PROJECT:

LOCATION:
SUBJECT: CE 111 - QUANTITY SURVEYING

SUMMARY OF BILL OF QUANTITIES

ITEM NO. DESCRIPTION TOTAL COST

I GENERAL REQUIREMENTS -

II EARTHWORKS -

III STRUCTURAL WORKS -

IV ARCHITECTURAL WORKS -

V PLUMBING WORKS -

VI ELECTRICAL WORKS -

VII MECHANICAL WORKS -

TOTAL PROJECT COST


-

TOTAL BLDG AREA (SQ.M.)


COST PER SQ.M. #DIV/0!

Submitted by: NAME / SIGNATURE


QS Student - BSCE 3A

NAME / SIGNATURE
QS Student - BSCE 3A

Submitted to:
ENGR. MELANIE ROSE P. PASCUA
CE Department Instructor
PROJECT:
LOCATION:
SUBJECT: CE 111 - QUANTITY SURVEYING

DETAILED COST ESTIMATE / BILL OF QUANTITIES

MARK-UPS IN
MATERIALS ESTIMATED TOTAL
ITEM PERCENT TOTAL MARK-UPS
DESCRIPTION LABOR DIRECT VAT INDIRECT TOTAL COST UNIT COST
NO. UNIT
QTY UNIT COST AMOUNT COST OCM PROFIT % VALUE COST
MEASURE
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(3 + 4) (6 + 7) (5 x 8) 5%(5 + 9) (9 + 10) (5 + 11) (12 / 1)
I GENERAL REQUIREMENTS
I.1 Mobilization/Demobilization 1.00 lot
I.2 Temporary Facilities 1.00 lot
I.3 Safety and Health 1.00 lot
Safety Helmet man-days
Safety Shoes man-days
Safety Vest man-days
Safety Gloves man-days
Rain Coat man-days
Rubber Boots man-days
Safety Signages 1.00 lot
Safety and Health Personnel 1.00 lot
I.4 Site Preparation/Demolition (if any) 1.00 lot
I.5 Testing and Inspections 1.00 lot
I.6 Bonds, Permits and Insurances 1.00 lot
Others (if any)
SUBTOTAL OF ITEM I 0.00 0.00 0.00
II EARTHWORKS

SUBTOTAL OF ITEM II 0.00


III STRUCTURAL WORKS

SUBTOTAL OF ITEM III 0.00


IV ARCHITECTURAL WORKS

SUBTOTAL OF ITEM IV 0.00


V PLUMBING WORKS

SUBTOTAL OF ITEM V 0.00


VI ELECTRICAL WORKS

SUBTOTAL OF ITEM VI 0.00


VII MECHANICAL WORKS

SUBTOTAL OF ITEM VII 0.00

TOTAL PROJECT COST Php 0.00

PREPARED BY: CONFORME:

Name/Signature ENGR. MELANIE ROSE P. PASCUA


QS Student - BSCE 3A CE Department Instructor

Name/Signature
QS Student - BSCE 3A
PROJECT:
LOCATION:
SUBJECT: CE 111 - QUANTITY SURVEYING

SUMMARY OF MATERIALS, LABOR AND EQUIPMENT COST

A MATERIAL COST
ITEM NO. DESCRIPTION UNIT UNIT COST

B LABOR RATES
ITEM NO. DESCRIPTION RATE PER HOUR RATE PER DAY

C EQUIPMENT RATES
ITEM NO. DESCRIPTION RATE PER HOUR RATE PER DAY
PREPARED BY:

CRISTOBAL, HENRIETTE MAY


QS Student - BSCE 3A

TABOR, CLAIRE
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING

CANVASS SHEET
Column1 Column2 Column3 Column4 Column5 Column6 Column7
ITEM OF WORK: GENERAL REQUIREMENTS AS OF: MARCH 01, 2024

SPECIFICATION UNIT SUPPLIER 1 COST (₱) UNIT SUPPLIER 2 COST


I. MOBILIZATION / DEMOBILIZATION
A. MINI DUMP TRUCK (RENTAL)
INCLUSIONS: PER DAY Acel Equipment ₱1,420.00 PER LOAD Blazo Truck Trading ₱6,000.00
MINI DUMP TRUCK
TRUCK OPERATOR
LABOR
GASOLINE
B.BOOM TRUCK (RENTAL)
INCLUSION: PER DAY Acel Equipment ₱1,017.90 PER DAY Rand R Boom Truck Rentals ₱10,000.00
BOOM TRUCK
TRUCK OPERATOR
GASOLINE
II. TEMPORARY FACILITIES
A. STORAGE FACILITY / TEMPORARY SHELTER / SITE OFFICE
G.I. CORRUGATED COLORED SHEET (0.4mm THK x 4' x 10') 1 Pc BETTER LUCK TRADING ₱506.00 1 Pc CITY LUCK ₱462.00
G.I. TIE WIRE #16 1 Kg WCO TRADING ₱85.00 1 Kg EAST LUMBER TRADING ₱75.00
MARINE PLYWOOD (3/4" THK 4' x 8') 1Pc BETTER LUCK TRADING ₱990.00 1Pc CITY LUCK ₱1,605.00
MARINE PLYWOOD (1/4" THK 4' x 8') 1 Pc BETTER LUCK TRADING ₱320.00 1 Pc EAST CENTRAL ₱480.00
ORDINARY PLYWOOD (1/4'' THK 4' X 8') BETTER LUCK TRADING ₱285.00 1Pc EAST CENTRAL ₱460.00
ORDINARY PLYWOOD (5mm THK,1220mm x 2440mm) 1 Pc CITIHARDWARE URDANETA ₱581.00 1 Pc CITIHARDWARE BINALONAN ₱760.00
COCO LUMBER (2" x 2" x 10') 1 Pc CITY LUCK ₱130.00 1 Pc EAST CENTRAL ₱180.00
COCO LUMBER (2" x 4" x 10') 1 Pc CITY LUCK ₱267.00 1 Pc EAST CENTRAL ₱420.00
COMMON NAILS (3") 1Kg BETTER LUCK TRADING ₱65.00 1kg CITY LUCK ₱65.00
COMMON NAILS (2") 1 Kg BETTER LUCK TRADING ₱65.00 1 Kg CITY LUCK ₱65.00
MISC:
FLUORESCENT TUBE 1 Pc WILCON DEPOT ₱319.00 1 Pc CITIHARDWARE VILLASIS ₱260.00
MONOBLOCK 1 Pc ACE HARDWARE ₱410.00 1 Pc BONUS ₱350.00
ELECTRIC FAN 1 Pc ACE HARDWARE ₱1,200.00 1 Pc CITIHARDWARE VILLASIS ₱1,149.00
B. TEMPORARY UTILITIES
ELECTRICITY BILL PER MONTH PANELCO ₱2,000.00 PER MONTH
WATER BILL PER MONTH PRIME WATER ₱1,000.00 PER MONTH
C. TEMPORARY SANITATION
WATER CLOSET 1 Pc BETTER LUCK TRADING ₱1,650.00 1 Pc EAST CENTRAL ₱1,150.00
PVC HOSE BIBB (1/2") 1 Pc REDNON TRADING ₱30.00 1 Pc WILCON DEPOT ₱90.00
PIPES AND FITTINGS 1 LS REDNON TRADING ₱1,200.00 1 LS CITIHARDWARE VILLASIS ₱1,000.00
D. FIRST AID STATION
FIRST AID KIT BOX 1 Pc REDNON TRADING ₱305.00 1 Pc ACE HARDWARE ₱1,049.00
MEDICINE & OTHER KITS 1 LS MERCURY DRUG PHARMACY ₱500.00 1 LS ST. JOSEPH ₱500.00
III. SAFETY AND HEALTH
A. PERSONAL PROTECTIVE EQUIPMENT
SAFETY SHOES 1 PAIR ACE HARDWARE ₱1,299.00 1 PAIR WILCON DEPOT ₱375.00
SAFETY VEST 1 PAIR CITY LUCK ₱225.00 1 PAIR WILCON DEPOT ₱234.00
SAFETY GLOVES 1 PAIR CITY LUCK ₱38.00 1 PAIR WILCON DEPOT ₱155.00
ELECTRIC RES. GLOVES 1 PAIR ACE HARDWARE ₱369.00 1 PAIR REDNON TRADING ₱299.00
SAFETY BOOTS 1 PAIR ACE HARDWARE ₱459.00 1 PAIR WILCON DEPOT ₱500.00
SAFETY GLASSES 1 Pc ACE HARDWARE ₱139.00 1 Pc WILCON DEPOT ₱101.00
SAFETY GOGGLES 1 Pc ACE HARDWARE ₱129.00 1 Pc WILCON DEPOT ₱247.00
SAFETY HELMET 1 Pc ACE HARDWARE ₱259.00 1 Pc WILCON DEPOT ₱562.00
RAIN COAT 1 Pc ACE HARDWARE ₱899.00 1 Pc WILCON DEPOT ₱399.00
RESPIRATOR 1 Pc ACE HARDWARE ₱80.00 1 Pc WILCON DEPOT ₱99.00
B. SAFETY AND HEALTH PERSONNEL
SAFETY OFFICER PER MONTH JTL LINK BUILDERS ₱20,000.00 PER MONTH LGG CONSTRUCTION ₱25,000.00
FIRST AIDER PER DAY JTL LINK BUILDERS ₱600.00 PER DAY LGG CONSTRUCTION ₱700.00
B. SAFETY SIGNAGE
SAFETY SIGNAGE SET 1 LS ACE HARDWARE ₱1,034.00 1 LS CITIHARDWARE BINALONAN ₱454.00
IV. SITE PREPARATION
SITE CLEARING 1 LS ₱10,000.00
V. TEMPORARY WORKS
A. TEMPORARY FENCING
G.I. ROUND PIPE (1-1/2"⌀, 6m) 1 Pc CONSUMER GOODS TRADING ₱550.00 1 Pc EAST LUMBER TRADING ₱520.00
G.I. PIPE CLAMP 1 Pc REDNON TRADING ₱46.00 1 Pc CITIHARDWARE VILLASIS ₱40.00
TARPAULIN 1m ACE HARDWARE ₱115.00 1m REDNON TRADING ₱60.00
G.I. TIE WIRE #16 1 Kg WCO TRADING ₱85.00 1 Kg EAST LUMBER TRADING ₱75.00
VI. TESTING AND INSPECTIONS
CONCRETE TESTING PER SAMPLE E.B. TESTING CENTER, INC. ₱1,090.00 PER SAMPLE DPWH ₱1,260.00
INCLUSION: INCLUSION:
COMPRESSIVE STRENGTH TEST COMPRESSIVE STRENGTH
FLEXURAL STRENGTH TEST FLEXURAL STRENGTH
CONCRETE HOLLOW BLOCKS SLUMP TEST
AIR CONTENT
UNIT WEIGHT
VII. PERMITS AND APPROVAL
BUILDING PERMIT
ZONING PERMIT
OCCUPANCY PERMIT
VIII. INSURANCE AND BONDS
CONSTRUCTION BONDS
INSURANCE
IX. SURVEYING AND LAYOUT
F.K SALDIVAR LAND SURVEYING GEODETIC ENGINEERS OF THE
LAND SURVEY 1 LOT ₱20,000.00 1 LOT PHILIPPINES, INC. PANGASINAN ₱20,000.00
SERVICES
CHAPTER

INCLUSION: INCLUSION:
SURVEY TEAM SURVEY TEAM
INSTRUMENT MAN INSTRUMENT MAN
TWO SURVEY AIDS TWO SURVEY AIDS
MOBILIZATION / DEMOBILIZATION MOBILIZATION / DEMOBILIZATION

PREPARED BY: CONFORME:

CRISTOBAL, HENRIETTE MAY ENGR. MELANIE ROSE P. PASCUA


QS Student - BSCE 3A CE Department Instructor

TABOR, CLAIRE
QS Student - BSCE 3A
GENERAL REQUIREMENTS
I. MOBILIZATION / DEMOBILIZATION
SPECIFICATION QTY DAYS REQUIRED RATE (PER DAY) AMOUNT
MINI DUMP TRUCK 1 2 ₱6,000.00 ₱12,000.00
BOOM TRUCK 1 2 ₱10,000.00 ₱20,000.00
TOTAL = ₱32,000.00

II. TEMPORARY FACILITIES


SPECIFICATION QTY UNIT COST AMOUNT
G.I. CORRUGATED COLORED SHEET (0.4mm THK x 4' x 10') 14 ₱506.00 ₱7,084.00
G.I. TIE WIRE #16 10 ₱85.00 ₱850.00
MARINE PLYWOOD (3/4" THK 4' x 8') 8 ₱990.00 ₱7,920.00
MARINE PLYWOOD (1/4" THK 4' x 8') 10 ₱320.00 ₱3,200.00
ORDINARY PLYWOOD (1/4'' THK 4' X 8') 12 ₱285.00 ₱3,420.00
ORDINARY PLYWOOD (5mm THK,1220mm x 2440mm) 16 ₱581.00 ₱9,296.00
COCO LUMBER (2" x 2" x 10') 10 ₱130.00 ₱1,300.00
COCO LUMBER (2" x 4" x 10') 8 ₱267.00 ₱2,136.00
COMMON NAILS (3") 6 ₱65.00 ₱390.00
COMMON NAILS (2") 6 ₱65.00 ₱390.00
FLUORESCENT TUBE 6 ₱319.00 ₱1,914.00
MONOBLOCK 4 ₱410.00 ₱1,640.00
ELECTRIC FAN 4 ₱1,200.00 ₱4,800.00
ELECTRICITY BILL 6 ₱2,000.00 ₱12,000.00
WATER BILL 6 ₱1,000.00 ₱6,000.00
WATER CLOSET 1 ₱1,650.00 ₱1,650.00
PVC HOSE BIBB (1/2") 1 ₱30.00 ₱30.00
PIPES AND FITTINGS 1 ₱1,200.00 ₱1,200.00

