S CURVE DRIVEN PILING

OWNER : PT. SIGMA KARYA BUANA


KONTRAKTOR : CV. INDOTEKNOTAMA LESTARI
LOCATION : Desa Semudun , kecamatan sungai Kunyit,
Kabupaten Mempawah , Kalimantan Barat

No. D E S C R I P T I O N Qty Unit

A. Mobilisasi dan Demobilisasi


1 Mob Demob Crane pancang, hammer, service dan personil 1 ls ###

B. Pekerjaan Pemancangan NPK Plant Mempawah


1 Pancang Main Building Spun pile ø400 mm L=36 Mtr 183 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 6,588 m' ###
Handling spun pile ø400 mm 6,588 m' ###
Joint spun pile ø400 mm 366 joint ###
2 Pancang Main Building Spun pile ø400 mm L=36 Mtr Lantai 43 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 1,032 m' ###
Handling spun pile ø400 mm 1,032 m' ###
Joint spun pile ø400 mm 43 joint ###
3 Pancang Platform Machinery Spun pile ø400 mm L=36 Mtr 179 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 6,444 m' ###
Handling spun pile ø400 mm 6,444 m' ###
Joint spun pile ø400 mm 358 joint ###
c Pancang Warehouse Raw Material 4 unit Spun pile ø400 mm L=36 Mtr Lantai 552 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 19,872 m' ###
Handling spun pile ø400 mm 19,872 m' ###
Joint spun pile ø400 mm 1,104 joint ###
Pancang Warehouse Raw Material 4 unit Spun pile ø400 mm L=24 Mtr Building168 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 4,032 m' ###
Handling spun pile ø400 mm 4,032 m' ###
Joint spun pile ø400 mm 168 joint ###
Pancang Product Warehouse Spun pile ø400 mm L=36 Mtr Lantai 115 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 4,140 m' ###
Handling spun pile ø400 mm 4,140 m' ###
Joint spun pile ø400 mm 230 joint ###
Pancang Product Warehouse Spun pile ø400 mm L=24 Mtr Building 44 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 1,056 m' ###
Handling spun pile ø400 mm 1,056 m' ###
Joint spun pile ø400 mm 44 joint ###
Pancang Storage Tank cap 1x500 Spun pile ø400 mm L=36 Mtr 11 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 396 m' ###
Handling spun pile ø400 mm 396 m' ###
Joint spun pile ø400 mm 22 joint ###
Pancang Workshop, Canteen,Heavy Equipment Spun pile ø400 mm L=24 Mtr 26 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 624 m' ###
Handling spun pile ø400 mm 624 m' ###
Joint spun pile ø400 mm 26 joint ###
Pancang Storage Tank cap 1x100 Spun pile ø400 mm L=36 Mtr 3 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 108 m' ###
Handling spun pile ø400 mm 108 m' ###
Joint spun pile ø400 mm 6 joint ###
Pancang Pondasi Weight Bridge Spun pile ø400 mm L=36 Mtr 28 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 1,008 m' ###
Handling spun pile ø400 mm 1,008 m' ###
Joint spun pile ø400 mm 56 joint ###
Pancang Office and laboratory sq pile 20x20 L = 12 Mtr 20 Nos
Pemancangan sq pile 20x20 L=12 Mtr 240 m' ###
Handling sq pile 20x20 240 m' ###
Pancang Musolah sq pile 20x20 L=12 Mtr 15 Nos
Pemancangan sq pile 20x20 L=12 Mtr 180 m' ###
Handling sq pile 20x20 180 m' ###
Pancang Guard House sq pile 20x20 L=12 Mtr 6 Nos
Pemancangan sq pile 20x20 L=12 Mtr 72 m' ###
Handling sq pile 20x20 72 m' ###
Pancang Gardu Listrik sq pile 20x20 L=12 Mtr 6 Nos
Pemancangan sq pile 20x20 L=12 Mtr 72 m' ###
Handling sq pile 20x20 72 m' ###

SUBTOTAL ###

PLANING
KUMULATIF PLANING
ACTUAL
KUMULATIFACTUAL
Page 1 of 5
S CURVE DRIVEN PILING

OWNER : PT. SIGMA KARYA BUANA


KONTRAKTOR : CV. INDOTEKNOTAMA LESTARI
LOCATION : Desa Semudun , kecamatan sungai Kunyit,
Kabupaten Mempawah , Kalimantan Barat

