Las Cortes Apartments - Time Impact Analysis - Final Draft
Las Cortes Apartments - Time Impact Analysis - Final Draft
Table of Contents
Introduction:...............................................................................................................................................4
Analysis Technique Used: Time Impact Analysis:.........................................................................................4
Sequence of Work:......................................................................................................................................5
List of Delay Events/Frag-nets:....................................................................................................................5
Baseline Critical Path:..............................................................................................................................5
Analysis Results:..........................................................................................................................................6
Update #01 – DD 08/03/2016:................................................................................................................6
Update #02 – DD 12/12/2016:................................................................................................................7
Update #02 – DD 12/12/2016:................................................................................................................8
Update #02 – DD 12/12/2016:................................................................................................................9
Update #03 – DD 02/10/2017:..............................................................................................................11
Update #04 – DD 03/16/2017:..............................................................................................................12
Weather Delays:....................................................................................................................................13
Conclusion:................................................................................................................................................14
2|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
List of Figures:
Figure 1: Illustrative Figure Showing the Predecessors & Successors for Delay 1........................................6
Figure 2: Illustrative Figure Showing the Predecessors & Successors for Delay 2........................................7
Figure 3: Illustrative Figure Showing the Predecessors & Successors for Delay 3........................................8
Figure 4: Illustrative Figure Showing the Predecessors & Successors for Delay 3.1.....................................9
Figure 5: Illustrative Figure Showing the Impact of Delays 3 & 3.1 on the Project Finish Date.................10
Figure 6: Illustrative Figure Showing the Predecessors & Successors for Delay 4......................................11
Figure 7: Illustrative Figure Showing the Predecessors & Successors for Delay 5......................................12
List of Tables:
Table 1: List of Delay Events........................................................................................................................5
Table 2: List of Weather delays.................................................................................................................13
Table 3: Delay Summary............................................................................................................................14
List of Appendices:
Appendix 01 - Las Cortes Baseline
Appendix 02 - Las Cortes Baseline - Critical Path
Appendix 03 - Update #01 DD08-03-2016 before delay 1
Appendix 04 - Update #01 DD08-03-2016 after delay 1
Appendix 05 - Update #02 DD12-12-2016 before delays 2, 3 & 3.1
Appendix 06 - Update #02 DD12-12-2016 after delay 2
Appendix 07 - Update #02 DD12-12-2016 after delay 3
Appendix 08 - Update #02 DD12-12-2016 after delay 3.1
Appendix 09 - Update #03 DD02-10-2017 before delay 4
Appendix 10 - Update #03 DD02-10-2017 after delay 4
Appendix 11 - Update #04 DD03-16-2017 before delay 5
Appendix 12 - Update #04 DD03-16-2017 after delay 5
3|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Introduction:
The construction of the “Las Cortes Townhomes” was awarded to Sun Country Builders
and construction began on July 08, 2016. The main scope of the project is the full construction
of 11 buildings, in addition to all the rough in works, finishes, landscape and hardscape.
The project is planned to end on February 06, 2018, however the actual finish date of
the project has been impacted due to certain delay events. There are a total of three major
delay incidents, with the most notable one being the delay in the start of the dry utilities due to
the Design of the Dry Utilities & Conversion not being completed as originally scheduled in the
GC Contract baseline schedule. As a result, Sun Country Builders performed this delay analysis
in order to support their claim for extension of time. Through this report, the results of “Time
Impact Analysis” will be presented and described in detail in order to assess how those three
major delays will impact the completion date of the project.
In the current project “Las Cortes Townhomes”, the actuals are applied on the baseline
for different data dates to quantify the impact of each delay event on the project’s finish date.
Also, there is a clear description of the delays and their effects in terms of the dates of
occurrence and the activities that are directly impacted.
4|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Sequence of Work:
Please refer to “Appendix 02 – Las Cortes Baseline – Critical Path” for more details.
