BILL OF QUANTITIES

SL NO DESCRIPTION OF WORK Unit QTY Unit Price Total Price


A. Mobilization
A.1 Preliminaries & mobilization
Cutting/ filling/ grading to make
A.2
finished ground level
A.3 Safety Gear

A.4 Monthly reports, Correspondences…etc

A.5 Sign Board

A.6 ANY OTHER ITEM


TOTAL OF A

B. Sub Structure works


B.1 Excavation

P.C.C for footings, Tie beams, Solid


B.2 block, etc

B.3 R.C for Raft,Isolated Footing

B.4 R.C. for strap beams , Tie beams

B.5 R.C for neck columns

B.6 R.C for Retaining Walls

B.7 Floor concrete with BRC mesh

B.8 Polythene sheets

B.9 water proofing system for Concrete

B.10 water proofing system for Solid Block

B.11 Refilling with excavated material

B.12 Refilling with imported material

B.13 Road Base

Expansion joint with flexole sheet &


B.14 mastic sealant “if required”

B.15 Dewatering “if required”

B.16 Anti termite control

B.17 U.G water tank

B.18 ANY OTHER ITEM


TOTAL OF B
C. Super Structure works
C.1 R.C. columns(Ground floor)

C.2 R.C. beams (Ground floor)

C.3 R.C. solid slab (Ground floor)

C.4 R.C.Lintels/Arches/ etc. (Ground floor)

C.5 R.C. columns (1st. floor)

C.6 R.C. beams (1st. floor floor)

C.7 R.C. solid slab (1st. floor floor)

C.8 R.C.Lintels/Arches/ etc. (1st. floor)

C.9 R.C. Staircase

C.10 Parapet

C.11 ANY OTHER ITEM


TOTAL OF C

D. Block Work
100 thick hollow block work (Ground
D.1 floor)
150 thick hollow block work (Ground
D.2 floor)
200 thick hollow block work (Ground
D.3 floor)
200 thick solid block work (Ground
D.4 floor)
200 thick block work “Thermal
D.5 insulated” (Ground floor)

D.6 100 thick hollow block work (1st. floor)

D.7 150 thick hollow block work (1st. floor)

D.8 200 thick hollow block work (1st. floor)

200 thick block work “Thermal


D.9 insulated” (1st. floor)

D.10 ANY OTHER ITEM

TOTAL OF D
E. Plaster works

E.1 Plaster for ceilings (Ground floor)

Plaster for internal walls (Ground


E.2 floor)

E.3 Plaster for external wall (Ground floor)

E.4 Plaster for ceilings (1st. floor)

E.5 Plaster for internal walls (1st. floor)

E.6 Plaster for external wall (1st. floor)

E.7 ANY OTHER ITEM


TOTAL OF E

F. External finishes
F.1 Full Epoxy system

F.2 Granite

F.3 Stainless steel finish

F.4 Groove in Plaster

F.5 Clay tiles

F.6 Reflective glass

F.6 ANY OTHER ITEM


TOTAL OF F

G. Floor finishes
G.1 Graniti tile (B.C Dhs)

G.2 Marble works (B.C Dhs)

G.3 Terrazzo tiles (B.C Dhs)


Ceramic tiles for toilet and pantry (B.C
G.4 Dhs)

Ceramic tiles for Rooms (B.C


G.5 Dhs)

Ceramic tiles for kitchen (B.C


G.5 Dhs)

G.5 ANY OTHER ITEM


TOTAL OF G

H. Skirting
H.1 Terrazzo

H.2 Granite

H.3 Marble

H.4 Ceramic tile

H.5 Graniti tile Skirting

H.6 Terrazzo steps

H.7 Granite steps

H.8 ANY OTHER ITEM


TOTAL OF H

I. Wall finish
I.1 Granite (B.C Dhs/m²)

I.2 Marble Cladding (B.C Dhs/m²)

I.3 Ceramic tiles (B.C Dhs/m²)

I.4 Emulsion Paint

I.5 Epoxy Paint

I.6 ANY OTHER ITEM


TOTAL OF I

J. Ceiling finishes
J.1 Emulsion paint

J.2 Epoxy paint

J.3 Spray Plaster

12 mm Gypsum board false ceiling as


J.4 per design

J.5 600x600mm gypsum tile vinyl backed

J.6 Cement Sheet

J.7 ANY OTHER ITEM


TOTAL OF J

K. External works
K.1 8 cm interlock in two color

K.2 6 cm interlock in two color

K.3 Curbstone

K.4 External stair

K.5 Garage

K.6 Septic tank & Soak away

K.6 Internal & External Manhols

K.7 PLANTED POINT

K.8 External lights ( baljactor NO. 2)

K.9 ANY OTHER ITEM


TOTAL OF K

L. Roofing & Waterproofing


Water proofing sys. For the roof as
L.1 specified
L.2 Roof tiles

L.3 Roof skirting

L.4 Water proofing for baths & kitchen

L.5 Aluminum Flushing for roof.

L.6 Mastic for roof

L.7 Water proofing for the plaster

L.8 Water Stops

L.9 ANY OTHER ITEM


TOTAL OF L

M. Joinery and wood work

N. Aluminum & Metal works

ELECTRICAL/ CATV/
O.
INSTALLATION

P. Gas Works
PLUMBING & DRAINAGE
Q.
INSTALLATION

R. A/C Works

S. Other works
S.1 Cupboards for kitchen

S.2 Mirror

S.3 Counters

S.4 Internal Signage

S.5 External Signage

S.6 Column Protection

TOTAL OF S

T. Compund wall (four side)


T.1 R.C.C OF Compund wall
T.2 BLOCK OF Compund wall
T.3 PLASTER OF Compund wall
T.4 PAINT OF Compund wall
T.5 ELEC. OF Compund wall
T.6 Gates
T.7 ANY OTHER ITEM
TOTAL OF T

X. TOTAL PRICE OF VILLA (ALL ITEM FROM (A) TO (T)

Y. TOTAL PRICE OF K. BLOCK

TOTAL PRICE OF VILLA & K.B.(X. & Y.)

Any item of work not included in this B.O.Q which is essential for the
satisfactory completion of the project, the Contractor has to add the
same in this list or to be considered elsewhere in their offer
%
1.50%

10%
20%

6%
6%

2%

3%
1%

2%

1.50%

3%
4%

5%

6%

10%

0.50%
7%

0.50%

1%

10%

tial for the


o add the
r

You might also like