114 | P a g e

2. With the Decline ac vi es isolated, click on any of the column headers to select the Decline tasks.

3. With all the Decline tasks selected, right-click and select Assign Resource(s) from the shortcut menu.

4. From the presented Assign Resources dialog box, select the Jumbo 1 resource from the le panel and click
115 | P a g e
The Jumbo 1 resource will now be assigned to the Decline tasks. Repeat the same checks as listed in the Checking
Resource Assignment Results sec on to confirm the assignment is correct.
5. Repeat the process to assign the remaining tasks to the following resources.
RESOURCE NAME ACTIVITY ASSIGNMENT
Blind Hole Borer Vent Rise
Jumbo 2 Remaining produc on tasks
Produc on Hole Rig Produc on Drilling
Stope Boggers Stope
Hydraulic Backfill Backfill

119 | P a g e
Once the leveling is complete, a report displays advising the elapsed me.
8. Click and the Resource Leveling dialog box.

A er processing, task dura ons are adjusted to accommodate the priori es setup in the Leveling rules.
Before Leveling
Pre Resource Leveling, all Produc on Hole Rig tasks have overlapping start dates
A er Leveling
Post Resource Leveling, the Produc on Hole Rig resourced tasks are pushed out compliant to the start date
priority.