TOTAL = ₱65,220.00
III. SAFETY AND HEALTH
SPECIFICATION QTY UNIT COST AMOUNT
SAFETY SHOES - ₱1,299.00 -
SAFETY VEST - ₱234.00 -
SAFETY GLOVES - ₱38.00 -
ELECTRIC RES. GLOVES - ₱369.00 -
SAFETY BOOTS - ₱500.00 -
SAFETY GLASSES - ₱139.00 -
SAFETY GOGGLES - ₱247.00 -
SAFETY HELMET - ₱562.00 -
RAIN COAT - ₱899.00 -
RESPIRATOR - ₱99.00 -
SAFETY SIGNAGE SET 1 ₱1,034.00 ₱1,034.00
FIRST AID KIT BOX 1 ₱1,049.00 ₱1,049.00
MEDICINE & OTHER KITS 1 ₱500.00 ₱500.00

SPECIFICATION QTY DAYS REQUIRED RATE (PER DAY) AMOUNT


SAFETY OFFICER 1 - ₱833.33 -
FIRST AIDER 1 - ₱700.00 -

TOTAL =

IV. SITE PREPARATION


SPECIFICATION QTY UNIT COST AMOUNT
SITE CLEARING 1 ₱10,000.00 ₱10,000.00
TOTAL = ₱10,000.00

V. TEMPORARY WORKS
SPECIFICATION QTY UNIT COST AMOUNT
G.I. ROUND PIPE (1-1/2"⌀, 6m) 16 ₱550.00 ₱8,800.00
G.I. PIPE CLAMP 18 ₱46.00 ₱828.00
TARPAULIN 36 ₱115.00 ₱4,140.00
G.I. TIE WIRE #16 6 ₱85.00 ₱510.00
TOTAL = ₱14,278.00

VI. TESTING AND INSPECTIONS


SPECIFICATION QTY UNIT COST AMOUNT
CONCRETE TESTING
INCLUSION:
COMPRESSIVE STRENGTH 2 ₱180.00 ₱360.00
FLEXURAL STRENGTH 2 ₱210.00 ₱420.00
SLUMP TEST 2 ₱290.00 ₱580.00
AIR CONTENT 2 ₱290.00 ₱580.00
UNIT WEIGHT 2 ₱290.00 ₱580.00
TOTAL = ₱2,520.00

VII. PERMITS AND APPROVAL


SPECIFICATION QTY UNIT COST AMOUNT
BUILDING PERMIT 1 - -
ZONING PERMIT 1 - -
OCCUPANCY PERMIT 1 - -
TOTAL =

VIII. INSURANCE AND BONDS


SPECIFICATION QTY UNIT COST AMOUNT
CONSTRUCTION BONDS 1 - -
INSURANCE 1 - -
TOTAL =

IX. SURVEYING AND LAYOUT


SPECIFICATION QTY UNIT COST AMOUNT
LAND SURVEY
INCLUSION:
SURVEY TEAM
1 ₱20,000.00 ₱20,000.00
1 ₱20,000.00 ₱20,000.00
INSTRUMENT MAN
TWO SURVEY AIDS
MOBILIZATION / DEMOBILIZATION
TOTAL = ₱20,000.00

GENERAL REQUIREMENTS SUB-TOTAL ₱144,018.00

NOTE: THE FOLLOWING ARE NOT INCLUDED


SAFETY AND HEALTH
PERMITS AND APPROVAL
INSURANCE AND BONDS
PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING

EARTHWORKS

I. EXCAVATION WORKS

FOR FOOTING COLUMN

LEGEND QUANTITY LENGTH


F1-C1 15 1.45
TOTAL VOLUME FOR EXCAVATION OF FOOTING C

FOR FOOTING TIE BEAM

FLOOR PLAN
TOTAL HORIZONTAL DIMENSION 8.95
TOTAL VERTICAL DIMENSION 15.45
TOTAL FLOOR AREA 138.2775

LINE LENGTH
A 5.625
A' 4.825
B 7.3
C 5.375
D 13.85
1 4.45
2 8.15
4 4.25
5 3.5
6 3.45
TOTAL LENGTH OF FOOTING TIE BEAM:
TOTAL LENGTH (m) WIDTH (m) DEPTH (m)
60.775 0.25 0.5
TOTAL VOLUME FOR FOOTING TIE BEAM:

FOR WALL FOOTING

LENGTH TOTAL LENGTH FOR WALL F


LINE A' 1.4365
3.2625
LINE B' 1.826
TOTAL LENGTH (m) WIDTH (m) DEPTH (m)
3.2625 0.3 1.6
TOTAL VOLUME FOR WALL FOOTING:

FOR SEPTIC TANK

LENGTH (m) WIDTH (m) DEPTH (m)


4.4 1.8 2.1

TOTAL EXCAVATION VOLUME

II. SOIL POISONING


FOR FOOTING COLUMN

LEGEND QUANTITY LENGTH


F1-C1 15 1.45
TOTAL AREA OF SOIL POISONING FOR FOOTING-C

FOR FOOTING TIE BEAM

TOTAL LENGTH OF FOOTING TIE BEAM:

TOTAL LENGTH (m) WIDTH (m) DEPTH (m)


60.775 0.25 0.45
TOTAL AREA OF SOIL POISINING FOR FOOTING TIE BEAM:

FOR WALL FOOTING

TOTAL LENGTH (m) WIDTH (m) DEPTH (m)


3.2625 0.3 0.7
TOTAL AREA OF SOIL POISONING FOR WALL FOOTING:

FOR SLAB ON GRADE

LENGTH WIDTH DEPTH


15.45 8.95 0.1
TOTAL AREA OF SOIL POISONING FOR SOG:

TOTAL AREA FOR SOIL POISONING :

III. GRAVEL BEDDING

NOTE: CONSIDER 10% WASTAGE

FOR FOOTING COLUMN

LEGEND QUANTITY LENGTH


F1-C1 15 1.45
TOTAL VOLUME OF GRAVEL BEDDING FOR FOOTING-C

FOR FOOTING TIE BEAM


TOTAL LENGTH OF FOOTING TIE BEAM:

TOTAL LENGTH (m) WIDTH (m) DEPTH (m)


60.775 0.25 0.1
TOTAL VOLUME OF GRAVEL BEDDING FOR FOOTING TIE BEAM:

FOR WALL FOOTING

TOTAL LENGTH (m) WIDTH (m) DEPTH (m)


60.775 0.3 0.1
TOTAL VOLUME OF GRAVEL BEDDING FOR WALL FOOTING:

FOR SLAB ON GRADE

AREA WIDTH VOLUME


141.37 0.1 14.14
TOTAL VOLUME OF GRAVEL BEDDING FOR SLAB ON GRADE:

TOTAL RAW VOLUME FOR GRAVEL BEDDING


TOTAL VOLUME FOR GRAVEL B

IV. BACKFILLING

NOTES: 1. SUBTRACT THE GRAVEL BEDDING OF SOG TO THE RAW TOTAL OF GRAV
2. CONSIDER 10% WASTAGE AND 30% COMPACTION

TOTAL RAW VOLUME FOR GRAVEL BEDDING

TYPE QUANTITY LENGTH


F1 15
C1 15

TOTAL VOLUME OC
TOTAL VOLUME OF BACKFIL
TOTAL VOLUME OF BACKFILL (CONSIDERING WASTAGE AND COMPA

V. FILLING

VOLUME OF SOIL RE

VOLUME TO FILL

LENGTH WIDTH
15.45 8.95
TOTAL VOLUME FOR FILLING:

TOTAL VOLUME FOR FILLING CONSIDERING WASTAGE AND COMP


TOTAL VOLUME TO BE FILLED WI

PREPARED BY:

CRISTOBAL, HENRIETTE MAY


QS Student - BSCE 3A

TABOR, CLAIRE
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
N

THWORKS

TING COLUMN

WIDTH DEPTH VOLUME(m^2)


1.45 2.9 91.45875
E FOR EXCAVATION OF FOOTING COLUMN: 91.45875

TING TIE BEAM

OR PLAN
COLUMN FTB
LENGTH 0.25 0.25
WIDTH 0.4 0.35
60.775
TOTAL VOLUME (m³)
7.597
7.597

LL FOOTING

TOTAL LENGTH FOR WALL FOOTING


3.2625
TOTAL VOLUME (m³)
1.566
1.566

EPTIC TANK

TOTAL VOLUME (m³)


16.632

109.657
TING COLUMN

WIDTH DEPTH AREA(m^2)


1.45 1.9 167.4025
F SOIL POISONING FOR FOOTING-COLUMN 167.4025

TING TIE BEAM

60.775

AREA (m^2)
69.891
69.891

LL FOOTING

AREA(m^2)
2.66
2.657

AB ON GRADE

AREA (SURFACE)
141.37
141.37

381.319

TING COLUMN

WIDTH DEPTH VOLUME(m^2)


1.45 0.2 19.5025
GRAVEL BEDDING FOR FOOTING-COLUMN 21.45275

TING TIE BEAM


60.775

VOLUME
27.349
30.084

LL FOOTING

VOLUME
36.57
40.222

AB ON GRADE

15.55

VEL BEDDING (NOT CONSIDERING WASTAGE): 97.55


TOTAL VOLUME FOR GRAVEL BEDDING: 107.31

F SOG TO THE RAW TOTAL OF GRAVEL BEDDING


OMPACTION

TOTAL EXCAVATION VOLUME 109.657


VEL BEDDING (NOT CONSIDERING WASTAGE): 97.55

WIDTH DEPTH VOLUME


15
15.00

TOTAL VOLUME OCCUPIED: 30.00


TOTAL VOLUME OF BACKFILL (RAW): 79.66
ONSIDERING WASTAGE AND COMPACTION): 113.909

VOLUME OF SOIL REMAINED: (4.25)

DEPTH VOLUME
0.1 141.37
TAL VOLUME FOR FILLING: 155.50

CONSIDERING WASTAGE AND COMPACTION: 222.37


TOTAL VOLUME TO BE FILLED WITH SOIL: 226.62
PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING

ITEM OF WORK: EARTHWORKS AS OF: MARCH, 2024

SPECIFICATION UNIT Supplier 1 Cost UNIT

I. EXCAVATION WORKS
BACKHOE EXCAVATOR (RENT)
INCLUSIONS: BACKHOE, LABOR, GASOLINE PER DAY HEAVY EQUIPMENT RENTALS 15000 PER DAY

INCLUSIONS: TRACKED EXCAVATOR PER DAY MHV BUILDERS ₱2,000.00 PER DAY

UNSKILLED WORKERS PER DAY EPO CONSTRUCTION ₱650.00 PER DAY


SPADE PER PIECE ACE HARDWARE ₱389.00 PER PIECE
SHOVEL PER PIECE ACE HARDWARE ₱389.00 PER PIECE
PICK AXE PER PIECE BNNC TRADING ₱395.00 PER PIECE
WHEEL BARROW PER PIECE GALBA DEPOT ₱1,778.00 PER PIECE

II. SOIL POISONING


SOLIGNUM SOILGUARD PER GALLON WILCON DEPOT ₱5,475.00 PER GALLON
SPRAYER (capacity=5 liters) PER PIECE ACE HARDWARE ₱1,099.00 PER PIECE
UNSKILLED WORKER PER DAY EPO CONSTRUCTION ₱650.00 PER DAY

III. GRAVEL BEDDING


GRAVEL
INCLUSION:
PER cu.m NAVAL CONSTRUCTION SUPPLY ₱1,600.00 PER cu.m
GRAVEL
DRIVER/OPERATOR
UNSKILLED WORKER PER DAY EPO CONSTRUCTION ₱650.00 PER DAY

IV. BACKFILL/FILLING
SOIL (LOOSE)
INCLUSION:
4 cu.m PER LOAD TOMAS CONSTRUCTION TRADING ₱2,000.00 2.5 cu.m PER LOAD
SOIL (LOOSE)
DRIVER/OPERATOR
SKILLED WORKER PER DAY EPO CONSTRUCTION ₱1,500.00 PER DAY
UNSKILLED WORKER PER DAY EPO CONSTRUCTION ₱650.00 PER DAY
PREPARED BY: CONFORME:

CRISTOBAL, HENRIETTE MAY


QS Student - BSCE 3A

TABOR, CLAIRE
QS Student - BSCE 3A
I. EXCAVATIO
24
SPECIFICATION NO. OF UNIT
BACKHOE EXCAVATOR (RENT) 1
TRACKED EXCAVATOR (RENT) 2
Supplier 2 Cost SPADE 5
SHOVEL 10
WHEEL BARROW 5
PICK AXE 4

