RPT 7006 H0 SS3 50 00 001 0
RPT 7006 H0 SS3 50 00 001 0
PLANT: HABSHAN-0
HOLD LIST
REVISION HISTORY
Rev
Section or Page
. Date Description of Change
Revised
No.
Section 4,
Subsections Document updated based on Electrical site visit
B 26-11-2020
1.2,3.2, 5.1,5.2 & findings & COMPANY comments
6.2
TABLE OF CONTENTS
1 PROJECT DESCRIPTION.......................................................................................................
1.1 Introduction....................................................................................................................
1.2 Project Objective and Scope.........................................................................................
1.3 Purpose of this document..............................................................................................
2 DEFINITIONS & ABBREVIATIONS.....................................................................................
2.1 Definitions......................................................................................................................
2.2 Abbreviations.................................................................................................................
3 SITE VISIT AND LIST OF PARTICIPANTS........................................................................
3.1 Telecom Team Site Visit...............................................................................................
3.2 Electrical Team Site Visit...............................................................................................
4 SITE VISIT AGENDA...............................................................................................................
5 SITE VISIT FINDINGS AND OBSERVATIONS................................................................
5.1 Telecom.......................................................................................................................
5.2 Electrical......................................................................................................................
6 CONCLUSIONS AND FURTHER ACTIONS......................................................................
6.1 Telecom.......................................................................................................................
6.2 Telecom - Conclusion updated based on site visit findings dated 11th to 16th
January, 1st to 7th February 2021............................................................................................
6.3 Electrical......................................................................................................................
ATTACHMENT 1 – EQUIPMENT LAYOUT- SS-3 WITH SITE VISIT FINDINGS................
ATTACHMENT 2 – ELECTRICAL SITE VISIT FINDINGS- EQUIPMENT LAYOUT-
SS-3 ....................................................................................................................................................
1 PROJECT DESCRIPTION
1.1 Introduction
The Habshan & Bab Gas Complex is a set of gas processing facilities operated by ADNOC
Gas Processing (AGP) and located approximately 140km southwest of the city of Abu Dhabi.
The first plant in the complex was commissioned almost four decades ago. Since then, several
other plants were added to the complex making it one of the largest gas processing facilities in
the world.
In order to ensure the continued viability of Habshan and Bab Gas Complex, ADNOC Gas
Processing regularly reviews the installed equipment and systems, and carries out necessary
refurbishments, upgrades, replacements and additions to ensure that the facilities can be
operated in a safe, sustainable and efficient manner. This project is a continuation of these
efforts.
ADNOC Gas Processing (hereinafter referred to as COMPANY) has assigned M/s Bilfinger
Tebodin Middle East Ltd. (hereafter referred to as CONSULTANT) to carry out Front End
Engineering & Design (FEED) and Detail Engineering for the Project to enable COMPANY to
engage a Procurement & Construction (PC) Contractor to execute the Project.
CONSULTANT shall perform Engineering for the PROJECT as per Scope of Services under
the framework Agreement No. TE.18.048 (J) / 2018-21 /SRC/021. CONSULTANT shall carry
out Engineering for the project to enable COMPANY to engage a Procurement & Construction
(PC) Contractor to execute the PROJECT without further detailed engineering.
The objective of the project is to ensure safety and security of personnel and buildings by
providing adequate public address system annunciation, safety monitoring and incident review
capability, and controlled access to critical buildings by implementing/enhancing the Public
Address, CCTV and Access Control Systems in accordance with international codes,
standards, HSE and Electronic Security requirements.
The scope includes the following main items, in addition to all associated multi-disciplinary
works:
New CCTV and Access Control Systems in Habshan & Bab Process Buildings
New Public Address System in Bab Plant Area & Residential Complex
Integration of the above system including Security LAN and Video Analytics
The purpose of this document is to outline the observations, findings and conclusions as an
outcome of the site visit jointly conducted by COMPANY and CONSULTANT representatives to
Substation No.2 of Habshan plant.
2.1 Definitions
PROJECT Habshan and Bab Telecom Systems Upgrade Project No. 7006
2.2 Abbreviations
IT Information Technology
SS Substation
The site visit to SS-3 of Habshan Plant was conducted on 25 th August 2020. COMPANY and
CONSULTANT personnel who attended the site visit are listed in the table below.
COMPANY
CONSULTANT
The site visit to SS-3 Habshan Plant was conducted between 11 th to 16th January 2021.
COMPANY and CONSULTANT personnel who attended the site visit are listed in the table
below.
COMPANY
CONSULTANT
The site visit to SS-3 of Habshan Plant was conducted between 1st to 7th February 2021.
COMPANY and CONSULTANT personnel who attended the site visit are listed in the table
below.
COMPANY
CONSULTANT
The site visit to SS-3 of Habshan Plant was conducted on 10 th November 2020. COMPANY
and CONSULTANT personnel who attended the site visit are listed in the table below.
COMPANY
CONSULTANT
The site visit to SS-3 of Habshan Plant was conducted on 23 rd March 2021. COMPANY and
CONSULTANT personnel who attended the site visit are listed in the table below.
COMPANY
CONSULTANT
Visual inspection and verification of existing Telecom facilities (CCTV cameras, ACS
devices & Fibre Optic Cabinets) related to the PROJECT scope.
Inspection and verification of the Fibre Optic Tie-ins at SS-3 for extending Security LAN
network from NMCR.
Visit SS-3 and identify locations and space for the following
5. Network Cabinet
Verify the existing power supply to the Telecom Cabinet (Breaker rating, cable size)
To identify from which DB the existing Telecom Cabinet power supply is fed and identify
spare feeders in the same DB if possible. Also identify space to install new breakers in the
DB if required.