5|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Analysis Results:
Update #01 – DD 08/03/2016:
Before adding Delay 1 – Abatement/Demolition Production Durations Impacted due to
Existing Utility Lines & Poles Removal:
According to the actuals implemented into the schedule, the project’s finish date shifted
from February 6, 2018 back to February 13, 2018, with a total of 7 non-excusable days of delay.
After adding Delay 1 - Abatement/Demolition Production Durations Impacted due to Existing
Utility Lines & Poles Removal:
This delay has a direct impact on the structural demolition under phase II, in addition to
the site rough grading under phase I.
This delay has a start date of August 03, 2016 and a finish date of November 09, 2016, as
per the figure below.
Figure 1: Illustrative Figure Showing the Predecessors & Successors for Delay 1
This delay impacted the longest path of the project, pushing out the project’s finish date
from February 13, 2018 to February 22, 2018, giving Sun Country Builders the right to claim for
9 calendar days.
6|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
7|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Figure 2: Illustrative Figure Showing the Predecessors & Successors for Delay 2
Even though this delay impacted the start of Phase I Structures, it still has no Impact on
the project’s finish date. As can be seen on the figure above, building 2 still has 27 days of total
float even after adding the delay, as it is not on the longest path.
8|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Figure 3: Illustrative Figure Showing the Predecessors & Successors for Delay 3
9|Page
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
This delay impacted the start of the framing for buildings 1, 2 & 5, with building 2 now
driving the project’s new longest path, which resulted in shifting the project’s finish date from
March 05, 2018 to July 31, 2018, giving Sun Country Builders the right to claim for 148 calendar
days.
Figure 4: Illustrative Figure Showing the Predecessors & Successors for Delay 3.1
10 | P a g e
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Figure 5: Illustrative Figure Showing the Impact of Delays 3 & 3.1 on the Project Finish Date
This delay impacted the start of the framing for buildings 1, 2 & 5, shifting the project’s
finish date from July 31, 2018 to September 11, 2018, giving Sun Country Builders the right to
claim for an additional 42 calendar days.
11 | P a g e
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Figure 6: Illustrative Figure Showing the Predecessors & Successors for Delay 4
Even though this delay impacted the start of the structural works of building 6 & 7, it still
has no Impact on the project’s finish date. As can be seen on the figure above, building 6 still
has 118 days of total float even after adding the delay, as it is not on the longest path.
12 | P a g e
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Figure 7: Illustrative Figure Showing the Predecessors & Successors for Delay 5
Even though this incident delayed the foundation works of building 2, it still has no Impact
on the project’s finish date. As can be seen on the figure above, building 2 foundation works
still has 111 days of total float even after adding the delay, as it is not on the longest path.
13 | P a g e
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Weather Delays:
This topic discusses the weather delays impacting the project and their concurrency with
the previously mentioned delays.
There are a total of 22.5 days of rain delays impacting the project as per the table below.
Table 2: List of Weather delays
The days highlighted in yellow are concurrent with the previously mentioned delays, a
total of 18 and half days, thus the remaining 4 days should only be deducted from the total
amount of weather delays provided by the contract, which sums up to 17 days.
14 | P a g e
Las Cortes Townhomes – HUD Project No.: 122-35726 Delay Analysis: Time Impact Analysis / Report date: 06/09/2017
Conclusion:
The total accounted delays that has an impact on the at completion date are 222
calendar days according to the analysis, pushing the project’s finish date back to
September 16, 2018.
18.5 days out of the 22.5 days of rain delays are concurrent with the previously
mentioned delays, thus the remaining 4 days should only be deducted from the total
amount of weather delays provided by the contract, which sums up to 17 day, the
contractor’s balance should be 13 days under contract.
Upon the addition of some of the delays, the “at completion date” keeps getting pushed
out. The longest path changes with every added delay as well. However, the distortion
caused by concurrent delays is a very critical issue for Sun Country Builders, since this
may have caused loss of resources and efficiency.
Below are the summarized results for the full analysis process:
Table 3: Delay Summary
15 | P a g e