MAIR CONSTRUCTION 12500

LABOR C
JMS HEAVY EQUIPMENT RENTALS₱1,700.00 SPECIFICATION NO. OF UNIT
UNSKILLED WORKERS (10 DAYS) 10
SKILLED WORKERS (5 DAYS) 2
PRAGMATIC ₱570.00 DRIVER (3 DAYS) 1
WILCON ₱420.00
WILCON ₱450.00
WILCON ₱790.00 BACKFILLING
WILCON ₱7,708.00 SPECIFICATION NO. OF UNIT
SOIL 53

MEGA HARDWARE ₱4,800.00 BREAKDOWN OF COMPUTATIO


BUILDMATE ONLINE DEPOT ₱750.00 SPECIFICATION cu.m per LOAD
PRAGMATIC ₱570.00 SOIL 4

GPC CONSTRUCTION ₱1,000.00

PRAGMATIC ₱570.00

GPC CONSTRUCTION ₱1,200.00

PRAGMATIC ₱1,200.00
PRAGMATIC ₱570.00
CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
I. EXCAVATION WORKS
NO. OF UNIT COST PER UNIT AMOUNT

1 ₱15,000.00 ₱15,000.00
2 ₱2,000.00 ₱4,000.00
5 ₱420.00 ₱2,100.00
10 ₱450.00 ₱4,500.00
5 ₱7,708.00 ₱38,540.00
4 ₱790.00 ₱3,160.00

TOTAL AMOUNT ₱67,300.00

LABOR COST
NO. OF UNIT COST PER UNIT AMOUNT

10 ₱650.00 ₱65,000.00
2 ₱1,500.00 ₱30,000.00
1 ₱1,500.00 ₱45,000.00

TOTAL AMOUNT ₱140,000.00

BACKFILLING/FILLING
NO. OF UNIT COST PER UNIT AMOUNT
53 ₱2,000.00 ₱106,000.00

TOTAL AMOUNT ₱106,000.00


BREAKDOWN OF COMPUTATION FOR FILLING MATERIAL
cu.m per LOAD VOLUME OF FILLING NO. OF UNIT NEEDED
4 210.94 52.73500000

TOTAL AMOUNT ₱173,300.00


PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING

I. CONCRETE WORKS

A. FOOTING (CLASS C)

TOTAL VOLUME BAGS OF CEMENT


SYMBOL VOLUME (m3) QUANTITY SAND (m3) GRAVEL (m3)
(m3) (40 kg)
F1 9.461 15 9.461 57 4.74 9.47

B. COLUMN (CLASS C)

TOTAL VOLUME BAGS OF CEMENT


SYMBOL VOLUME (m3) QUANTITY SAND (m3) GRAVEL (m3)
(m3) (40 kg)
C1 13.14 15 13.14 79 6.57 13.14

C. WALL FOOTING (CLASS C)


TOTAL VOLUME BAGS OF CEMENT
SYMBOL AREA (m2) LENGTH (m) SAND (m3) GRAVEL (m3)
(m3) (40 kg)
WF 0.6525 4 0.33 0.66

D. BEAMS (CLASS C)
LENGTH (m) VOLUME (m3) BAGS OF CEMENT
SYMBOL SAND (m3) GRAVEL (m3)
(40 kg)
FTB 60.775 5.318 99 8.19 16.38
2B1 19.63 1.963
2B2 31.25 3.125
2B3 20.625 2.063
RB 44.7 3.91
TOTAL VOLUME OF BEAMS (m3) 16.38
E. SLABS (CLASS C)
1. SLAB ON GRADE
BAGS OF CEMENT
AREA (m2) VOLUME (m3) (40 kg) SAND (m3) GRAVEL (m3)
141.37 17.67 107 8.84 17.67
2.. SECOND FLOOR SLAB
BAGS OF CEMENT
AREA (m2) VOLUME (m3) (40 kg) SAND (m3) GRAVEL (m3)
62.293 7.79 47 3.9 7.79

F. STAIRS (CLASS C)
1. WAIST SLAB
HORIZONTAL
TOTAL HEIGHT OF LENGTH OF ONE
LENGTH OF STEPS THICKNESS (m) WIDTH (m) VOLUME OF WAIST SLAB (m3)
STEPS (m) WAIST SLAB (m)
(m)
4.365 0.125 4.37 1.78 1.8 1.75
2. RISER/THREAD
AREA (m2) WIDTH (m) VOLUME OF RISER/THREAD (m 3)
1.93 0.2 1.92
3. LANDING
LENGTH (m) WIDTH (m) THICKNESS (m) VOLUME OF LANDING (m3)
2.5 0.6 0.15 1.5
BAGS OF CEMENT
(40 kg) SAND (m ) 3
GRAVEL (m3)
TOTAL VOLUME OF STAIRS (m3) 5.17
32 2.59 5.17

SUMMARY ON CONCRETE WORKS


TOTAL BAGS OF CEMENT (40 kg) 425
TOAL VOLUME OF SAND (m3) 35.16
TOTAL VOLUME OF GRAVEL (m3) 70.28

III. REINFORCING STEEL BAR (RSB) WORKS

A. FOOTING
LENGTH OF CUTBARS IN ONE
CUTBARS PER FOOTING QUANTITY TOTAL PIECES
CUTBARS SIDE OF FOOTING
1.7 8 16 15 240
CALCULATING WASTAGE
NO. OF CUTBARS / STEEL BAR THAT REQ'D NO. OF TOTAL WASTAGE
SIZES (m) NO. OF STEEL BAR
CAN BE OBTAINED STEEL BAR (m)
6 3.53 80 80 72
7.5 4.42 60 60 42
9 5.3 48 48 24
10.5 6.18 40 40 12
12 7.06 34.29 35 11.95
13.5 7.95 34.29 35 64.45
STEELS TO BE ORDERED
TOTAL WASTAGE
LEAST WASTAGE NO. OF 16mm Ø STEEL BARS TO BE
SIZES (m) SIZE OF STEEL BAR TO BE USED (m)
(m) ORDERED (pcs)
(m)
6 72
7.5 42
9 24
11.95 12 35
10.5 12
12 11.95
13.5 64.45
TIE WIRE
TOTAL LENGTH OF
NO. OF TIES LENGTH OF TIE (m) LENGTH OF 1kg NO. 16 G.I. WIRE (m) TOTAL MASS OF NO. 16 G.I. WIRE (kg)
TIE (m)
960 0.3 1 53 0.02

SUMMARY ON FOOTING
QUANTITY (pcs) RSB LENGTH (m)
0 6
0 7.5
TOTAL NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
0 9
0 10.5
0 12
0 13.5
TOTAL MASS OF NO. 16 G.I. WIRE (kg) 0.02

B. WALL FOOTING (NO CUT BARS)


1. CUT BARS
LENGTH OF ONE CUT BAR 0.7
TOTAL QUANTITY OF WALL FOOTING
14
CALCULATING WASTAGE
SIZES (m) LENGTH OF ONE BAR NO. OF STEEL BAR
6 0.7 8.57
7.5 0.7 10.71
USE 10.5 M LONG STEEL BAR
9 0.7 12.86
10.5 0.7 15.00
12 0.7 17.14
13.5 0.7 19.29
DIVIDE TOTAL CUT BARS FOR WF AT BARS
1 1 PC. OF 10 MM X 10.5M GRADE 40 RSB
3. TIE WIRE
TOTAL LENGTH OF
NO. OF TIES LENGTH OF TIE (m) LENGTH OF 1kg NO. 16 G.I. WIRE (m) TOTAL MASS OF NO. 16 G.I. WIRE (kg)
TIE (m)
42 0.25 11 53 0.21

SUMMARY ON WALL FOOTING


TOTAL NO. OF BARS (pcs) 1

TOTAL MASS OF NO. 16 G.I. WIRE (kg) 0.21

C. COLUMNS
I. MAIN REINFORCEMENT (DIRECT COUNTING METHOD)
SYMBOL LENGTH (m) RSB LENGTH (m) NO. OF BARS (pcs) NO. OF COLUMNS TOTAL NO. OF BARS (pcs)
C1 8.5 9 8 15 120
QUANTITY (pcs) RSB LENGTH (m)
NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
120 9

II. LATERAL TIES (DIRECT COUNTING METHOD)


LENGTH OF ONE NO. OF LATERAL TIES IN ONE QUANTITY OF C1 TOTAL NO. OF
SPAN (m) TOTAL (pcs)
STIRRUP (m) COLUMN (pcs) (pcs) STIRRUPS (pcs)
1.8 25 15 375
4.25 35 15 525
1.4 1669
3 38 11 418
1.35 39 9 351
CALCULATING WASTAGE

NO. OF CUTBARS / STEEL BAR THAT REQ'D NO. OF TOTAL WASTAGE


SIZES (m) NO. OF STEEL BAR
CAN BE OBTAINED STEEL BAR (m)

6 4.29 417.25 418 171.4


7.5 5.36 333.80 334 168.4
9 6.43 278.17 279 174.4
10.5 7.5 238.43 239 172.9
12 8.58 208.63 209 171.4
13.5 9.65 185.45 186 171.4

STEELS BARS TO BE ORDERED

TOTAL WASTAGE
LEAST WASTAGE NO. OF 10mm Ø STEEL BARS TO BE
SIZES (m) SIZE OF STEEL BAR TO BE USED (m)
(m) ORDERED (pcs)
(m)

6 171.40
7.5 168.40
9 174.40
168.40 7.5 334
168.40 7.5 334
10.5 172.90
12 171.40
13.5 171.40
III. TIE WIRE
NO. OF MAIN BARS TOTAL NO. OF LENGTH OF TIE TOTAL LENGTH OF
NO. OF TIES (pcs) MASS OF NO. 16 G.I. WIRE (kg)
(pcs) STIRRUPS (pcs) (m) TIE (m)
8 1669 13352 0.3 4006 75.59

SUMMARY ON COLUMNS

QUANTITY (pcs) RSB LENGTH (m)

0 6
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs) 334 7.5
0 9
0 10.5
0 12
0 13.5

QUANTITY (pcs) RSB LENGTH (m)

TOTAL NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs) 0 6


0 7.5
120 9
0 10.5
0 12
0 13.5

TOTAL MASS OF NO. 16 G.I. WIRE (kg) 75.59

D. BEAMS
I. MAIN REINFORCEMENT (DIRECT COUNTING METHOD)
1. FTB
COLUMN GRID LENGTH (m) RSB LENGTH (m) NO. OF BARS (pcs)
A 5.625 6 7
A' 4.825 6 6
B 7.3 7.5 9
5.375 6 7
C
13.85 9 15
D
1 4.45 6 6
2 8.15 9 10
4 4.25 7.5 6
5 3.5 7.5 6
6 3.45 7.5 6
QUANTITY (pcs) RSB LENGTH (m)
NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs) 26 6
27 7.5
25 9
2. 2ND FLOOR BEAMS
COLUMN GRID LENGTH (m) RSB LENGTH (m) NO. OF BARS (pcs)
B-1 1.963 6 2
B-2 3.125 6 4
B-3 2.0625 6 3
QUANTITY (pcs) RSB LENGTH (m)
NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
9 6

3. RB

COLUMN GRID LENGTH (m) RSB LENGTH (m) NO. OF BARS (pcs)

A 3.65 6 4
B 4.65 6 5
C 3.65 6 4
D 8.5 9 8
2 8.15 9 8
3 8.15 9 8
4 0.8 6 1
5 7.15 7.5 1
QUANTITY (pcs) RSB LENGTH (m)
NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs) 14 6
1 7.5
24 9
II. STIRRUPS (DIRECT COUNTING METHOD)
1. FTB
LENGTH OF ONE QUANTITY OF FTB TOTAL NO. OF
SPAN (m) NO. OF STIRRUPS IN ONE BEAM (pcs) TOTAL (pcs)
STIRRUP (m) (pcs) STIRRUPS (pcs)
1.8 25 15 375
4.25 35 15 525
1.4 1669
3 38 11 418
1.35 39 9 351
NO. OF CUTBARS / STEEL BAR THAT REQ'D NO. OF TOTAL WASTAGE
SIZES (m) NO. OF STEEL BAR
CAN BE OBTAINED STEEL BAR (m)
6 4.229 417.25 418 171.4
7.5 5.36 333.80 334 168.4
9 6.43 278.17 279 174.4
10.5 7.5 238.43 239 172.9
12 8.58 208.63 209 171.4
13.5 9.65 185.45 186 174.4
STEELS BARS TO BE ORDERED
TOTAL WASTAGE
LEAST WASTAGE NO. OF 10mm Ø STEEL BARS TO BE
SIZES (m) SIZE OF STEEL BAR TO BE USED (m)
(m) ORDERED (pcs)
(m)
6 171.40
7.5 168.40
9 174.40
168.40 7.5 334
10.5 172.90
12 171.40
13.5 174.40
2ND FLOOR BEAMS
LENGTH OF ONE QUANTITY OF FTB TOTAL NO. OF
BEAMS NO. OF STIRRUPS IN ONE BEAM (pcs) TOTAL (pcs)
STIRRUP (m) (pcs) STIRRUPS (pcs)
B-1 1.96 24 2 48
B-2 3.13 30 4 120 249
B-3 2.06 27 3 81