Identify spare feeders in the existing UPS/Non-UPS DB’s to feed the new Plant CCTV
Note down the name plate details of Electrical panels like UPS, DB’s, etc. where tie-in to
be done.
Check for spare slot for cable entry in the DB’s/ UPS Panel
4.1[5.1] Telecom
It was observed that in order to ensure that front and rear side of each cabinet /panel in
SS-3 is within camera viewing angle, the total quantity of cameras required to meet the
required coverage is as detailed below.
In addition, in order to ensure that each critical building entry/exit is monitored, the total
quantity of outdoor cameras required to meet the required coverage is as detailed below.
It was noted that personnel entry doors (3 Nos.) are unmanaged (i.e. no access control
available) and there is enough space available for installation of controlled door assembly
(including indoor card reader, exit push button, emergency break glass unit, door contacts,
electromagnetic locks).
It was observed that as other equipment doors-double leaf (1 No.) are unmanaged (i.e. no
access control available), uncontrolled door assembly (i.e. door contact) shall be provided
as per project scope.
The battery room for SS-3 is inside the switchgear room and no separate door contacts
shall be provided for the same.
It was observed that there is enough space for installation of new wall mounted junction
box of size 500 x 500 x 250mm (W x H x D) for new ACS controller required at SS-3.
Existing Fire & safety panel is available in air lock room of SS-3. Required ACS interface
with Fire Alarm system shall be considered as part of project scope.
It was observed that there is no Fibre Optic Cabinet in SS-3 at present but the site
informed that new Fibre Optic Cabinet shall be installed as part of ongoing project and
details shall be shared with the Consultant.
It was noted that there is enough space for installation of new wall mounted network
cabinet of size 700 x 600 x 600mm (W x H x D) which shall house the new patch panels
and access switch required as part of this project.
New GI conduits and existing trays where available, shall be used to route the ACS &
CCTV system cables inside SS-3.
4.1.5 Site Visit finding dated 11th to 16th January, 1st to 7th February 2021
Section 5.1.1, 5.1.2, 5.1.3 (Updation) shall be refered below as part of Rev 0:-
The location of the cameras as per the CCTV Coverage study and location of Access
Control devices was verified at site and updated in Attachment -1.
Existing Telectron Panel 01-FAP-301 which was identified for Access Control System and
F&G interface as hardwired.
Spare space for installation of new FOPP cabinet for installation of Access switches, patch
panels is verified.
New Single Mode FOC cable to SS-24 (19-24) cores shall be reserved; COMPANY shall
lay this cable.
4.2[5.2] Electrical
4.2.1 Proposed to install a new 240V UPS DB at SS-28 fed from nearest IES-16 F&G UPS
System 80-EE-2853A/B to cater all power requirement for the Project.Site Visit Finding
dated 11th to 31st March 2021.
The site visit was conducted in order to get familiarized with the existing electrical facilities and
to verify the required spare / space feeder availability for the new equipment/systems to be
installed for the PROJECT. Refer Attachment-2 for further details and site visit findings.
Switchgear Room:
Spare & Space feeders identified in the Existing Switchgear (presently feeding the existing DC
Charger).
Space available to install APC Type UPS units (A&B) and battery cabinets in the existing
switchgear room.
Space available to install 3nos. of new wall mounted DB’s in the switchgear Room.
Battery Room:
No space available.
Tag: 80-MCC-301
Incomer Rating
Incomer A : 2800A
Incomer B : 2800A
Ammeter Reading
No spare available.
For space feeders, spare terminal block shall be added in cable compartment.
No spare available
For space feeders, spare terminal block shall be added in cable compartment.
Tag: 80-EE-303
Make: Areva
Incomer Rating
Ammeter Reading
Bus A : 100A
Bus B : 100A
For space feeders, spare terminal block shall be added in cable compartment.
For space feeders, spare terminal block shall be added in cable compartment.
Tag: 3P-1
Incomer – 160A
Tag: 80-EE-RP-0301
Make: Yokogawa
Tag: 80-UA-3
[6] PROPOSED TO FED FROM NEAREST IES-2 F&G UPS SYSTEM 80-EE-0334A/B TO
CATER ALL POWER REQUIREMENT FOR THE PROJECT.
4.3[7.1] Telecom
Equipment layout of SS-3 is updated based on site visit findings & attached as
Attachment-1.
CCTV coverage study shall be carried out based on the location of the cameras finalized
during site survey.
Consultant shall raise request for the details of the existing Fire & safety Panel.
Consultant shall raise request for the details of the new Fibre Optic Cabinet/panel to be
installed by COMPANY under ongoing project.
CONSULTANT Doc. No. Document No. Doc. Class Page
11985-00-7119109 RPT-7006-H0-SS3-50-00-001 3 16 of 19
ADNOC GAS PROCESSING
HABSHAN & BAB TELECOM SYSTEMS UPGRADE
PROJECT No. 7006
SITE VISIT REPORT Rev.
SUBSTATION NO. 3 – HABSHAN 0
Outdoor Plant area cameras (4 Nos.) fibre allocation details shall be updated during
subsequent site visits.
4.4[7.2] Telecom - Conclusion updated based on site visit findings dated 11th to 16th
January, 1st to 7th February 2021
Equipment layout of SS-3 is updated based on site visit findings & attached as Attachment-1.
4.5 Electrical
Electrical
All new power supply requirement will be derived from the proposed new DB.Spare/space feeders
and equipment space identified in section 5.2 can be utilized to feed the new power requirement
for the project. All new power supply requirement will be derived from the proposed new DB.
All new power supply requirement will be derived from the proposed new DB.