DESIGN DEVELOPMENT DELIVERABLES LIST

The Design Development Phase should provide definite design conclusions based on the approved
Schematic Design framework and represent approximately 50% of design completion. Where the
consultant requires a decision or recommendation to proceed to the Construction Document Phase,
adequate supportive and explanatory information should be provided upon which a determination can
be made. The submittal should be presented in the Standard Plan and Specification format with
additional narrative materials as necessary. Provide written response to owners schematic review
comments. Resolve any outstanding issues on schematic design checklist. Designer shall insure all sub-
consultant work is coordinated.

Objective: To develop in further detail the approved conceptual design. The design documents should
clearly identify the developed civil, architectural, structural, mechanical, electrical, plumbing and fire
protection design solutions. All major features and components of the design solution should be
documented and included in the updated cost estimate. Upon approval of the Design Development
Package by the owner, the design team will begin execution the final construction design details. The
approved Design Development Package constitutes a complete concept and no further changes to the
plans, elevations or building systems will be allowed except to comply with construction or code
requirements.

The following represents the minimum deliverables under this phase of the project, unless specifically
struck out during fee negotiations. The A/E shall submit this checklist with each item checked/initialed
as a representation that all minimum deliverables have been satisfied.

CIVIL DRAWINGS
A. Site Plan
 Building location plan  Utility Plans
a. Tie building dimensionally with a. Identify existing and new utilities to the
pertinent adjacencies, permanent building (electrical, water, gas, fiber
bench mark, street lines, property lines, and telephone)
required setbacks, easements, rights of b. Identify sanitary and storm laterals
way from the building to the mains
b. Indicate manholes, sewers, hydrants, c. Identify site storm sewers, inlets,
light standards, interface with survey. manholes, etc.
 Grading and paving plans, include contours,
critical spot elevations, main floor level B. Site Sections
datum elevation  Include typical driveway, parking area,
a. Include sidewalks, ramps, stairs, sidewalk cross sections.
driveways, parking areas including
layout geometry C. Typical Design Details
b. Site drainage and retention areas
 Railing, stairs, ramps, walkway paving types
and patterns, benches, site lighting, other
significant features

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 1 of 6


ARCHITECTURAL DRAWINGS
A. Code Analysis Plan
 Code Footprint (include all fire rated walls,  Code Analysis (show on drawings)
partitions, barriers, etc.)

B. Architectural Floor Plans


 Dimensioned structural bay system  All keyed references complete (match lines,
 Internal partitions located, drawn and building sections, large scale plans, key
dimensioned notes, etc.)
 All casework and other equipment called  Finish floor elevations noted
out on plans  Expansion joints indicated
 Major mechanical/electrical systems  Building cores (stairs, elevators, toilets,
determined and their requirements shafts, etc) drawn to a larger scale (+/ -
reflected and indicated on the plans ¼”=1’-0”), dimensioned and keyed to larger
including louvers, areaways and utility scale plans
entrances  Plans and elevations of feature areas
 Locate all plumbing fixtures (lobby, special spaces) drawn to a larger
 All rooms named and numbered scale (+/ - ¼”=1’-0”) with all surfaces shown
 Locate exterior and interior doors and and materials called out and keyed to larger
windows scale plans
 Locate typical and fire rated partition types  Demolition plan

C. Reflected Ceiling Plan


 Located lighting fixtures, speakers, cameras  Identify major ceiling materials and their
 Soffits/bulkheads, skylights relationship with partitions
 Identify all areas with exposed structure

D. Roof Plan
 Dimensioned structural grid and building  Locate rooftop equipment
offsets  Locate expansion joints
 Roof access locations and types  For roof replacement projects, reference
 Roof material and slopes core cuts and indicate components to be
 Primary and secondary roof drain locations removed vs. to remain
 Typical roof details denoting system
components

E. Exterior Building Elevations


 Building elevations including roof structures  Exterior mechanical equipment
and foundations  All materials noted; demarcation of
 Identify and locate all exterior windows and materials shown
doors  Detailed elevations at a larger scale (+/ -
 Identify floor levels, vertical dimensions and ¼”=1’-0”) as necessary to explain intent
overall building heights (building entrance, special
 Column center lines brickwork/masonry, building canopy, etc.)
 Locate expansion joints and major panel  Major keyed references: match lines,
joints buildings sections, wall sections

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 2 of 6


F. Building and Wall Sections
 Include major building sections, identify  Vertical dimensions including floor to floor
column lines, feature openings and and ceiling heights
relationships between floors, ceilings,  Finish grades around the building
structure and mechanical systems  Typical wall sections or assembly details

G. Landscaping Plans
 Site plan indicating lawn and plantings.  Consideration is to be given to the
topographic information for drainage

H. Details
 Large scale details of major exterior wall  Key areas shown including stairs, elevators,
assemblies, (parapets to foundation) loading docks, shafts and other conditions
 Large scale details of major foundation and where wall sections reveal the third
perimeter treatment dimension
 Typical window and door details (i.e. head  Major casework elevations and millwork
jamb and sill conditions) profiles
 Typical interior and exterior columns details  Partition types

I. Interior Elevations
 Elevations of significant interior spaces

J. Schedules
 Draft interior finish schedule  Draft window and glazing schedule
 Draft door and frame schedule

STRUCTURAL DRAWINGS
A. Structural Plans
 Foundation plan including interior and  Framing plans for all floors and roof
perimeter foundations, footings, piles, including major member sizes noted or
caissons, wall beams and grade beams as scheduled
needed.  Typical column sizes shown
 Locate columns, beams, purlins, joists, etc
.
B. Structural Sections/Details
 Major penetrations (i.e. slab openings, pits,  Provide wind, seismic, dead and live loads
tunnels and ramps) located on drawings design information.
 Expansion joints located  Location of in-floor electrical system
 Typical edge of slab details for cladding  Special conditions noted (shoring,
attachment underpinning, etc.)
 Footing, beam, column and connection  Updated structural building elevations.
details.

