Project REPORT 2

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

[CREDIBLE TECHNICAL WORKS LIMITED]

MPIRANI SECONDARY SCHOOL

WORK PROGRESS REPORT.


DATED:10/06/2024

Project Name:

The Proposed Construction of 6 Classes and 2No Ablution Blocks at Mpirani Secondary
School- Kwale County.
Project Consultants:
Linear Cost Consultants
Project Sponsor:

M-Pesa Foundation.

Client:

Mpirani Secondary School


Contractor:

Credible Technical works Limited


Commencement Date: 30th May 2024.

Reporting Week: 2

Prepared by: James Kariuki


[CREDIBLE TECHNICAL WORKS LIMITED]

Work Progress Schedule Week 1


A. Proposed Construction of 6 No. classrooms
Activity Completion Date Comments/
% Completed

Hardcore laying Done 100%

Hardcore compaction Done 100%

Formwork (150mm Done 100%


High)

Hardcore Done 100%


300mm,Murram
spreading(50mm
thick),Antitermite ,Dpm,
200mm foundation walling Done 100%

Mass concrete 50mm under strip base Done 100%

150mm thick floor bed Done 100%

Steel Reinforcement & BRC Done 100%

Walling 200mm thick stone walling Done 100%


[CREDIBLE TECHNICAL WORKS LIMITED]
Formwork to Ring Beam ongoing 5%

Steel Reinforcement to Ring Beam Not Done Not done


[CREDIBLE TECHNICAL WORKS LIMITED]

B. Proposed 2No Ablution Blocks

Activity Comments/
% Completed
Excavation & Earthworks Done 100%

Setting out strip Foundations Started Started


General weekly Weather Report
Weather type:
1) Sunny
2) Temperatures range between 26ºC-28ºC during the week.

Work projections. (Week 2)


1. Proposed 6 No. Classroom construction
 Formwork for ring beam will be complete
 Steel for Ring beam will be ongoing
 Concreting will be ongoing

2. Proposed 2No. Ablution Blocks


 Concrete to strip Foundations will be complete
 Strip Foundation walling started

Site Safety.
Safety;
All safety measures are in place
Accidents; No accident reported
[CREDIBLE TECHNICAL WORKS LIMITED]

MATERIALS ON SITE
1. Ballast 7tonnes

2. Sand 25tonnes

3. Cement 200bags

4. Timber 2000ft

5. Black polythene dpm 2pcs

6. Blocks 1000pcs
[CREDIBLE TECHNICAL WORKS LIMITED]

REFERENCE IMAGES ON PROGRESS REPORT

Proposed Construction of 6No Classrooms


[CREDIBLE TECHNICAL WORKS LIMITED]
[CREDIBLE TECHNICAL WORKS LIMITED]

REFERENCE IMAGES ON PROGRESS REPORT

Proposed Construction of 2No Ablution works


Excavation works
[CREDIBLE TECHNICAL WORKS LIMITED]
[CREDIBLE TECHNICAL WORKS LIMITED]
[CREDIBLE TECHNICAL WORKS LIMITED]

LIST OF WORKERS ON SITE

DATE NAMES WORK/OCCUPATION


3/06/24 - 8/06/24 Khassim Abdalla Mason
Ali kombo Mason
Nyota Mason
Dullah Mason
Ngowa Ngowa Mason
Mwilu Kangae Mason
Ali Nyiro Mason
Moti Mason
Mrisia Mason
Chiguba Mason

3/06/24 - 8/06/24 Juma yusuf Casuals


Bazul Aziz Casuals
Rasta Casuals
Mamake Chiru Casuals
Bi safari Casuals
Rama Casuals
Hamisi Casuals
Masha Casuals
Ndoro Casuals
Madzuwa Casuals
Mweru Casuals
Kachiro Casuals
Mbeyu Casuals
Chirunga Casuals
Kazungu Casuals
Jasim mbeyu Casuals
Guji Charo Casuals
Mrisa Casuals

3/06/24 - 8/06/24 EXCAVATION


GUYS
Kayanda
Aziz Mbeyu
Jumaa Muzungu
Ambrose Vusa