PART – F

SCHEDULE OF FINANCIAL QUOTE

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
482

Name of work: Construction of Additional infrastructure at National Institute of Technology, Trichy, Tamil
Nadu. SH 1:- Construction of Annex buildings for Mechanical and Metallurgical & Materials
Engineering (MMME) Department (G+2) & Laboratory Annex Building for Production Engineering
Department, (G+2), Including Internal Water Supply, Sanitary Installations, Civil External service
connections, Internal Electrical Installations, Lighting conductors, External LT service connection, RO plant,
Water coolers, Audio Visual system, VRF/VRV AC System, CCTV, EPABX, Lift, Firefighting with down comer
system, UPS, Automatic Fire alarm system ,Power wiring and plugs, LAN Networking, Wi-Fi System,
emergency light & illuminated signages, Street Lighting, Overhead tanks, Levelling , Internal Roads & Path
ways with kerb stone, Sewer, storm water drains, Filter water supply, Horticulture work, Dismantling
works and all other related works to make the buildings functional on Engineering, Procurement and
Construction (EPC) Contract basis

SCHEDULE OF QUANTITIES
Sl. Rate Amount
Description of Item Quantity Unit
No. (Rs.) ( Rs.)
1 2 4 5 6
Composite Work including Civil and E & M
Work: Building portion
Construction of Additional infrastructure at
National Institute of Technology, Trichy, Tamil
Nadu.
(a) Planning, Designing & Execution of all
related Services including Internal Water
Supply , Sanitary Installations, over head water
tanks on terrace for drinking and fire fighting,
Civil External Service Connections etc as per
NBC 2016 and integrating with existing lines
and with External Development works,
Levelling, Internal Roads & Path ways, Sewer,
1 Filter water supply, Horticulture works, and all
other related works to make the building
functional on Engineering, including design of
minor components for which design not
specifically provided for etc., all complete as
per the scope, specifications, conditions and
other details stipulated in Part B and by
incorporating stipulated specifications and
integrating all internal & external services
pertaining to Civil and making the facilities
functional all complete as per directions of
Engineer-in-Charge on Engineering, Procurement
and Construction (EPC) Contract basis.
(b) Planning, designing and execution of E&M

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
483

components i.e., Internal Electrical


Installations, power wiring & plugs,
Telephone conducting and wiring,
lightning conduits, Water Coolers,
emergency light and illuminated signages, 2
no’s machine Room type 13 No passenger lift
of speed 1.0 m/s, fire alarm system( manual),
Firefighting with down comer system, Fire
extinguishers, LED lights, External LT
Electrical Service connection, LT Cable,
Street light poles with UG cabling, LED street
lighting system with fittings and control units,
Low Side HVAC works including Chiller lines,
IP Based LAN &Wi-Fi Networking and IP
Surveillance System ( CCTV) , IPEPABX system
etc System all complete as per the scope ,
specifications, conditions and other details
stipulated in Part C and by incorporating
stipulated specifications and integrating all
internal & external services pertaining to
Electrical and making the facilities functional
all complete as per directions of Engineer-in-
Charge on Engineering, Procurement and
Construction (EPC) Contract basis
(c) Obtaining and submission of all necessary
statutory approvals on completion of above
proposed building work from all local
authorities, completion certificate from all
concerned local bodies or any other
authorities, obtaining water and electricity
connections from concerned state authorities
etc including preparation & submission of all
'As built drawings' (on completion of entire
work).
Note: -
1. Defect liability period of 36 months after the
issue of the certificate final or otherwise, of
completion of work, or till the final bill has
been prepared and passed whichever is later
is included in the scope of above work as
stipulated in the NIT/Tender document
2. Measurement of Plinth Area for payment will
be as per guidelines on IS Code: 3861 and

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
484

Annexure II of DPAR-2021
Areas marked as OTS (Open to Sky)/Shaft and
Architectural boxes marked on Detailed
Architectural floor plans attached with this
tender document will not be measured in
plinth area for payment.
Note: Architectural boxes/elevations shown in
Drawings will not be measured as plinth area