CALCULATING WASTAGE
NO. OF CUTBARS / STEEL BAR THAT REQ'D NO. OF TOTAL WASTAGE
SIZES (m) NO. OF STEEL BAR
CAN BE OBTAINED STEEL BAR (m)
6 4.29 62.25 63 49.32
7.5 5.36 49.80 50 46.32
9 6.43 41.50 42 49.32
10.5 7.5 35.57 36 49.34
12 8.58 31.13 32 10.03
13.5 9.65 27.67 28 12.33
STEELS BARS TO BE ORDERED
TOTAL WASTAGE
LEAST WASTAGE NO. OF 10mm Ø STEEL BARS TO BE
SIZES (m) SIZE OF STEEL BAR TO BE USED (m)
(m) ORDERED (pcs)
(m)
6 49.32
7.5 46.32

49.32
10.03 12 32

9
10.03 12 32

10.5 49.34
12 10.03
13.5 12.33

RB
LENGTH OF ONE QUANTITY OF FTB TOTAL NO. OF
SPAN (m) NO. OF STIRRUPS IN ONE BEAM (pcs) TOTAL (pcs)
STIRRUP (m) (pcs) STIRRUPS (pcs)
3.65 30 4 120
8.15 60 8 480
8.15 60 8 480 1140
1.4
0.8 10 1 10
7.15 50 1 50

CALCULATING WASTAGE
NO. OF CUTBARS / STEEL BAR THAT REQ'D NO. OF TOTAL WASTAGE
SIZES (m) NO. OF STEEL BAR
CAN BE OBTAINED STEEL BAR (m)
6 4.29 285.00 285 114
7.5 5.36 228.00 228 114
9 6.43 190.00 190 114
10.5 7.5 162.86 163 115.5
12 8.58 142.50 143 120
13.5 9.65 126.67 127 118.5
STEELS BARS TO BE ORDERED
TOTAL WASTAGE
LEAST WASTAGE NO. OF 10mm Ø STEEL BARS TO BE
SIZES (m) SIZE OF STEEL BAR TO BE USED (m)
(m) (m) ORDERED (pcs)
6 114.00
7.5 114.00
9 114.00
114.00 6 285
10.5 115.50
12 120.00
13.5 118.50

III. TIE WIRE


1. FTB
NO. OF MAIN BARS TOTAL NO. OF LENGTH OF TIE TOTAL LENGTH OF
NO. OF TIES (pcs) MASS OF NO. 16 G.I. WIRE (kg)
(pcs) STIRRUPS (pcs) (m) TIE (m)
6 1669 10014 0.3 3005 56.7
2. BEAMS
NO. OF MAIN BARS TOTAL NO. OF LENGTH OF TIE TOTAL LENGTH OF
NO. OF TIES (pcs) MASS OF NO. 16 G.I. WIRE (kg)
(pcs) STIRRUPS (pcs) (m) TIE (m)
8 249 1992 0.3 598 11.29
3. RB
NO. OF MAIN BARS TOTAL NO. OF LENGTH OF TIE TOTAL LENGTH OF
NO. OF TIES (pcs) MASS OF NO. 16 G.I. WIRE (kg)
(pcs) STIRRUPS (pcs) (m) TIE (m)
6 1140 6840 0.3 2052 38.72

SUMMARY ON BEAMS
QUANTITY (pcs) RSB LENGTH (m)
49 6
28 7.5
TOTAL NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
169 9
0 10.5
35 12
0 13.5
QUANTITY (pcs) RSB LENGTH (m)
285 6
Err:504 7.5
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs)
Err:504 9
1 10.5
32 12
Err:504 13.5
TOTAL MASS OF NO. 16 G.I. WIRE (kg) 182.53
E. SLABS
SLAB ON GRADE
IN 13 m SPAN
LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES
5.23 5 0.3 18

CALCULATING WASTAGE
SIZES NO. OF CUTBARS / STEEL BAR THAT CAN NO. OF STEEL REQ'D NO. OF TOTAL WASTAGE
(m) BE OBTAINED BAR STEEL BAR (m)
6 1.15 18 18 13.86
7.5 1.44 18 18 40.86
9 1.73 18 18 67.86
10.5 2.01 9 9 0.36
12 2.3 9 9 13.86
13.5 2.59 9 9 27.36
STEELS BARS TO BE ORDERED
SIZES TOTAL WASTAGE LEAST WASTAGE SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
(m) (m) (m) (m) ORDERED (pcs)
6 13.86
7.5 40.86
9 67.86
0.36 10.5 9
10.5 0.36
12 13.86
13.5 27.36

LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES


4.3 4 0.3 15

CALCULATING WASTAGE
(m) (m) (m) (m) ORDERED (pcs)
6 13.86
7.5 40.86
9 67.86
0.36 10.5 9
10.5 0.36
12 13.86
13.5 27.36

LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES


4.3 4 0.3 15

CALCULATING WASTAGE
SIZES NO. OF CUTBARS / STEEL BAR THAT CAN NO. OF STEEL REQ'D NO. OF TOTAL WASTAGE
(m) BE OBTAINED BAR STEEL BAR (m)
6 1.4 15 15 25.5
7.5 1.75 15 15 48
9 2.1 7.5 8 7.5
10.5 2.45 7.5 8 19.5
12 2.8 7.5 8 31.5
13.5 3.14 5 5 3
STEELS BARS TO BE ORDERED
SIZES TOTAL WASTAGE LEAST WASTAGE SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
(m) (m) (m) (m) ORDERED (pcs)
6 25.5
7.5 48
9 7.5
3 13.5 5
10.5 19.5
12 31.5
13.5 3

IN 6 m SPAN
LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES
13.36 12 0.3 41

SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE


NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs) (m) ORDERED (pcs)
9 41
USING 9m, THE REMAINING CUT BAR IS = 4.36
CALCULATING WASTAGE
SIZES NO. OF CUTBARS / STEEL BAR THAT CAN NO. OF STEEL REQ'D NO. OF TOTAL WASTAGE
6 1.38 41 41 67.24
7.5 1.73 41 41 128.74
9 2.07 20.5 21 10.24
10.5 2.41 20.5 21 41.74
12 2.76 20.5 21 73.24
13.5 3.1 13.667 14 10.24
STEELS BARS TO BE ORDERED
SIZES TOTAL WASTAGE LEAST WASTAGE SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
(m) (m) (m) (m) ORDERED (pcs)
6 67.24
7.5 128.74
9 10.24
10.24 9 21
10.5 41.74
12 73.24
13.5 10.24

LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES


STEELS BARS TO BE ORDERED
SIZES TOTAL WASTAGE LEAST WASTAGE SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
(m) (m) (m) (m) ORDERED (pcs)
6 67.24
7.5 128.74
9 10.24
10.24 9 21
10.5 41.74
12 73.24
13.5 10.24

LENGTH OF CUTBARS LENGTH COVERED SPACING TOTAL PIECES


2.43 1 0.3 10

CALCULATING WASTAGE
SIZES NO. OF CUTBARS / STEEL BAR THAT CAN NO. OF STEEL REQ'D NO. OF TOTAL WASTAGE
6 2.47 5 5 5.7
7.5 3.09 3.334 4 5.7
9 3.71 3.334 4 11.7
10.5 4.33 2.5 3 7.2
12 4.94 2.5 3 11.7
13.5 5.56 2 2 2.7
STEELS BARS TO BE ORDERED
SIZES TOTAL WASTAGE LEAST WASTAGE SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
(m) (m) (m) (m) ORDERED (pcs)
6 5.7
7.5 5.7
9 11.7
2.7 13.5 2
10.5 7.2
12 11.7
13.5 2.7

TIE WIRE ON SLAB ON GRADE


TOTAL LENGTH OF LENGTH OF 1kg NO. 16 G.I. WIRE
NO. OF TIES LENGTH OF TIE (m) TOTAL MASS OF NO. 16 G.I. WIRE (kg)
TIE (m) (m)
1484 0.3 446 53 8.42

SECOND FLOOR SLAB


TOTAL AREA OF SLAB ONE WAY SLAB AREA TWO WAY SLAB AREA SPACING
62.293 13.658 48.635 0.3

SOLVING BY AREA METHOD


SIZE OF STEEL BAR TO BE USED NO. OF 10mm Ø STEEL BARS TO BE
TYPE OF SLAB MULTIPLIER
(m) ORDERED (pcs)
ONE WAY SLAB 1.192 7.5 17
TWO WAY SLAB 2.182 7.5 107

SOLVING BY AREA METHOD


TYPE OF SLAB MULTIPLER MASS OF TIE WIRE (Kg)
ONE WAY SLAB 0.126 1.73
TWO WAY SLAB 2.182 106.13

SUMMARY ON SLABS
QUANTITY (pcs) RSB LENGTH (m)

0 6
124 7.5
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs)
62 9
SOLVING BY AREA METHOD
TYPE OF SLAB MULTIPLER MASS OF TIE WIRE (Kg)
ONE WAY SLAB 0.126 1.73
TWO WAY SLAB 2.182 106.13

SUMMARY ON SLABS
QUANTITY (pcs) RSB LENGTH (m)

0 6
124 7.5
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs)
62 9
9 10.5
0 12
7 13.5
TOTAL MASS OF NO. 16 G.I. WIRE (kg) 116.28

F. STAIRS
USING DIRECT COUNTING METHOD
QUANTITY OF QUANTITY OF
SPECIFICATION TOTAL LENGTH SIZE OF STEEL BAR
CUT BARS STEEL BAR
C1 1.5 5 1 6m x 10mm Ø GRADE 33 RSB
C2 0.6 8 1 6m x 12mm Ø GRADE 33RSB
C3 3.6 7 3 7.5m x 12mm Ø GRADE 33 RSB
C4 5.5 9 3 10.5m x 12mm Ø GRADE 33 RSB
C5 1.2 16 1 10.5 x 12mm Ø GRADE 33 RSB
C6 0.5 60 6 10.5 m x 12mm Ø GRADE 33 RSB
C7 1.3 23 3 10.5m x 10mm Ø GRADE 33 RSB
C8 1.9 6 2 9m x 16mm Ø GRADE 33 RSB

TIE WIRE ON SLAB ON GRADE


TOTAL LENGTH OF
NO. OF TIES LENGTH OF TIE (m) LENGTH OF 1kg NO. 16 G.I. WIRE (m) TOTAL MASS OF NO. 16 G.I. WIRE (kg)
TIE (m)
534 0.3 161 53 3.04

SUMMARY ON STAIRS
QUANTITY (pcs) RSB LENGTH (m)
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs)
1 6

QUANTITY (pcs) RSB LENGTH (m)


1 6
TOTAL NO. OF 12mm Ø STEEL BARS TO BE ORDERED (pcs) 3 7.5

10 10.5
TOTAL NO. OF 12mm Ø STEEL BARS TO BE ORDERED (pcs)

10 10.5

QUANTITY (pcs) RSB LENGTH (m)


TOTAL NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
2 9

TOTAL MASS OF NO. 16 G.I. WIRE (kg) 3.04

SUMMARY ON RSB WORKS


QUANTITY (pcs) RSB LENGTH (m)
#REF! 6
#REF! 7.5
TOTAL NO. OF 10mm Ø STEEL BARS TO BE ORDERED (pcs)
#REF! 9
#REF! 10.5
#REF! 12
#REF! 13.5
QUANTITY (pcs) RSB LENGTH (m)
0 6
1 7.5
TOTAL NO. OF 12mm Ø STEEL BARS TO BE ORDERED (pcs)
0 9
3 10.5
10 12
0 13.5
QUANTITY (pcs) RSB LENGTH (m)
#REF! 6
#REF! 7.5
TOTAL NO. OF 16mm Ø STEEL BARS TO BE ORDERED (pcs)
#REF! 9
#REF! 10.5
#REF! 12
#REF! 13.5
TOTAL MASS OF NO. 16 G.I. WIRE (kg) #REF!

