Pipe - Velocity - On Gravity Sloped Pipes
Pipe - Velocity - On Gravity Sloped Pipes
Pipe - Velocity - On Gravity Sloped Pipes
160 Dia. 1.486 x 0.1632 x 0.1000 0.0242 1.486 x 0.2581 x 0.1000 0.0384
= = 2.42 Ft./Sec = 3.84 Ft./Sec
slope 1/100 n (0.01) 0.01 n (0.01) 0.01
200 Dia. 1.486 x 0.1886 x 0.0900 0.0252 1.486 x 0.2996 x 0.0900 0.0401
= = 2.52 Ft./Sec = 4.01 Ft./Sec
slope 1/125 n (0.01) 0.01 n (0.01) 0.01
315 Dia. 1.486 x 0.2472 x 0.0707 0.0260 1.486 x 0.3799 x 0.0707 0.0399
= = 2.60 Ft./Sec = 3.99 Ft./Sec
slope 1/200 n (0.01) 0.01 n (0.01) 0.01
400 Dia. 1.486 x 0.2994 x 0.0577 0.0257 1.486 x 0.4755 x 0.0577 0.0408
= = 2.57 Ft./Sec = 4.08 Ft./Sec
1/300 n (0.01) 0.01 n (0.01) 0.01
Project: WATANI RESIDENTIAL DEVELOPMENT PHASE 1A
Location: KHALIFA - A, Abu Dhabi
160 Dia. 1.486 x 0.1632 x 0.1000 0.0242 1.486 x 0.2004 x 0.0707 0.0211
= = 2.42 Ft./Sec = 2.11 Ft./Sec
1/200 n (0.01) 0.01 n (0.01) 0.01
200 Dia. 1.486 x 0.1886 x 0.0900 0.0252 1.486 x 0.2996 x 0.0707 0.0315
= = 2.52 Ft./Sec = 3.15 Ft./Sec
1/200 n (0.01) 0.01 n (0.01) 0.01
315 Dia. 1.486 x 0.2472 x 0.0707 0.0260 1.486 x 0.3799 x 0.0707 0.0399
= = 2.60 Ft./Sec = 3.99 Ft./Sec
slope 1/200 n (0.01) 0.01 n (0.01) 0.01
400 Dia. 1.486 x 0.2994 x 0.0577 0.0257 1.486 x 0.4755 x 0.0707 0.0500
= = 2.57 Ft./Sec = 5.00 Ft./Sec
1/200 n (0.01) 0.01 n (0.01) 0.01
Project: WATANI RESIDENTIAL DEVELOPMENT PHASE 1A
Location: KHALIFA - A, Abu Dhabi
110 Dia. 1.486 x 0.1392 x 0.1000 0.0207 1.486 x 0.2004 x 0.0707 0.0211
= = 2.07 Ft./Sec = 2.11 Ft./Sec
1/200 n (0.01) 0.01 n (0.01) 0.01