Construction of Annex Building for Mechanical


& Metallurgical and Materials Engineering
Department( G+2) for NIT at Trichy Including
Internal Water Supply, Sanitary Installations,
Civil External service connections, Internal
Electrical Installations, External LT service
connection, RO plant, Water coolers, Audio
Visual system, VRF/VRV AC System, CCTV,
EPABX, Lift, Fire fighting with wet riser
system, Automatic Fire alarm system, Power
1.1 8472.50 Sqm 54321.6648 460240305.00
wiring and plugs, LAN Networking, Wi-Fi
System, emergency light & illuminated
signages, Street Lighting ,Terrace water tanks
, Levelling, Internal Roads & Path ways with
kerb stone, Sewer, storm water drains, Filter
water supply, Horticulture work, and all other
related works to make the building functional
on Engineering, Procurement and
Construction (EPC) Contract basis.

Construction of Annex Building for Production


Engineering Department ( G+2)for NIT at Trichy
Including Internal Water Supply, Sanitary
Installations, Civil External service connections,
Internal Electrical Installations, External LT
service connection, RO plant, Water coolers,
Audio Visual system, VRF/VRV AC System, 228475547.00
1.2 4393.39 Sqm 52004.3854
CCTV, EPABX, Lift, Firefighting with wet riser
system, Automatic Fire alarm system, Power
wiring and plugs, LAN Networking, Wi-Fi
System, emergency light & illuminated
signages, Street Lighting, Terrace water tanks ,
Levelling, Internal Roads & Path ways with kerb
stone, Sewer, storm water drains, Filter water

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
485

supply, Horticulture work, and all other related


works to make building functional on
Engineering, Procurement and Construction
(EPC) Contract basis.

Grand Total 688715852.00

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
486

Central Public Works Department


N.I.T. No:
Name of work: Construction of Additional infrastructure at National Institute of Technology,
Trichy, Tamil Nadu. SH 1:- Construction of Annex buildings for Mechanical and
Metallurgical & Materials Engineering (MMME) Department (G+2) & Laboratory Annex
Building for Production Engineering Department, (G+2), Including Internal Water Supply,
Sanitary Installations, Civil External service connections, Internal Electrical Installations,
Lighting conductors, External LT service connection, RO plant, Water coolers, Audio Visual
system, VRF/VRV AC System, CCTV, EPABX, Lift, Firefighting with down comer system,
UPS, Automatic Fire alarm system ,Power wiring and plugs, LAN Networking, Wi-Fi System,
emergency light & illuminated signages, Street Lighting, Overhead tanks, Levelling ,
Internal Roads & Path ways with kerb stone, Sewer, storm water drains, Filter water supply,
Horticulture work, Dismantling works and all other related works to make the buildings
functional on Engineering, Procurement and Construction (EPC) Contract basis
SCHEDULE OF QUANTITY
Name of the Contractor
Percentage
Estimated cost above or % in Total Cost
Sl.No. Name of component
(Rs) below the Figures (Rs)
estimated cost
1 2 3 4 5 6
Overall composite 688715852.00
A
Package
Total Rs. 688715852.00

1. The Column Nos 4&5 are mandatory to be filled by the bidders/ tenderers. If all these columns
are left blank, the tender become invalid.
2. The amount in figures in column No.6 shall appear automatically corresponding to the
percentage quoted in column No.4 & 5.
3. The tenderer is need to quote the percentage only above or below or at par with the
estimated cost to cover all the rates of item covered under package.
4. The percentage shall be written in 2 (two) place of decimal.
5. If the percentage selection in column No 4 is “At Par", by default the percentage will be
considered as “Zero" only. In other words if "At par" is selected in column No.4, then no need to
fill column No.5
6.The Payment will be made as per the PAYMENT SCHEDULE mentioned in Part-E

Signature of Contractor Executive Engineer-I


CPWD,Trichy

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)
487

CORRECTION-Nil INSERTION-Nil AE(C) AE(E)

DELETION-Nil OMISSION-Nil EE(C) EE(E)


AE(E)

You might also like