No. D E S C R I P T I O N Qty Unit

A. Mobilisasi dan Demobilisasi


1 Mob Demob Crane pancang, hammer, service dan personil 1 ls

B. Pekerjaan Pemancangan NPK Plant Mempawah


Pancang Main Building Spun pile ø400 mm L=36 Mtr 183 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 6,588 m'
Handling spun pile ø400 mm 6,588 m'
Joint spun pile ø400 mm 366 joint
Pancang Main Building Spun pile ø400 mm L=24 Mtr Lantai 43 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 1,032 m'
Handling spun pile ø400 mm 1,032 m'
Joint spun pile ø400 mm 43 joint
Pancang Platform Machinery Spun pile ø400 mm L=36 Mtr 179 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 6,444 m'
Handling spun pile ø400 mm 6,444 m'
Joint spun pile ø400 mm 358 joint
Pancang Warehouse Raw Material 2 unit Spun pile ø400 mm L=36 Mtr 514 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 18,504 m'
Handling spun pile ø400 mm 18,504 m'
Joint spun pile ø400 mm 1,028 joint
Pancang Warehouse Raw Material 2 unit Spun pile ø400 mm L=24 Mtr 32 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 768 m'
Handling spun pile ø400 mm 768 m'
Joint spun pile ø400 mm 32 joint
Pancang Product Warehouse Spun pile ø400 mm L=36 Mtr 116 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 4,176 m'
Handling spun pile ø400 mm 4,176 m'
Joint spun pile ø400 mm 232 joint
Pancang Product Warehouse Spun pile ø400 mm L=24 Mtr 48 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 1,152 m'
Handling spun pile ø400 mm 1,152 m'
Joint spun pile ø400 mm 48 joint
Pancang Storage Tank cap 1x500 Spun pile ø400 mm L=36 Mtr 11 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 396 m'
Handling spun pile ø400 mm 396 m'
Joint spun pile ø400 mm 22 joint
Pancang Workshop Heavy Equipment Spun pile ø400 mm L=24 Mtr 26 Nos
Pemancangan spun pile ø400 mm L=24 Mtr 624 m'
Handling spun pile ø400 mm 624 m'
Joint spun pile ø400 mm 26 joint
Pancang Storage Tank cap 2x100 Spun pile ø400 mm L=36 Mtr 3 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 108 m'
Handling spun pile ø400 mm 108 m'
Joint spun pile ø400 mm 6 joint
Pancang Pondasi Weight Bridge Spun pile ø400 mm L=36 Mtr 28 Nos
Pemancangan spun pile ø400 mm L=36 Mtr 1,008 m'
Handling spun pile ø400 mm 1,008 m'
Joint spun pile ø400 mm 56 joint
Pancang Office and laboratory sq pile 20x20 L = 12 Mtr 20 Nos
Pemancangan sq pile 20x20 L=12 Mtr 240 m'
Handling sq pile 20x20 240 m'
Pancang Musolah sq pile 20x20 L=12 Mtr 15 Nos
Pemancangan sq pile 20x20 L=12 Mtr 180 m'
Handling sq pile 20x20 180 m'
SUBTOTAL

PLANING
KUMULATIF PLANING
ACTUAL
KUMULATIFACTUAL

Page 2 of 5
KEBUTUHAN TIANG PANCANG

OWNER : PT. SIGMA KARYA BUANA


KONTRAKTOR : CV. INDOTEKNOTAMA LESTARI
LOCATION : Desa Semudun , kecamatan sungai Kunyit,
Kabupaten Mempawah , Kalimantan Barat

No. D E S C R I P T I O N

B. Pekerjaan Pemancangan NPK Plant Mempawah


Pancang Main Building Spun pile ø400 mm L=36 Mtr
Pancang Main Building Spun pile ø400 mm L=24 Mtr Lantai
Pancang Platform Machinery Spun pile ø400 mm L=36 Mtr
Pancang Warehouse Raw Material 4 unit Spun pile ø400 mm L=36 Mtr
Pancang Warehouse Raw Material 4 unit Spun pile ø400 mm L=24 Mtr
Pancang Product Warehouse Spun pile ø400 mm L=36 Mtr
Pancang Product Warehouse Spun pile ø400 mm L=24 Mtr
Pancang Storage Tank cap 1x500 Spun pile ø400 mm L=36 Mtr
Pancang Workshop Heavy Equipment Spun pile ø400 mm L=24 Mtr
Pancang Storage Tank cap 3x100 Spun pile ø400 mm L=36 Mtr
Pancang Pondasi Weight Bridge Spun pile ø400 mm L=36 Mtr
Pancang Office and laboratory sq pile 20x20 L = 12 Mtr
Pancang Musolah sq pile 20x20 L=12 Mtr
Pancang Guard House sq pile 20x20 L=12 Mtr
Pancang Gardu Listrik sq pile 20x20 L=12 Mtr

TOTAL BOTTOM /PENSIL SPP DIAM 400 MM, P=12M


TOTAL MIDLE SPP DIAM 400 MM, P=12 M
TOTAL BOTTOM SQUARE PILE 20 X 20 CM P=6 M
TOTAL MIDLE/UPPER SQUARE PILE 20 X 20 CM P=6 M
NCANG

Qty Unit BOTTOM MIDLE

183 Nos 183 366

43 Nos 43 43

179 Nos 179 358

552 Nos 552 1,104

168 Nos 168 168

115 Nos 115 230

44 Nos 44 44

11 Nos 11 22

26 Nos 26 26

3 Nos 3 6

28 Nos 28 56

20 Nos 20 20 pun middle 2610

15 Nos 15 15 square bottom 5

6 Nos 6 6
6 Nos 6 6
STOCK
1,352 1258 94
2423 2610 -187
47 51
47 51
pun middle 2610

square bottom 5

You might also like