DETAIL ESTIMATE

ESTIMATE FOR THE PROPOSED CONSTRUCTION OF GROUND FLOOR RESIDENTIAL


BUILDING IN NEW S.F NO: 292/3 PATTA NO: 1638, ANNIMANGALAM PANCHAYAT,
THIRUMANUR SUB OFFICE, ARIYALUR TALUK & DISTRICT.

OWNER :Mr:S. RAVISHANKAR TOTAL AMOUNT Rs, 809110.9

S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.


TH
1 Earthwork excavation for
Foundation in all types of soils
except in hard rocks only.
column
9"/9" 14 1.06 m 1.06 m 1.22 m 19.19 m³
TOTAL 19.19 m³
2 Sand filling with clear fine river
sand for foundation Pit and
basement
i)Foundation- column
9"/9" 14 1.06 m 1.06 m 0.5 m 7.865 m³
ii) Basement
1)Entrance 1 2.71 m 2.59 m 0.5 m 3.509 m³
2)Foyer 1 2.93 m 2.56 m 0.5 m 3.75 m³
3)Hall 1 6.55 m 2.59 m 0.5 m 8.482 m³
4)Kitchen 1 2.94 m 2.13 m 0.5 m 3.131 m³
5)Bedroom 1 1 2.93 m 3.05 m 0.5 m 4.468 m³
6)Bedroom 2 1 2.93 m 3.05 m 0.5 m 4.468 m³
7)Toilet 1 1.29 m 1.9 m 0.5 m 1.226 m³
TOTAL 36.9 m³
3 P.C.C 1:5:10 for foundation.
i)Foundation
9"/9" 14 1.06 m 1.06 m 0.5 m 7.865 m³

4 Flooring concrete in 1:4:8 using


40mm jelly and fine river sand
including all materials and labour
charges.
1)Entrance 1 2.71 m 2.59 m 0.15 m 1.078 m³
2)Foyer 1 2.93 m 2.56 m 0.15 m 1.152 m³
3)Hall 1 6.55 m 2.59 m 0.15 m 2.606 m³
4)Kitchen 1 2.94 m 2.13 m 0.15 m 0.962 m³
5)Bedroom 1 1 2.93 m 3.05 m 0.15 m 1.373 m³
6)Bedroom 2 1 2.93 m 3.05 m 0.15 m 1.373 m³
7)Toilet 1 1.29 m 1.9 m 0.15 m 0.376 m³
TOTAL 16.78 m³
S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.
TH
5 Brickwork in CM 1:6 mix using
clear fine river sand and well
burnt Chamber bricks, including
all material and labour charges.

Basement
1)All round mainwall & Cross walls
1 43.9 m 0.23 m 0.61 m 6.159 m³
Superstructure GF
1)All round mainwall 1 30.5 m 0.23 m 3.06 m 21.48 m³
2)Cross walls 1 13.4 m 0.23 m 3.06 m 9.431 m³
3)4 1/2" wall 1 4.72 m 0.11 m 3.06 m 1.589 m³
TOTAL 38.66 m³
Parapet wall
1)All round mainwall 1 35.4 m 0.23 m 0.91 m 7.409 m³
TOTAL 7.409 m³
46.07 m³
Deduct for opennings
MD - Main Door -1 1.22 m 0.23 m 2.13 m -0.6 m³
D1-Door -2 0.99 m 0.23 m 2.13 m -0.97 m³
AO- Arch Open -1 0.99 m 0.23 m 2.13 m -0.49 m³
W1- Window -3 1.21 m 0.23 m 1.37 m -1.14 m³
KW-Window -1 1.21 m 0.23 m 0.91 m -0.25 m³
V -Ventilator -1 0.91 m 0.23 m 0.76 m -0.16 m³
TD-Toilet door -1 0.76 m 0.11 m 2.13 m -0.18 m³
TOTAL 45.89 m³