III. FORMWORKS

A. FOOTING
PLYWOODS
PERIMETER AREA QUANTINTY TOTAL AREA AREA OF PLYWOOD PIECES OF PLYWOOD
6 10.8 15 162 2.88 57
LUMBER AND NAILS
MULTIPLIER BOARD FOOT PIECES OF 2"X2"X18' LUMBER MASS OF NAILS
29.67 1691.19 282 50.74

B. COLUMN
PLYWOODS
PERIMETER AREA PCS TOTAL AREA AREA OF PLYWOOD PIECES OF PLYWOOD
1.5 12.91 33 170.88 2.88 60

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X20' LUMBER MASS OF NAILS
29.67 1780.2 268 53.41

D. BEAMS
FOOTING TIE BEAM
PLYWOODS
PERIMETER AREA QUANTINTY TOTAL AREA AREA OF PLYWOOD PIECES OF PLYWOOD
1.05 63.82 1 LOT 63.82 2.88 23

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X16' LUMBER MASS OF NAILS
29.67 682.41 128 20.48

SECOND FLOOR BEAM


PLYWOODS
PIECES OF
SYMBOL PERIMETER AREA QUANTINTY TOTAL AREA AREA OF PLYWOOD
PLYWOOD
BEAM 1.15 8.23 1 LOT 8.23 2.88 3
TOTAL 3

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X10' LUMBER MASS OF NAILS
29.67 89.01 27 2.68

ROOF BEAM
PLYWOODS
PERIMETER AREA PCS TOTAL AREA AREA OF PLYWOOD PIECES OF PLYWOOD
1.05 46.94 1 LOT 46.94 2.88 17

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X10' LUMBER MASS OF NAILS
29.67 504.39 152 15.14
E. SLAB
SLAB ON GRADE
PLYWOODS
AREA AREA OF PLYWOOD PIECES OF PLYWOOD
141.37 2.88 50

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X14' LUMBER MASS OF NAILS
29.67 1483.5 318 44.51

SECOND FLOOR SLAB


PLYWOODS
AREA AREA OF PLYWOOD PIECES OF PLYWOOD
62.293 2.88 22

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X14' LUMBER MASS OF NAILS
29.67 652.74 140 19.59

F. STAIR
PLYWOODS
PIECES OF
WAIST SLAB THREAD RISER LANDING TOTAL AREA AREA OF PLYWOOD
PLYWOOD
0.125 0.2 0.3 2.5 3.125 2.88 2

LUMBER AND NAILS


MULTIPLIER BOARD FOOT PIECES OF 2"X2"X14' LUMBER MASS OF NAILS
29.67 59.34 13 1.79

TOTAL PIECES OF PLYWOOD 234


TOTAL PIECES OF 2"X2"X10' LUMBER 179
TOTAL PIECES OF 2"X2"X14' LUMBER 471
TOTAL PIECES OF 2"X2"X16' LUMBER 128
TOTAL PIECES OF 2"X2"X18' LUMBER 282
TOTAL PIECES OF 2"X2"X20' LUMBER 268
TOTAL MASS OF NAILS (Kg) 208.34

IV. SCAFFOLDINGS

A. STAGING FOR COLUMN


VERTICAL SUPPORT
LONGEST LENGTH QUANTITY TOTAL LENGTH MULTIPLIER BOARD FOOT PIECES OF 2"X3"X12' MASS OF NAILS
4.25 15 63.75 7 446.25 75 13.39
HORIZONTAL SUPPORT
LONGEST LENGTH QUANTITY TOTAL LENGTH MULTIPLIER BOARD FOOT PIECES OF 2"X2"X16' MASS OF NAILS
5.05 15 75.75 21 1338.75 287 40.17

DIAGONAL BRACE
LONGEST LENGTH QUANTITY TOTAL LENGTH MULTIPLIER BOARD FOOT PIECES OF 2"X2"X10' MASS OF NAILS
6.61 15 99.15 11.67 743.97 224 22.32

B. STAGING FOR BEAM


VERTICAL SUPPORT
TOTAL LENGTH MULTIPLIER BOARD FOOT PIECES OF 2"X3"X22' MASS OF NAILS
71.53 6 429.18 40 1.2

HORIZONTAL SUPPORT
TOTAL LENGTH MULTIPLIER BOARD FOOT PIECES OF 2"X2"X20' MASS OF NAILS
71.53 4.67 334.0451 51 1.53

C. STAGING OF SLAB
TOTAL AREA MULTIPLIER BOARD FOOT PIECES OF 2"X3"X20' MASS OF NAILS
203.663 9.1 1853.3333 186 5.58

TOTAL PIECES OF 2"X2"X10' LUMBER 224


TOTAL PIECES OF 2"X3"X12' LUMBER 75
TOTAL PIECES OF 2"X2"X16' LUMBER 287
TOTAL PIECES OF 2"X2"X20 LUMBER 237
TOTAL PIECES OF 2"X3"X22' LUMBER 40
TOTAL MASS OF NAILS (Kg) 84.19

V. STEEL WORKS

TRUSS
I. TRUSS 1
TOTAL LENGTH
SPECIFICATION LENGTH QUANTITY (PCS) TOTAL LENGTH STEEL C - CHANNEL
PER TRUSS
X1 3.65
X2 3.15
X3 0.32
X4 0.53
X5 0.3
X6 0.3
X7 0.5
Y1 0.43 TOTAL PIECES = 45.36 / 10m = 4.536
SAY 5 PIECES USE 5 PCS. OF 2" x 4" x
11.34 4 45.36
1.20 x 10m GALVANIZED STEEL C -
CHANNEL
TOTAL PIECES = 45.36 / 10m = 4.536
SAY 5 PIECES USE 5 PCS. OF 2" x 4" x
Y2 0.46 11.34 4 45.36
1.20 x 10m GALVANIZED STEEL C -
Y3 0.53 CHANNEL
Y4 0.46
Y5 0.33
Y6 0.22
Y7 0.16

II. TRUSS 2
TOTAL LENGTH
SPECIFICATION LENGTH QUANTITY (PCS) TOTAL LENGTH STEEL C - CHANNEL
PER TRUSS
Y8 1.35
Y9 1.32
Y10 1.15
Z1 1.1
Z2 0.62 TOTAL PIECES = 7.21 / 8m = 0.90 SAY
7.21 1 7.21 1PIECE USE 1 PC. OF 2" x 4" x 1.20 x 8m
Z3 0.6 GALVANIZED STEEL C - CHANNEL
Z4 0.34
Z5 0.3
Z6 0.23
Z7 0.2

III.TRUSS 3
TOTAL LENGTH
SPECIFICATION LENGTH QUANTITY (PCS) TOTAL LENGTH STEEL C - CHANNEL
PER TRUSS
Z8 1
Z9 1
Z10 1 TOTAL PIECES = 4.79/ 6m = 0.79 SAY
4.79 1 4.79 1PIECE USE 1 PC. OF 2" x 4" x 1.20 x 6m
X8 1 GALVANIZED STEEL C - CHANNEL
X9 0.47
X10 0.32

C- PURLINS

LENGTH QUANTITY (PCS) TOTAL LENGTH NO. OF PIECES C - PURLINS


10.8 15 162 17 USE 17 PCS. OF 2" x 3" x 1.20 x 10m C - PURLINS

SAG ROD

LENGTH QUANTITY (PCS) TOTAL LENGTH NO. OF PIECES STEEL BAR


10.8 18 194.4 20 USE 20 PCS. OF 10mmØ x 10m SAG ROD
ANGLE BAR CLEATS

NUMBER OF INTERSECTION OF TRUSS AND C - PURLINS TOTAL PIECES OF ANGLE BAR CLEATS
60 USE 60 PIECES OF ANGLE BAR CLEATS

WELDING ROD

WEIGHT OF C -
WEIGHT OF STEEL
PURLINS PER TOTAL WEIGHT MULTIPLIER TOTAL WELDING ROD IN KG.
TRUSS PER METER
METER
13.08 17.9 30.98 2% 0.62

TOTAL PIECES OF 2" x 4" x 1.20 x 10m GALVANIZED STEEL C - CHANNEL 5


TOTAL PIECES OF 2" x 4" x 1.20 x 8m GALVANIZED STEEL C - CHANNEL 1
TOTAL PIECES OF 2" x 4" x 1.20 x 6m GALVANIZED STEEL C - CHANNEL 1
TOTAL PIECES OF 2" x 3" x 1.20 x 10m C - PURLINS 17
TOTAL PIECES OF 10mmØ x 10m SAG ROD 20
TOTAL PIECES OF ANGLE BAR CLEATS 60
TOTAL WELDING ROD IN KG. 0.62

PREPARED BY:

HENRIETTE MAY K. CRISTOBAL


QS Student - BSCE 3A

CLAIRE TABOR
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
COST COMPUTATION (STRUCTURAL WORKS
I. CONCRETE WORKS
SPECIFICATION QTY.
40 KG. OF CEMENT 425
SAND 36
GRAVEL 71
TOTAL

II. RSB WORKS


SPECIFICATION QTY.
6m x 10mm Ø STEEL BAR #REF!
7.5m x 10mm Ø STEEL BAR #REF!
9m x 10mm Ø STEEL BAR #REF!
10.5m x 10mm Ø STEEL BAR #REF!
12m x 10mm Ø STEEL BAR #REF!
13.5m x 10mm Ø STEEL BAR #REF!
6m x 12mm Ø STEEL BAR #REF!
7.5m x 12mm Ø STEEL BAR #REF!
10.5m x 12mm Ø STEEL BAR #REF!
12m x 12mm Ø STEEL BAR #REF!
13.5m x 12mm Ø STEEL BAR #REF!
6m x 16mm Ø STEEL BAR #REF!
7.5m x 16mm Ø STEEL BAR #REF!
9m x 16mm Ø STEEL BAR #REF!
10.5m x 16mm Ø STEEL BAR #REF!
13.5m x 16mm Ø STEEL BAR #REF!
NO. 16 GI TIE WIRE (KG) #REF!
TOTAL

III. FORMWORKS
SPECIFICATION QTY.
1.2m x 2.4m PLYWOOD 234
2" x 2" x 10' LUMBER 179
2" x 2" x 14' LUMBER 471
2" x 2" x 16' LUMBER 128
2" x 2" x 18' LUMBER 282
2" x 2" x 20' LUMBER 268
COMMON NAILS (KG) 208.34
TOTAL

IV. SCAFFOLDING
SPECIFICATION QTY.
2" x 2" x 10' LUMBER 224
2" x 2" x 16' LUMBER 287
2" x 2" x 20' LUMBER 237
2" x 3" x 12' LUMBER 75
2" x 3" x 22' LUMBER 40
COMMON NAILS (KG) 85
TOTAL

V. STEEL WORKS
SPECIFICATION QTY.
2" x 4" x 1.20 x 10m GALVANIZED STEEL C - CHANNEL 5
2" x 4" x 1.20 x 8m GALVANIZED STEEL C - CHANNEL 1
2" x 4" x 1.20 x 6m GALVANIZED STEEL C - CHANNEL 1
"2 x 3" x 1.20 x 10m C- PURLINS 17
10mm Ø X 10m SAG ROD 20
ANGLE BAR CLEATS 60
WELDING ROD (KG) 1
TOTAL

STRUCTURAL WORKS TOTAL AMOUNT

CANVASS SHEET

ITEM OF WORK: AS OF: APRIL,09 2024


CONCRETE WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
I. CONCRETE WORKS
PORTLAND CEMENT BAG (40kg) PhilCon ₱247.50
SAND Load PhilCon ₱1,700.00
GRAVEL Load PhilCon ₱2,350.00

CANVASS SHEET

ITEM OF WORK: RSB AS OF: APRIL,24 2024


WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
II. RSB WORKS
10mm Ø x 6.00m per pc Starport PH ₱194.12
10mm Ø x 7.50m per pc Starport PH ₱241.40
10mm Ø x 9.00m per pc Starport PH ₱288.67
10mm Ø x 10.50m per pc Starport PH ₱337.95
10mm Ø x 12.00m per pc Starport PH ₱386.23
10mm Ø x 13.50m per pc Starport PH ₱434.51

12mm Ø x 6.00m per pc Starport PH ₱278.39


12mm Ø x 7.50m per pc Starport PH ₱347.99
12mm Ø x 9.00m per pc Starport PH ₱417.59
12mm Ø x 10.50m per pc Starport PH ₱487.18
12mm Ø x 13.50m per pc Starport PH ₱605.06

16mm Ø x 6.00m per pc Starport PH ₱494.70


16mm Ø x 7.50m per pc Starport PH ₱618.38
16mm Ø x 9.00m per pc Starport PH ₱742.06
16mm Ø x 10.50m per pc Starport PH ₱865.73
16mm Ø x 12.00m per pc Starport PH ₱989.41
16mm Ø x 13.50m per pc Starport PH ₱1,037.69

GI #16 TIE WIRE per kgs. PhilCon ₱65.00

CANVASS SHEET

ITEM OF WORK:
AS OF: APRIL,09 2024
FORMWORKS & STAGING
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
III. FORMWORKS AND SCAFFOLDINGS
1.20m x 2.40m x 1/2" PLYWOOD per pc PhilCon ₱574.00
0.90m x 1.8m x 1/4" PLYWOOD per pc PhilCon ₱381.00
2" x 2" x 8' LUMBER (COCO) per bd.ft. PhilCon ₱20.39
2" x 2" x 10' LUMBER (COCO) per pcs. PhilCon ₱285.00
2" x 2" x 14' LUMBER (COCO) per pcs. PhilCon ₱300.00
2" x 2" x 18' LUMBER (COCO) per pcs. PhilCon ₱545.00
2" x 2" x 20' LUMBER (COCO) per pcs. PhilCon ₱650.00
2" x 2" x 22' LUMBER (COCO) per bd.ft. PhilCon ₱20.39
2" x 2" x 24' LUMBER (COCO) per bd.ft. PhilCon ₱20.39
2" x 3" x 12' LUMBER (COCO) per pcs. PhilCon ₱380.00
2" x 3" x 20' LUMBER (COCO) per pcs. PhilCon ₱950.00
ASSORTED CWN kgs. PhilCon ₱69.18

CANVASS SHEET

ITEM OF WORK: STEEL


AS OF: APRIL, 24 2024
WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
IV. STEEL WORKS
ANGLE BAR (25mm x 25mm x 5mm thick) per 6 meter PhilCon ₱608.00
ANGLE BAR (50mm x 50mm x 3mm thick) per 6 meter PhilCon ₱721.00
ANGLE BAR (50mm x 50mm x 5mm thick) per 6 meter PhilCon ₱1,100.00
C - PURLINS (75mm x 50mm x 1.0mm thick) per 6 meter PhilCon ₱427.00
SAG ROD (12mm Ø) per 6 meter PhilCon ₱380.00
CHANNEL (75mm x 50mm x 3mm thick) per 6 meter Steel Innovation Philippines ₱1,669.00
FASCIA BOARD (12mm x 12" x 8') per pc LPM EXPRESS ₱507.00
CLEATS (140mm x 6mm thick) per pc ACCORD STEEL CLADDING ₱496.70
MS PLATE (4' x 8' x 3mm thick) per pc PhilCon ₱3,225.00
BOLTS & NUTS (M16 - 75mm) per pc PhilCon ₱35.00
Washers per pc PhilCon ₱1.00
Welding Rod per kgs. PhilCon ₱117.00

PREPARED BY:

HENRIETTE MAY K. CRISTOBAL


QS Student - BSCE 3A

CLAIRE TABOR
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
RUCTURAL WORKS)

UNIT COST TOTAL COST


₱250.00 ₱106,250.00
₱2,100.00 ₱75,600.00
₱2,500.00 ₱177,500.00
₱359,350.00

UNIT COST TOTAL COST


#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF!