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 3 of 6


MECHANICAL DRAWINGS
A. Mechanical Floor Plans
 Locate major equipment such as boilers,  Heating and cooling load criteria for each
cooling towers, air handling units, heat space and major duct or pipe runs sized to
pumps, exhaust fans, unit heaters, interface with structural and architectural
perimeter fin tubes, etc. building components.
 Mechanical room equipment layouts are  Locate intake and exhaust louvers
shown  Coordinate ceiling plenum space with
 Size and locate utility risers, shafts, chases architectural, plumbing, fire protection,
and equipment coordinated with electrical, structural
architectural plans  Air and water flow diagrams showing CFM
 Consider access and replacement and GPM respectively.
requirements with all equipment room  Show electrical requirements such as panel
layouts. size, location, voltage and current
 Indicate typical layouts of all ceiling devices requirements for mechanical equipment.

B. Sections
 Critical mechanical room cross sections  Corridor sections indicating duct clearances

C. Cut Sheets / Product Data


 Grills and diffusers  Controls/Building Management Control
 Special equipment Systems (BMCS)

PLUMBING / FIRE PROTECTION DRAWINGS


A. Plumbing / Fire Protection Floor Plans / Detail Plans
 Locate all toilets, urinals, lavatories, mop  Coordinate plumbing chase and shaft
sinks, floor drains and drinking fountains depths with architectural
 Size and locate utility risers, shafts, chases  Consider access and replacement
and equipment on architectural plans requirements with all room layouts
 Locate underslab sanitary and supply lines  Coordinate ceiling plenum space with
 Locate maintenance hose bibs in toilet architectural, fire protection, mechanical,
rooms, custodial rooms and on exterior of electrical and structural
building  Coordinate piping site and flows with
 Include roof drainage system (quantity and existing sprinklers if applicable.
location of roof drains, internal and external  Fire Sprinklers: On new construction, make
downspouts) arrangements to perform a flow test.
 Coordinate fixture sizes and mounting Include the flow test report in the Contract
heights (including any special accessibility Documents.
and age groups)

B. Cut Sheets / Product Data


 Plumbing fixtures  Special Equipment
 Sprinkler heads  Fire suppression system

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 4 of 6


ELECTRICAL DRAWINGS
A. Electrical Floor Plans
 Size and locate utility equipment on  Locate electrical devices for typical
architectural plans. classroom, offices, special classrooms
 Major electrical equipment (switch gear, including power receptacles, computer,
distribution panels, emergency generator, telephone, TV, light switches, closed circuit
transfer switches, UPS system, etc.) TV, fire alarm, security and intercom
dimensioned and drawn to scale into the devices
space allocated, also include riser diagram  Locate exit and emergency lighting and fire
or one line diagram. alarm devices (consider ADA requirements)
 Identify service amperage and voltage  Consider access and replacement
requirements requirements with all utility room layouts
 Locate size of conduit runs, cable trays,  Coordinate ceiling plenum space with
risers, shafts, chases, etc architectural, plumbing, fire protection,
 Locate size site electrical: transformers, mechanical, structural
underground service, entrance details, etc  Update design calculations to include
 Identify typical and feature lighting fixtures: power consuming equipment and load
ceiling and wall types characteristics.
 Identify electric and telephone panel room  Site lighting, locate and identify all lighting
locations fixtures.

B. Cut Sheets / Product Data


 Light fixtures  Factory installed lighting and voltage surge
 Fire alarm devices protection equipment
 Special equipment

OTHER REQUIREMENTS
A. Specialty Consultants
 All specialty consultants should provide the same level of information which is required for MEP
disciplines. Typical specialty consultants include: Lab, security, acoustical, A/V and kitchen consultants

B. Specifications
 Draft specification
 When a product is specified, three manufacturers must be listed as acceptable. Contact the Project
Manager if circumstances require a product to be dual or sole sourced.

C. Cost Estimates and Schedule


 Major line items costs for all building  Update cost estimate of construction and
components, verify inclusion of all elements compare it to the allowable funds for
by cross-checking against specification for construction.
omissions  Estimate construction period, identify any
 Identify escalation to mid-point of phased work and any long-lead time for
construction special items.
 Sole source items identified as approved.

D. Energy Report
 Updated energy report

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 5 of 6


E. General
 As documents develop, confer with approval process as needed for
regulatory agencies connection to their systems.
 Identify all documents with Northwest’s b. Investigate and report on their review
project name and number of all applicable local, public and utility
 Apply the same date to all documents regulations;
 Review the building design program, scope c. Notify the Architect of space and
of work and verify compliance location requirements for systems
 Mechanical and electrical engineers: d. Prepare estimates of probable
a. Contact utility companies and public operating costs with recommendations
authorities for all services and initiate for implementation

F. Submittals
 Two (2) complete sets of submittals for review
 Electronic thumb drive of all submittals

Rev 03/02/2020 Adapted from State of Missouri OA FMDC Page 6 of 6