6 R.C.C 1:2:4 for foundation,


column, Beam, lintels,
sunshades, roof beam & slabs,
waist slabs and lofts including
barbending, centering and
strutting and shuttering,
including all materials and labour
charges.
a)Footing Concrete
9"/9" 14 0.23 m 0.23 m 1.22 m 0.904 m³
S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.
TH
b)PIinth beam Concrte
1)All round mainwall 1 30.5 m 0.23 m 0.61 m 4.281 m³
2) Cross wall-9" 1 13.4 m 0.23 m 0.61 m 1.88 m³
3) Cross wall-4½" 1 4.72 m 0.11 m 0.61 m 0.317 m³
c)Column Concrete
Column Upto G.F roof
9"/9" 14 0.23 m 0.23 m 3.68 m 2.725 m³
Column for Parapet
9"/9" 14 0.23 m 0.23 m 0.91 m 0.674 m³
d)Lintel beam G.F
1)All round mainwall 1 30.5 m 0.23 m 0.46 m 3.228 m³
2) Cross wall-9" 1 13.4 m 0.23 m 0.46 m 1.418 m³
3) Cross wall-4½" 1 4.72 m 0.11 m 0.46 m 0.239 m³
f)Sunshade G.F
W1- Window 3 1.68 m 0.61 m 0.11 m 0.338 m³
KW-Window 1 1.68 m 0.61 m 0.11 m 0.113 m³
g)Roof slab G.F
1) All around the building 1 6.55 m 8.69 m 0.15 m 16.39 m³
2) entrance roof slab 1 2.48 m 2.59 m 0.15 m 6.22 m³
h)Waist slab
common staircase 1 0.99 m 7.8 m 0.15 m 9.941 m³
TOTAL 48.67 m³
7 Plastering the walls of
superstructure in CM 1:5,
including the cost of all materials
and labour charges. curing and
etc.
a)Out side G.F
1) All around the Building G.F 1 30.5 m 3.66 m 111.6 m²
2)Parapet wall (Inner& outer) 1 30.5 m 0.91 m 27.76 m²
b)In side G.F
1)Entrance 1 2.71 m 2.59 m 3.05 m 9.35 m³
2)Foyer 1 2.93 m 2.56 m 3.05 m 9.54 m³
3)Hall 1 6.55 m 2.59 m 3.05 m 13.19 m³
4)Kitchen 1 2.94 m 2.13 m 3.05 m 9.12 m³
5)Bedroom 1 1 2.93 m 3.05 m 3.05 m 10.03 m³
6)Bedroom 2 1 2.93 m 3.05 m 3.05 m 10.03 m³
7)Toilet 1 1.29 m 1.9 m 3.05 m 7.24 m³
Deduct for openings
MD - Main Door -1 1.22 m 0.23 m 2.13 m -0.6 m³
D1-Door -2 0.99 m 0.23 m 2.13 m -0.97 m³
AO- Arch Open -1 0.99 m 0.23 m 2.13 m -0.49 m³
W1- Window -3 1.21 m 0.23 m 1.37 m -1.14 m³
KW-Window -1 1.21 m 0.23 m 0.91 m -0.25 m³
V -Ventilator -1 0.91 m 0.23 m 0.76 m -0.16 m³
TD-Toilet door -1 0.76 m 0.11 m 2.13 m -0.18 m³
TOTAL 204.1 m²
S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.
TH