UNIT COST TOTAL COST


₱580.00 ₱135,720.00
₱285.00 ₱51,015.00
₱300.00 ₱141,300.00
₱348.00 ₱44,544.00
₱545.00 ₱153,690.00
₱650.00 ₱174,200.00
₱80.00 ₱16,667.20
₱717,136.20

UNIT COST TOTAL COST


₱285.00 ₱63,840.00
₱348.00 ₱99,876.00
₱650.00 ₱154,050.00
₱380.00 ₱28,500.00
₱950.00 ₱38,000.00
₱80.00 ₱6,800.00
₱391,066.00

UNIT COST TOTAL COST


₱450.00 ₱2,250.00
₱400.00 ₱400.00
₱370.00 ₱370.00
₱560.00 ₱9,520.00
₱380.00 ₱7,600.00
₱496.00 ₱29,760.00
₱117.00 ₱117.00
₱37,477.00

#REF!

HEET

AS OF: APRIL,09 2024

UNIT SUPPLIER 2 COST

BAG (40kg) Dreamhome ₱250.00


Load Dreamhome ₱2,100.00
Load Dreamhome ₱2,500.00

HEET

AS OF: APRIL,24 2024

UNIT SUPPLIER 2 COST (₱)

per pc Cebu Steel Corporation ₱162.62


per pc Cebu Steel Corporation ₱203.28
per pc Cebu Steel Corporation ₱243.94
per pc Cebu Steel Corporation ₱284.59
per pc Cebu Steel Corporation ₱325.25
per pc Cebu Steel Corporation ₱365.91

per pc Cebu Steel Corporation ₱234.43


per pc Cebu Steel Corporation ₱293.04
per pc Cebu Steel Corporation ₱351.65
per pc Cebu Steel Corporation ₱410.26
per pc Cebu Steel Corporation ₱509.52

per pc Cebu Steel Corporation ₱412.80


per pc Cebu Steel Corporation ₱516.01
per pc Cebu Steel Corporation ₱619.21
per pc Cebu Steel Corporation ₱722.41
per pc Cebu Steel Corporation ₱825.61
per pc Cebu Steel Corporation ₱866.27

per kgs. Top-Most Hardware & Construction Supply ₱85.00

HEET

AS OF: APRIL,09 2024

UNIT SUPPLIER 2 COST

per pc Dreamhome ₱580.00


per pc Dreamhome ₱390.00
per bd.ft. Dreamhome ₱30.25
per pcs. Dreamhome ₱280.00
per pcs. Dreamhome ₱289.00
per pcs. Dreamhome ₱530.00
per pcs. Dreamhome ₱630.00
per bd.ft. Dreamhome ₱30.25
per bd.ft. Dreamhome ₱30.25
per pcs. Dreamhome ₱370.00
per pcs. Dreamhome ₱900.00
kgs. Dreamhome ₱80.00

HEET

AS OF: APRIL, 24 2024

UNIT SUPPLIER 2 COST (₱)


per 6 meter Dreamhome ₱560.00
per 6 meter Dreamhome ₱678.00
per 6 meter Dreamhome ₱1,014.00
per 6 meter Dreamhome ₱409.00
per 6 meter Dreamhome ₱357.00
per 6 meter Dreamhome ₱1,501.00
per pc Dreamhome ₱507.00
per pc Dreamhome ₱433.05
per pc Dreamhome ₱3,204.00
per pc Dreamhome ₱33.69
per pc Dreamhome ₱1.00
per kgs. Dreamhome ₱86.00

K. CRISTOBAL
BSCE 3A

ABOR
BSCE 3A

OSE P. PASCUA
t Instructor
PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING
MASONRY WORKS
USING 10 X 20 X 40 CM CHB
A. CONCRETE HOLLOW BLOCKS
FOR GROUND FLOOR
AREA NO. PER sq.m NO. OF PCS
12.61 12.5 158
23.78 12.5 297
23.78 12.5 297
15.54 12.5 194
14.79 12.5 185
19.30 12.5 241
19.44 12.5 243
12.61 12.5 158
5.44 12.5 68
11.94 12.5 149
11.84 12.5 148

TOTAL: 2138
B. MORTAR FOR BLOCK LAYING
AVERAGE THICKNESS (0.0125)
THICKNESS WIDTH LENGTH VOLUME (CUBIC METER)
0.0125 0.1 16 0.02
TOTAL VOLUME: 0.2

USING CLASS C MIXTURE (40KG CEMENT)

CEMENT (PCS.) SAND (M3)


1.8 0.2
C. MORTAR FILLER FOR HOLLOW CELL
THICKNESS WIDTH LENGTH VOLUME (CUBIC METER)
0.05 0.075 0.2 0.00075
TOTAL VOLUME: 0.003
TOTAL VOLUME CELLS FOR 400 CHB
TOTAL VOLUME: 6.414665625
REFER TO TABLE 2-1 USING CLASS C MIXTURE
CEMENT (PCS.) SAND (M3)
57.731990625 6.414665625
D. PLASTERING AT AN AVERAGE OF (0.016M) THICK
AREA VOLUME
96 1.536
REFER TO TABLE 2-1 USING CLASS C MIXTURE
CEMENT (PCS.) SAND (M3)
13.824 1.536
E. CHB FOOTING
THICKNESS WIDTH LENGTH VOLUME (CUBIC METER)
0.15 0.4 16 0.96

CEMENT SAND GRAVEL


5.76 0.48 0.096
F. CHB REINFORCEMENT AT 80CM

AREA (M2) 48
REFER TO TABLE 3-4
VERTICAL REINFORCEMENT AT 80CM
NO. OF PIECES
48 1.6 76.8 12.8
TOTAL NO. OF PIECES OF 10MM X 6.0 RSB 13
VERTICAL REINFORCEMENT EVERY 3 LAYERS
NO. OF PIECES
48 2.15 103.2 17.2
TOTAL NO. OF PIECES OF 10MM X 6.0 RSB 18
G. GI TIE WIRE
REFER TO TABLE 3-5
USING 25 CM TIE WIRE

400 0.0016 0.64


TOTAL KG. OF NO.16 TIE WIRE 0.64
SUMMARY OF MATERIALS (MASONRY WORKS)
10 X 20 X 40 CHB = 2138 PIECES
40 KG CEMENT (CLASS C) = 80 BAGS
SAND = 11 M3
GRAVEL = 1 M3
10 MM X 6.0 M RSB = 31 PCS
NO. 16 G.I TIE WIRE = 0.64 KG

TILE WORKS
FLOOR FINISH 1
0.60 X0.60 CERAMIC TILES FLOOR FINISH (GLAZE)
LOCATION LENGTH WIDTH AREA
LIVING ROOM 3.63 4.66 16.9158
BEDROOM 1 3.32 3.78 12.5496
FLOOR FINISH 2
0.60 X0.60 TEXTURE CERAMIC TILES FLOOR FINISH (GLAZE)
LOCATION LENGTH WIDTH AREA
KITCHEN 2.32 3.18 7.3776
BEDROOM 2 3.07 3.18 9.7626
BEDROOM 3 2.88 2.3 6.624
MASTERS BEDROOM 3.32 3.78 12.5496
FLOOR FINISH 3
0.20 X 0.20 CERAMIC TILES FLOOR FINISH (UNGLAZE)
LOCATION LENGTH WIDTH AREA
TOILET AND BATH GROUND FLOOR 2.72 2.5 6.8
TOILET AND BATH (MASTERS) 2.72 2.5 6.8
FLOOR FINISH 4
0.60 X 0.60 CERAMIC FLOOR TILES UNGLAZE
LOCATION LENGTH WIDTH AREA
BALCONY 3.63 2.28 8.2764
FLOOR FINISH 4
0.60 X 0.60 CERAMIC FLOOR TILES UNGLAZE
LOCATION LENGTH WIDTH AREA
BALCONY 3.63 2.28 8.2764
TOTAL AREA
FF1 29.4654 30
FF2 36.3138 37
FF3 13.6 14
FF4 8.2764 9
FLOOR FINISH 1
TOTAL AREA = 30 SQM
200 CM X 200 CM CERAMIC TILES FLOOR FINISH (GLAZE)
REFER TO TABLE

NUMBER OF TILES
AREA MULTIPLIER NUMBER OF PIECES
30 26 780
SAY 780 PIECES OF 200 CM BY 200 CM CERAMIC GLAZED TILES
PORTLAND CEMENT
REFER TO TABLE
AREA MULTIPLIER NUMBER OF BAGS
30 0.33 9.9
SAY 10 BAGS OF PORTLAND CEMENT
SAND
REFER TO TABLE

AREA MULTIPLIER NUMBER OF CUBIC METER


30 0.03 0.9
SAY 1 CUBIC METER OF SAND
TILE GROUT
REFER TO TABLE
AREA MULTIPLIER NUMBER OF BAGS
30 0.13 3.9
SAY 4 BAGS OF TILE GROUT

FLOOR FINISH 2
TOTAL AREA = 37 SQM
200 CM BY 200 CM TEXTURE CERAMIC TILES FLOOR FINISH (GLAZE)
REFER TO TABLE

NUMBER OF TILES
AREA MULTIPLIER NUMBER OF PIECES
37 26 962
SAY 962 PIECES OF 200 CM BY 200 CM CERAMIC GLAZED TILES
PORTLAND CEMENT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


37 0.33 12.21
SAY 13 BAGS OF PORTLAND CEMENT
SAND
REFER TO TABLE

AREA MULTIPLIER NUMBER OF CUBIC METER


37 0.03 1.11
SAY 2 CUBIC METER OF SAND
TILE GROUT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


37 0.13 4.81
SAY 5 BAGS OF TILE GROUT

FLOOR FINISH 3
TOTAL AREA = 14 SQM
600 MM X 600 MM CERAMIC TILES FLOOR FINISH (UNGLAZE)
REFER TO TABLE

NUMBER OF TILES
AREA MULTIPLIER NUMBER OF PIECES
14 2.92 40.88
SAY 41 PIECES OF 600 MM X 600 MM CERAMIC TILES FLOOR FINISH (UNGLAZE)
PORTLAND CEMENT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


14 0.33 4.62
SAY 5 BAGS OF PORTLAND CEMENT
SAND
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


14 0.03 0.42
SAY 1 CUBIC METER OF SAND
TILE GROUT
REFER TO TABLE
AREA MULTIPLIER NUMBER OF BAGS
14 0.13 1.82
SAY2 BAGS OF TILE GROUT
FLOOR FINISH 4
TOTAL AREA = 9 SQM
600 MM X 600 MM CERAMIC TILES FLOOR FINISH (UNGLAZE)
REFER TO TABLE

NUMBER OF TILES
AREA MULTIPLIER NUMBER OF PIECES
6 2.92 17.52
SAY 18 PIECES OF 600 MM X 600 MM CERAMIC TILES FLOOR FINISH (UNGLAZE)
PORTLAND CEMENT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


9 0.33 2.97
SAY 3 BAGS OF PORTLAND CEMENT
SAND
REFER TO TABLE
AREA MULTIPLIER NUMBER OF BAGS
9 0.03 0.27
SAY 1 CUBIC METER OF SAND
TILE GROUT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


9 0.13 1.17
SAY2 BAGS OF TILE GROUT

WALL FINISHES
WF2 (4 LAYER OF 200 CM BY 200 CM CERAMIC TILES) GLAZE
LOCATION LENGTH OF WALL
KITCHEN 3.07
BEDROOM 2 3.07
BEDROOM 3 2.88
TOTAL 9.02
TOTAL AREA = 10 SQM
200 CM X 200 CM CERAMIC TILES FLOOR FINISH (GLAZE)
REFER TO TABLE
NUMBER OF TILES
AREA MULTIPLIER NUMBER OF PIECES
10 26 260
HEIGHT OF WALL 3.4O METERS
TOTAL LAYERS 17 4 LAYERS 62 PIECES OF TILES
SAY 62 PIECES OF 200 CM BY 200 CM CERAMIC GLAZED TILES
PORTLAND CEMENT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


