.752 -8493.072
fs= 479.02 Mpa > fsa ( =240 Mpa) 677126550.4 111814102 38622.66559 7.89E+08
Increase the amount of reinforcing bars provided 4.79E+02 479.02 788.979
Provide Φ16 c/c 80 mm Increase the amount
> of reinforcing
411.96bars provided 240 240
5280 fsa =240 Mpa 240 fsa ( =240 Mpa
b) Negative moment reinforcement
d1= 33 mm
d2= 68 mm
1.26764E+22 dp= 347 mm
dn= 312 mm
2
The equivalent concrete area, n*A n = 8792.000 mm
0.5*bX2 =(n-1)*Ap*(d 1 -X)+n*An*(dn-X) X= 60.1 mm 60.1 -47.728 167.933921 60.10296074 1000000000
3 2 2
Icr=(b*X )/3+(n*A p *(d 1 -X) )+(n*An*(dn-X) ) = 643.159E+06 mm4 557871024.9 72371295.1 12916687.34 6.43E+08
fs =(n*MPn*(d p -X))/Icr = 281.33 Mpa 2.81E+02 281.33 643.159
Where:- MPn= unfactored negative moment For top steel, dc= 201.93
For top steel, dc=68 mm, A= 2*68*160 =21760mm2 21760 240
1/3
fsa=23000/(d c*A) = 201.93 Mpa fsa = Mpa fsa ( = Mpa
30 (change in spacing of bars)
Trial Δs= 30 mm (change in spacing of bars)
Δs S = 130 mm As =1545.85 mm2 30 1545.85 130.00000 13 13.00
An =1545.85mm2, S=130mm dn=312mm, n=Es/Ec =7, d2=68 mm, Ap =2512mm2, Mpn= -102.61571 KN-m/m
Thus, the corresponding values of X, Icr, fs and fsa are: 65.85 -51.7859 183.493538 65.85381921 1000000000
X=65.85 mm, Icr= 769.795E+06 mm4, fs=229.68Mpa, fsa=216.4Mpa 500 1 51.7859 -7747.0248
fs= 229.68 Mpa > fsa ( =216.4 Mpa) 17680 655619094.4 95196645.8 18979702.51 7.70E+08
There is a problem of Cracking. Therefore increase areas of rebars 229.683427 229.68 769.795
Thus, Provide Φ16 c/c 130 mm There is a problem
> of Cracking.
216.4
Therefore increase areas
240 of rebars 240
8580 fsa =240 Mpa fsa ( =216.4 Mpa
Investigation of Fatigue Limit State -13.28 -13.28
Fatigue need not be investigated for concrete decks in multi-girder applications. [AASHTO Art 9.5.3]
Page 74
Result and Discussion
Recommendation for optimum design for cost and general characteristic combined highway
and railway double deck cable stayed box girder bridge design includes,
Proper measuring and assumption of number of cables used inside a group of
strands, and over all span cable requirement.
Selection of adequate diameter and strength requirement of cables,
Proper Span length and depth proportioning of the box girder
Excellent pylon number selection, proportioning of height, size and other.
Weight parameter of construction materials and quality parameters.
Construction methodologies and others.
Page 75
Reference
1. M.M. Hassan, A.O. Nassef, and A.A. El Damatty, Optimal Design of semi fan cable stayed
bridges, https://www.researchgate.net/publication/263151747
2. Víctor Folqué Ceballos, Feasibility of a hybrid bridge: suspension and cable – stayed model 2016,
June 2016.
3. American Association of State Highway and Transportation Officials (AASHTO) LRFD
Bridge design specification, sixth edition, 2012.
4. American Railway Engineering and Maintenance-of-Way Association (AREMA) Manual
for Railway Engineering (MRE), 2010.
5. Nuruye Adane, Comparison of analysis models of highway and railway bridges loads and load
combinations, Adiss Ababa university school of civil and environmental Engineering, 2013
6. K. Humpf & M. Müller John f . Design, analysis and construction of Puente Mercosur—
third bridge across the Orinoco River, Germany.
7. Ladislav Fryba, Dynamics of railway bridges, second revised edition, co-published with
Thomas Telford ltd., London, 1996, printed in the Czech Republic.
8. Temesgen Dolla, Analysis and Design of Pre-Stressed Concrete (PSC) Girder Railway Bridge, A
project submitted to Addis Ababa institute of technology, 2016.
9. Mohamed and Ahmed, Suez Canal cable stayed bridge Project, Kafr EI sheik university, faculty
ofcivil engineering.
10. Roger L. Brockenbrough, Frederick S.Merritt, Structural steel designer‘s Handbook,
Fourth Edition, the McGraw-Hill companies,Inc.,2006.
11. Edwin H.Gaylord, JR, Charles N. Gaylord, James E. Stallmeyer ,Structural engineering
Handbook, fourth Edition, © 1997 by McGraw-Hill companies,Inc.
Page 76
Page 77