8 Ceiling plastering in CM 1:3


including the cost of all materials
and labour charges.
Ground floor
1)Entrance 1 2.71 m 2.59 m 7.019 m²
2)Foyer 1 2.93 m 2.56 m 7.501 m²
3)Hall 1 6.55 m 2.59 m 16.96 m²
4)Kitchen 1 2.94 m 2.13 m 6.262 m²
5)Bedroom 1 1 2.93 m 3.05 m 8.937 m²
6)Bedroom 2 1 2.93 m 3.05 m 8.937 m²
7)Toilet 1 1.29 m 1.9 m 2.451 m²
TOTAL 58.07 m²
9 Supplying and fixing of
Teakwood panelled doors and
using well seasoned including the
cost of all materials and labour
charges.
G.F
MD - Main Door 1 1.22 m 2.13 m 2.602 m³
D1-Door 2 0.99 m 2.13 m 4.228 m³
AO- Arch Open 1 0.99 m 2.13 m 2.114 m³
W1- Window 3 1.21 m 1.37 m 4.973 m³
KW-Window 1 1.21 m 0.91 m 1.101 m³
V -Ventilator 1 0.91 m 0.76 m 0.692 m³
TD-Toilet door 1 0.76 m 2.13 m 1.619 m³
TOTAL 17.33 m²
10 Dadooing the toilet & kitchen
walls with better quality glassed
tiles including the cost of all
materials and labour charges.(g.f)

Ground floor
1.Toilet-attached 1 7 m 2.13 m 14.94 m²
2.Kitchen 1 5 m 2.13 m 10.67 m²
TOTAL 25.61 m²

11 Supplying and fixing of M.S. Grill


for Windows including the cost of
all materials and labour charges.

W1- Window 3 1.22 m 1.37 m 5.02 m³


KW-Window 1 1.21 m 0.91 m 1.101 m³
V -Ventilator 1 0.9 m 0.76 m 0.684 m³
TOTAL 6.805 m²
S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.
TH
12 painting two coat enamal paint
over one coat zinc primer to all
m.s grill both side including all
material and labour charges.
Same qty as item 11 & both side : 1 13.6 m² 13.64 m²
13 11*2
Floor finish with imported
marble18mm thk including
supplying laying and polishing
including all materials and
labour charges.
Ground Floor
1)Entrance 1 2.71 m 2.59 m 7.019 m²
2)Foyer 1 2.93 m 2.56 m 7.501 m²
3)Hall 1 6.55 m 2.59 m 16.96 m²
4)Kitchen 1 2.94 m 2.13 m 6.262 m²
5)Bedroom 1 1 2.93 m 3.05 m 8.937 m²
6)Bedroom 2 1 2.93 m 3.05 m 8.937 m²
7)Toilet 1 1.29 m 1.9 m 2.451 m²
TOTAL 58.07 m²

14 polishing over doors and


windows using good quality
melamine polish two coats over
one coat of sealar and including
the cost of all materials and
labour charges.
Same qty as item no : 9*2 1 17.3 m SAY 34.66 m²
15 Colorwash using good quality
emulsion over one coats of
whitewash and ,including the cost
of all materials and labour
charges.
a)Outside G.F
i)Outside take item no 7 1 139 m SAY 139.4
b)Inside G.F
Il) In side take item no 7 1 68.5 m SAY 68.5
c)Ceiling Area G.F
Same qty as per item no 8 SAY

1 58.1 m 58.07
16 providing compound wall gate in
strainless steel frame and wooden
planks including fitting &
fixtures including the cost of all
materials and labour charges. L.S
S.NO DESCRIPTION OF WORKS NOS. LENGTH BREAD DEPTH QTY.
TH
17 Provision for electrical
arrangements including fitting &
fixtures including the cost of all
materials and labour charges. L.S
18 Provision of water sump in R.C.C
wall including fitting & fixtures
including the cost of all materials
and labour charges. L.S
19 Provision for external & internal
plumbing arrangemants including
fitting & fixtures including the
cost of all materials and labour
charges.
20 Provision for staircase handrail
including fitting & fixtures
including the cost of all materials
and labour charges. L.S
21 Provision for internal and
external sanitary works and
septic tank & dispersion trench
arrangements including fitting &
fixtures including the cost of all
materials and labour charges. L.S
22 Provision for bore well & motor
including fitting & fixtures
including the cost of all materials
and labour charges. L.S
23 Miscellaneous charges

L.S

ENGINEER