3.1 0.33 1.023
SAY 2 BAGS OF PORTLAND CEMENT
SAND
REFER TO TABLE
AREA MULTIPLIER NUMBER OF CUBIC METER
3.1 0.03 0.093
SAY 1 CUBIC METER OF SAND
TILE GROUT
REFER TO TABLE

AREA MULTIPLIER NUMBER OF BAGS


3.1 0.13 0.403
SAY 1 BAG OF TILE GROUT

SUMMARY OF MATERIALS (TILE WORKS)


SAY 1804 PIECES OF 200 CM BY 200 CM CERAMIC GLAZED TILES
SAY 33 BAGS OF PORTLAND CEMENT
SAY 6 CUBIC METER OF SAND
SAY 14 BAGS OF TILE GROUT
SAY 59 PIECES OF 600 MM X 600 MM CERAMIC TILES FLOOR FINISH (UNGLAZE)

PAINTING WORKS
WALLS LENGTH AREA
WALL 1 0.275 0.935
WALL 2 0.425 1.445
WALL 3 15.45 52.53
WALL 4 1.65 5.61
WALL 5 1.025 3.485
WALL 6 1.05 3.57
WALL 7 1.25 4.25
WALL 8 0.45 1.53
WALL 9 0.5 1.7
WALL 10 5.05 17.17
WALL 11 0.275 0.935
WALL 12 0.425 1.445
WALL 13 12.35 41.99
WALL 14 1.65 5.61
WALL 15 1.025 3.485
WALL 16 1.05 3.57
WALL 17 1.25 4.25
WALL 18 0.45 1.53
WALL 19 0.5 1.7
WALL 20 5.05 17.17
TOTAL AREA: 173.91
CONCRETE NEUTRALIZER
TOTAL AREA MULTIPLIER NUMBER OF GALLON
173.91 30 5.8
NO. OF PINTS CONCRETE NEUTRALIZER 2.4
SAY 3 PINTS
1 PINT IS EQUAL TO 0.473 LITERS
ACRYLIC LATEX PAINT AT 40SQM PER 4 LITERS
TOTAL AREA MULTIPLIER NUMBER OF CANS
173.91 40 4.35
SAY 5 CANS
FOR SECOND COAT
NUMBER OF CANS MULTIPLIER TOTAL
5 2 10
ADD 10 &
ORDER 11 CANS AT 4 LITER
SUMMARY OF MATERIALS (PAINTING WORKS)
MATERIALS QUANTITY AREA TOTAL GALLON
CONCRETE NEUTRALIZER 0.02 174 3.48
CONCRETE PRIMER 0.04 174 6.96
PATCHING COMPOUND 0.05 174 8.7
SEMIGLOSS (DOUBLE COAT) 0.08 174 13.92
WOOD /TIMBER PAINTING MATERIALS
MATERIALS QUANTITY AREA TOTAL
GLAZING PUTTY 0.05 174 8.7
FLAT WALL ENAMEL 0.04 174 6.96
ENAMEL QUICK DRY 0.04 174 6.96
PAINT THINNER 0.25 174 43.5
TINTING COLOR 0.01 174 1.74
METAL/STEEL PAINTING MATERIALS (PER SQM)
MATERIALS QUANTITY AREA TOTAL
RED OXIDE PRIMER 0.04 174 6.96
ENAMEL PAINT 0.1 174 17.4
PAINT THINNER 0.25 174 43.5
TINTING COLOR 0.01 174 1.74
DOORS
3'' X 6'' DOOR JAMB
DOORS HEADER JAMB QUANTITY
D1 4 8 4
D2 3 7 2
D3 3 7 2
AD1 8 7 1
AD2 6 7 1
ORDER
HEADER JAMB
3'' X 6'' X 14' 3'' X 6'' X 16'
3'' X 6'' X 14' 3'' X 6'' X 16'
3'' X 6'' X 14' 3'' X 6'' X 16'
3'' X 6'' X 18' 3'' X 6'' X 16'
3'' X 6'' X 16' 3'' X 6'' X 16'
SUMMARY OF MATERIALS (DOOR JAMBS)
3'' X 6'' X 14' 8 PCS
3'' X 6'' X 16' 1 PC
3'' X 6'' X 18' 1 PC
SUMMARY OF MATERIALS (DOOR HEADER)
3'' X 6'' X 16' 1O PCS
WINDOWS
WINDOWS JAMBS HEADER/SILL MULION
W1 8 FT 4 FT 4 FT
W2 8 FT 4 FT 4 FT
W3 8 FT 7 FT 4 FT
W4 5 FT 12 FT 3 FT
W5 3 FT 5 FT 3 FT
W6 3 FT 2 FT 1.5 FT
WINDOWS TRANSCOM QUANTITY
W1 4 FT 3
W2 4 FT 2
W3 7 FT 4
W4 12 FT 1
W5 5 FT 1
W6 2 FT 1
SUMMARY OF MATERIALS (WINDOW JAMBS)
3'' X 6'' X 8' 9 PCS
3'' X 6'' X 6' 1 PC
3'' X 6'' X 4' 2 PCS
SUMMARY OF MATERIALS (WINDOW HEADER/SILL)
3'' X 6'' X 12' 1 PC
3'' X 6'' X 8' 5 PCS
3'' X 6'' X 6' 6 PCS
3'' X 6'' X 4' 1 PC
SUMMARY OF MATERIALS (WINDOW MULION)
3'' X 6'' X 6' 12 PCS
SUMMARY OF MATERIALS (WINDOW TRANSOM)
3'' X 6'' X 12' 1 PC
3'' X 6'' X 10' 5 PCS
3'' X 6'' X 6' 6 PCS
3'' X 6'' X 4' 1 PC
WINDOW FRAMES
WINDOWS JAMBS HEADER/SILL MULION
W1 8 FT 4 FT 4 FT
W2 8 FT 4 FT 4 FT
W3 8 FT 7 FT 4 FT
W4 5 FT 12 FT 3 FT
W5 3 FT 5 FT 3 FT
W6 3 FT 2 FT 1.5 FT
WINDOWS TRANSCOM QUANTITY
W1 4 FT 3
W2 4 FT 2
W3 7 FT 4
W4 12 FT 1
W5 5 FT 1
W6 2 FT 1
FIBER GLASS FRAME WINDOW
WINDOWS SIZE TOTAL LENGTH TO BE FRAMED
W1 32
W2 32
W3 56
W4 60
201
W5 15
W6 6
FIBER GLASS FRAME TO BE ORDER (1/2 INCH)
SIZE OF CUT (SQ.FT) TOTAL PIECES SAY 3 PIECES OF 80 SQ.FT 1/2 INCH FIBER
80 2.5125 GLASS

CEILING WORKS
FLOOR AREA (1ST FLOOR)
DESCRIPTION LENGTH WIDTH AREA
LIVING ROOM 3.85 6.225 23.96625
BEDROOM (1ST FLOOR) 3.875 4 15.5
TOILET AND BATH 2.35 2.9 6.815
KITCHEN 3.075 4.1 12.6075
FLOOR AREA (2ND FLOOR)
DESCRIPTION LENGTH WIDTH AREA
MASTER BEDROOM 3.8 5.05 19.19
T &B MASTER BEDROOM 2 2.9 5.8
BEDROOM 2 4.1 3.075 12.6075
BEDROOM 3 3.85 3.075 11.83875
HALLWAY 1.18 5.85 6.903
TOTAL AREA OF
115.228
GROUND AND SECOND FLOOR
SAY 116 SQM
TIMBER-FRAMED CEILING
REFER TO TABLE
INTERIOR CEILING

MATERIAL DESCRIPTION MULTIPLIER TOTAL PIECES


4' x 8' FICEM BOARD 0.37 42.92
METAL FURING - 3m LENGTH 1.14 132.24
CARRYING CHANNEL - 3m LENGTH 0.37 42.92
HANGER ROD 1 116
CHANNEL CLIP 6 696
WALL ANGLE - 3m LENGTH 0.24 27.84
RIVET 14 1624
METAL SCREW 4 464
TIMBER-FRAMED CEILING
REFER TO TABLE
EXTERIOR CEILING
LOCATION LENGTH WIDTH AREA
PORCH 3.63 2.28 8.2764
BALCONY 2.88 2.32 6.6816
FRONT STAIRS 0.6 3.63 2.178
BACK STAIRS 0.6 2.28 1.368
TOTAL AREA 18.504
SAY 19 SQM
EXTERIOR CEILING
MATERIAL DESCRIPTION MULTIPLIER TOTAL PIECES
4' x 8' FICEM BOARD 0.37 7.03
METAL FURING - 3m LENGTH 1.14 21.66
CARRYING CHANNEL - 3m LENGTH 0.37 7.03
HANGER ROD 1 19
CHANNEL CLIP 6 114
WALL ANGLE - 3m LENGTH 0.24 4.56
RIVET 14 266
METAL SCREW 4 76

ROOFING WORKS
LENGTH = 11.3M
G.I SHEETS
REFER TO TABLE 6-8

AREA MULTIPLIER NUMBER Of PIECES


11.3 0.838 13.4844868735084
SAY 13.5 PIECES
RAFTER LENGTH 9.9 SAY 10 M
COMBINATION OF LENGTH
REFER TO TABLE 6-5
1.8 X 3.60 X 3.60 X 2.40
13.5 PIECES 0.80 X 1.80 G.I SHEETS
13.5 PIECES 0.80 X 3.60 G.I SHEETS
13.5 PIECES 0.80 X 3.60 G.I SHEETS
13.5 PIECES 0.80 X 2.40 G.I SHEETS
RIVETS
REFER TO TABLE 6-2

LENGTH TOTAL G.I SHEETS MULTIPLIER NO. OF NAILS / RIVETS


1.8 13.5 14 189
2.4 13.5 18 243
3.6 13.5 26 351
3.6 13.5 26 351
TOTAL NUMBER OF PIECES: 1134
CONVERTING TO KILOGRAMS
REFER TO TABLE 6-3
TOTAL NUMBER OF NAILS MULTIPLIER NUMBER OF KILOGRAMS
1134 180 6.3
SAY 6.5 KILOGRAMS OF NAILS/RIVETS
G.I WASHERS
TOTAL NUMBER OF NAILS MULTIPLIER TOTAL
1134 2 2268
CONVERTING TO KILOGRAMS
REFER TO TABLE 6-3

TOTAL NUMBER OF NAILS MULTIPLIER NUMBER OF KILOGRAMS


2268 126 18
18 KILOGRAMS OF G.I WASHERS
PLAIN G.I STRAP
500 mm X 150mm
TOTAL NUMBER OF RIVETS = 1134
REFER TO TABLE 6-4
TOTAL NUMBER OF NAILS MULTIPLIER NUMBER OF PIECES
1134 288 3.9375
SAY 4 PCS OF PLAIN G.I STRAP
LEAD WASHERS
REFER TO TABLE 6-3

TOTAL NUMBER OF NAILS MULTIPLIER NUMBER OF KILOGRAMS


1134 75 15.12
SAY 15.5 KILOGRAMS OF LEAD WASHERS
SUMMARY OF MATERIALS (ROOFING WORKS)
13.5 PIECES 0.80 X 1.80 G.I SHEETS
13.5 PIECES 0.80 X 3.60 G.I SHEETS
13.5 PIECES 0.80 X 3.60 G.I SHEETS
13.5 PIECES 0.80 X 2.40 G.I SHEETS
6.5 KILOGRAMS OF NAILS/RIVETS
18 KILOGRAMS OF G.I WASHERS
4 PCS OF PLAIN G.I STRAP
15.5 KILOGRAMS OF LEAD WASHERS
OTHER FINISHING MATERIALS
RAILINGS
LOCATION LENGTH LOCATION LENGTH
BALCONY FRONT 3.05 BALCONY BACK 3.1
3.85 3.85
3.05 3.1
TOTAL LENGTH 9.95 TOTAL LENGTH 10.05

TOTAL LENGTH TO BE RAILINGS 20

FOR 10mm X 10mm SQUARE STEEL BAR


TOTAL LENGTH SPACING HEIGHT OF CUTS TOTAL PIECES OF CUTS
20 0.1 1m 200

STEEL BAR TO BE ORDER


LENGTH OF
SIZE OF CUT TOTAL PIECES NO. OF CUTS PER STEEL BAR
STEEL BAR (m)
1 200 6 6
TOTAL PIECES TO BE ORDER 34

FOR 30mm x 30 mm SQUARE STEEL BAR


TOTAL LENGTH SPACING HEIGHT OF CUTS TOTAL PIECES OF CUTS
20 1 1m 20

STEEL BAR TO BE ORDER


LENGTH OF
SIZE OF CUT TOTAL PIECES NO. OF CUTS PER STEEL BAR
STEEL BAR (m)
1 20 6 6
TOTAL PIECES TO BE ORDER 4

FOR 30mm x 30 mm SQUARE STEEL BAR CONTINOUS


TOTAL LENGTH (TOP AND BOTTOM CONTINOUS BAR)
40
STEEL BAR TO BE ORDER
LENGTH OF
TOTAL LENGTH TOTAL PIECES TO BE ORDER
STEEL BAR (m)
40 6 7
TOTAL PIECES TO BE ORDER 7

SUMMARY OF MATERIALS (RAILINGS)


34 PIECES OF 10mm X 10mm SQUARE STEEL BAR
4 PIECES OF 30mm x 30 mm SQUARE STEEL BAR
7 PIECES OF 30mm x 30 mm SQUARE STEEL BAR CONTINOUS

OTHER FINISHES
FLOOR FINISH 5 AND FLOOR FINISH 6
NON-SKID CEMENT FLOOR FINISH
NON-SKID PLAIN CEMENT FLOOR FINISH
LOCATION LENGTH WIDTH AREA
PORCH 3.63 2.28 8.2764
BALCONY 2.88 2.32 6.6816
FRONT STAIRS 0.6 3.63 2.178
BACK STAIRS 0.6 2.28 1.368
TOTAL AREA 18.504
SAY 19 SQM
REFER TO TABLE 2-1
USING CLASS C MIXTURE (40KG CEMENT)
CEMENT (PCS.) SAND (M3)
142.5 9.5
SAY 143 BAGS OF 40 KGS. CEMENT "B" SAY 9.5 CUBIC METER OF SAND

PREPARED BY:

HENRIETTE MAY K. CRISTOBAL


QS Student - BSCE 3A

CLAIRE TABOR
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor
PROJECT: PROPOSED TWO STOREY RESIDENCE
LOCATION: DILAN PAURIDO ,URDANETA CITY PANGASINAN
SUBJECT: CE 111 - QUANTITY SURVEYING

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
MASONRY WORKS
CONCRETE HOLLOW BLOCKS PCS Topmost Hardware ₱19.00
CEMENT BAGS PhilCon ₱248.00
SAND CUBIC PhilCon ₱500.00
GRAVEL CUBIC PhilCon ₱530.00
10 MM X 6 M RSB PCS PhilCon ₱162.00
NO. 16 G.I TIE WIRE KGS PhilCon ₱65.00

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
TILE WORKS
200 CM X 200 CM GLAZED TILES PCS Wilcon ₱1,020.00
PORTLAND CEMENT BAGS PhilCon ₱45.00
SAND CUBIC PhilCon ₱500.00
GRAVEL CUBIC PhilCon ₱530.00
TILE GROUT BAGS Wilcon ₱145.00
600 MM X 600 MM UNGLAZED TILES PCS Wilcon ₱1,560.00

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
PAINTING WORKS
CONCRETE NEUTRALIZER 4 Liters Evercoat Painting ₱562.00
CONCRETE PRIMER 4 Liters Paint Republic ₱675.00
PATCHING COMPOUND 5Kgs SampCloudMan ₱763.37
SEMIGLOSS (DOUBLE COAT) Liter CMS Paint Depot ₱3,321.00
GLAZING PUTTY Liter Brix Industries ₱224.00
FLAT WALL ENAMEL Gallon Gazelle Building ₱790.00
ENAMEL QUICK DRY 4Liters Gazelle Building ₱813.00
PAINT THINNER 4 Liters Cane Industrial ₱420.00
TINTING COLOR Liters Evercoat Painting ₱523.00
RED OXIDE PRIMER 4 Liters SCL Hardware ₱559.00
ENAMEL PAINT 4 Liters Gazelle Building ₱980.00

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
DOORS AND WINDOWS
3'' X 6'' X 18' PCS PhilCon ₱1,900.00
3'' X 6'' X 16' PCS PhilCon ₱1,700.00
3'' X 6'' X 14' PCS PhilCon ₱1,590.00
3'' X 6'' X 12' PCS PhilCon ₱1,376.00
3'' X 6'' X 10' PCS PhilCon ₱1,267.00
3'' X 6'' X 8' PCS PhilCon ₱1,112.00
3'' X 6'' X 6' PCS PhilCon ₱1,112.00
3'' X 6'' X 4' PCS PhilCon ₱1,112.00
80 SQ.FT FIBER GLASS PCS PhilCon ₱150.00

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
CEILING WORKS
80 SQ.FT FIBER GLASS PCS PhilCon ₱150.00
1.20 X 2.40 PLYWOOD PCS PhilCon ₱580.00
4' x 8' FICEM BOARD PCS JamesHardie ₱877.00
4' x 8' GYPSUM BOARD PCS Ritemore Enterprise ₱440.00
METAL FURING (5m) PCS Metalink ₱121.00
CARRYING CHANNEL (5m) PCS Metalink ₱125.00
HANGER ROD PCS Metalink ₱12.00
CHANNEL CLIP PCS Metalink ₱4.00
WALL ANGLE (3m) PCS Cebu Bulders ₱55.00
RIVET BOX Cebu Bulders ₱150.00
METAL SCREW PCS Cebu Bulders ₱170.00

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
ROOFING WORKS
0.80 X 1.80 G.I SHEETS PCS Shopee ₱900.00

0.80 X 3.60 G.I SHEETS PCS Shopee ₱1,730.00

0.80 X 2.40 G.I SHEETS PCS Shopee ₱1,450.00


RIVETS KGS Philcon ₱169.79
G.I WASHERS KGS Shopee ₱150.00
G.I STRAP PCS Shopee ₱1,900.00
LEAD WASHERS KGS Philcon ₱165.31

CANVASS SHEET

ITEM OF WORK:
AS OF: MAY 19, 202
ARCHITECTURAL WORKS
SPECIFICATION UNIT SUPPLIER 1 COST (₱)
OTHERS
10mm X 10mm SQUARE STEEL BAR PCS Shopee ₱220.00
30mm X 30mm SQUARE STEEL BAR PCS RS Pro Stainless ₱456.12
30mm x 30 mm SQUARE STEEL BAR PCS RS Pro Stainless ₱7,849.00

PREPARED BY:

HENRIETTE MAY K. CRISTOBAL


QS Student - BSCE 3A

CLAIRE TABOR
QS Student - BSCE 3A

CONFORME:

ENGR. MELANIE ROSE P. PASCUA


CE Department Instructor

COST COMPUTATION (ARCHITECTURAL W


MASONRY WORKS
SPECIFICATION QTY.
CONCRETE HOLLOW BLOCKS 2138
CEMENT 80
SAND 11
GRAVEL 1
10 MM BY 6.0 M RSB 31
NO. 16 G.I TIE WIRE 1
TOTAL

TILE WORKS
SPECIFICATION QTY.
200 CM X 200 CM GLAZED TILES 1804
PORTLAND CEMENT 33
SAND 6
GRAVEL 1
TILE GROUT 14
600MM X 600 MM UNGLAZED TILES 59
TOTAL

PAINTING WORKS
SPECIFICATION QTY.
CONCRETE NEUTRALIZER 4
CONCRETE PRIMER 7
PATCHING COMPOUND 9
SEMI GLOSS (DOUBLE COAT) 14
GLAZING PUTTY 9
FLAT WALL ENAMEL 7
ENAMEL QUICK DRY 7
PAINT THINNER 88
TINTING COLOR 4
RED OXIDE PRIMER 7
ENAMEL PAINT 18
CAMEL HAIR PAINT BRUSH 10
PAINT ROLLER 4 INCHES 10
TOTAL

DOORS AND WINDOWS


SPECIFICATION QTY.
3'' X 6'' X 18' 1
3'' X 6'' X 16' 11
3'' X 6'' X 14' 8
3'' X 6'' X 12' 2
3'' X 6'' X 10' 5
3'' X 6'' X 8' 14
3'' X 6'' X 6' 25
3'' X 6'' X 4' 4
TOTAL

CEILING WORKS
SPECIFICATION QTY.
1.20 X 2.40 PLYWOOD 335

TOTAL

ROOFING WORKS
SPECIFICATION QTY.
0.80 X 1.80 G.I SHEETS 13.5
0.80 X 3.60 G.I SHEETS 13.5
0.80 X 2.40 G.I SHEETS 13.5
RIVETS 6.5
G.I WASHERS 18
G.I STRAP 4
LEAD WASHERS 15.5
TOTAL

OTHERS
SPECIFICATION QTY.
10mm X 10 mm SQUARE STEEL BAR 34
30mm X 30 mm SQUARE STEEL BAR 4
30mm X 30 mm SQUARE STEEL BAR 7
TOTAL

ARCHITECTURAL WORKS TOTAL AMOUNT


HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


RKS
PCS MHV Construction ₱20.00
BAGS MHV Construction ₱250.00
CUBIC MHV Construction ₱530.00
CUBIC MHV Construction ₱550.00
PCS Dreamhome ₱192.00
KGS Dreamhome ₱75.00

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


S
PCS Dreamhome ₱1,050.00
BAGS Dreamhome ₱50.00
CUBIC Dreamhome ₱530.00
CUBIC Dreamhome ₱550.00
BAGS Dreamhome ₱150.00
PCS Dreamhome ₱1,500.00

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


RKS
4 Liters Destiny Paint ₱700.00
4 Liters Arkhon ₱750.00
5Kgs Meisons ₱300.00
Liter Zhihan ₱2,999.00
Liter SampCloudMan ₱240.00
Gallon SampCloudMan ₱690.00
4Liters Ayan Construction ₱704.00
4 Liters Gazelle Building ₱575.00
Liters Ayan Construction ₱560.00
4 Liters Gazelle Building ₱579.00
4 Liters Dona Juana Hardware ₱1,091.00

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


DOWS
PCS PhilCon ₱1,900.00
PCS PhilCon ₱1,700.00
PCS PhilCon ₱1,590.00
PCS PhilCon ₱1,376.00
PCS PhilCon ₱1,267.00
PCS PhilCon ₱1,112.00
PCS PhilCon ₱1,112.00
PCS PhilCon ₱1,112.00
PCS Dreamhome ₱175.00

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


KS
PCS Dreamhome ₱175.00
PCS Dreamhome ₱550.00
PCS Const.ph ₱702.00
PCS Topmost Hardware ₱450.00
PCS Topmost Hardware ₱115.00
PCS Topmost Hardware ₱130.00
PCS Const.ph ₱15.00
PCS Const.ph ₱5.00
PCS Metalink ₱40.00
BOX Ritemore Enterprise ₱120.00
PCS Ritemore Enterprise ₱150.00

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST


RKS
PCS Shopee ₱900.00

PCS Shopee ₱1,730.00

PCS Shopee ₱1,450.00


KGS Philcon ₱169.79
KGS Shopee ₱150.00
PCS Shopee ₱1,900.00
KGS Philcon ₱165.31

HEET

AS OF: MAY 19, 2024

UNIT SUPPLIER 2 COST

PCS Shopee ₱220.00


PCS RS Pro Stainless ₱456.12
PCS RS Pro Stainless ₱7,849.00

AY K. CRISTOBAL
t - BSCE 3A

E TABOR
t - BSCE 3A

E ROSE P. PASCUA
ment Instructor

HITECTURAL WORKS)
ORKS
UNIT COST TOTAL COST
₱20.00 ₱42,760.00
₱250.00 ₱20,000.00
₱530.00 ₱5,830.00
₱550.00 ₱550.00
₱192.00 ₱5,952.00
₱75.00 ₱75.00
₱75,167.00

KS
UNIT COST TOTAL COST
₱1,050.00 ₱1,894,200.00
₱50.00 ₱1,650.00
₱530.00 ₱3,180.00
₱550.00 ₱550.00
₱150.00 ₱2,100.00
₱1,560.00 ₱92,040.00
₱1,993,720.00

ORKS
UNIT COST TOTAL COST
₱700.00 ₱2,800.00
₱750.00 ₱5,250.00
₱763.00 ₱6,867.00
₱3,321.00 ₱46,494.00
₱240.00 ₱2,160.00
₱790.00 ₱5,530.00
₱813.00 ₱5,691.00
₱575.00 ₱50,600.00
₱560.00 ₱2,240.00
₱579.00 ₱4,053.00
₱1,091.00 ₱19,638.00
₱576.00 ₱5,760.00
₱1,096.00 ₱10,960.00
₱168,043.00

NDOWS
UNIT COST TOTAL COST
₱1,900.00 ₱1,900.00
₱1,700.00 ₱18,700.00
₱1,590.00 ₱12,720.00
₱1,376.00 ₱2,752.00
₱1,267.00 ₱6,335.00
₱1,112.00 ₱15,568.00
₱1,112.00 ₱27,800.00
₱1,112.00 ₱4,448.00
₱90,223.00

RKS
UNIT COST TOTAL COST
₱580.00 ₱194,300.00

₱194,300.00

ORKS
UNIT COST TOTAL COST
₱900.00 ₱12,150.00
₱1,730.00 ₱23,355.00
₱1,450.00 ₱19,575.00
₱169.79 ₱1,103.64
₱150.00 ₱2,700.00
₱1,900.00 ₱7,600.00
₱165.31 ₱2,562.31
₱69,045.94

UNIT COST TOTAL COST


₱220.00 ₱7,480.00
₱456.12 ₱1,824.48
₱7,849.00 ₱54,943.00
₱64,247.48

NT ₱2,654,746.42