Long (8-0.05) +(4.50-0.05) +(6.25-0.05) =18.

6 *
3.238=61.008pies
2ø3/8*61.008*0.376*1.10=50.465 pies lb
2ø1/2*61.008*0.668*1.10=89.657 pies lb
Log trasversal 7.95+4+6.25/0.20+1=92
(0.45-0.05) +2(0.15) =0.7*3.28pie=2.296
92ø3/8*2.296*0.376*1.10=87.365 pie lb
Σ 50.465+89.657+87.365=227.487/100=2.274qq
V.H=18.28*0.45*0.25=2.056
P=2.275/2.056=1.109*2=alambre=2.218lbs/m 3

Despiece
2ø3/8*61.008/20=6.1=7ø3/8*20
2ø1/2*61.008/20=6.1=7ø1/2*20
Alambre=2.218*2.056=4.56lb
Acero Long sup=2ø3/8
Acero inf=2ø3/4+2ø1/2
Acero trasversal =Estø3/8@0.20
L=(12-0.05)+(6.5-0.05)+(6.25-0.05)=24.6*3.28pie=80.688
Acero Long supe 2ø3/8*80.688*0.376lb*1.10=66.745lbs
Acero inf 2ø3/4*80.688*1.502*1.10=266.625lbs
Acero inf 2ø1/2*80.688*0.668*1.10=118.579lbs
Long trasversal
11.95+6+6.25/0.20+1=122
L=2(0.60-0.05) +2(0.25-0.05) +2(0.15) =1.8*3.28pie=5.904
122 ø3/8*5.904*0.376lb*1.10=297.911
Σ=66.745+266.625+118.579+297.911=749.86/100=7.498 qq
V.H=24.25*0.25*0.60=3.637
P=7.498/3.637=2.061*2=alambre=4.122lbs
Despiece
2ø3/8*80.688/20=8.06=9ø3/8*20
2ø1/2*80.688/20=8.06=9ø1/2*20
2ø3/4*80.688/20=8.06=9ø3/4*20
122ø3/8*5.904/20=36.01=37ø3/8*20
Alambre=4.122*3.637=14.991lbs
8varilla de 1 + 4 varillas 3/8
Acero horizontal =Est varilla 3/8@0.20
L=1.5+0.60+4+0.35+0.8-0.05=7.2*3.28pie=23.616pie
A1=8 varillas de 1*23.616*2.67lb*1.10=554.881lbs
A2=4varillas de 3/4*23.616*1.502lb*1.10=156.073lbs
Acero trasversal
#4.30/0.20+1=22.5=23
L=2(0.8-0.05) +2(0.4-0.05) +2(0.15) =2.5*3.28=8.2
A3=23varillas 3/8*8.2*0.376lb*1.10=78.004lb
Estribó interior #23
L=4(0.40-0.025) +4(0.20-0.025) +2(0.15)
Pol= (1.5,0.7) +0.30=1.955*3.28pie=6.412
A4=23varillas 3/8*6.412*0.376lb*1.10=60.996
Σ=554.881+156.073+78.004+78.004+60.996=8849.954/100=8.499 qq

V.H= 4*0.80*0.40=1.28m 3

P= 8.499/1.28=6.625*2=alambre =13.25lbs/m 3

Despiece
8 varillas de 1 *23.616/20=9.446=10varillas 1@20
4 varillas de 3/8 *23.616/20=4.723=5varillas 3/8@20
Est ext. 23*8.2/20=9.43=10varillas 3/8@20
Est int23*6.412/20=7.373=8varillas 3/8@20
Alambre=1.28*13.25=16.96lbs
Acero en x
#= (2.25-0.06) /0.20+1=11.95=12
L= (1.75-0.06) +2(0.20) =2.09*3.28=6.855pies
AX= 12Ø1/2*6.855*0.668lb*1.10=60.444lbs
Acero en Y
#= (1.75-0.06) /0.20+1=9.45=10
L= (2.25-0.06) +2(0.15) =2.49*3.28=8.167pie
Ay= 10Ø3/8*8.167*0.376*1.10=33.778pie
Σ= 60.444*33.778=94.222/100=0.942 qq
V.H=1.75m*2.25m*0.35m=1.378m 3

P=0.942/1.378=0.683*2=alambre=1.366lbs
Despiece
12Ø1/2 *6.855/20=4.113=5 Ø1/2@20
10Ø3/8 *8.167/20=4.083=5 Ø3/8@20
Alambre = 1.366lbs*1.378m =1.882lbs
3
Acero vertical 4Ø3/8 + 4Ø1
Acero trasv: Est Ø3/8@0.20
L= 1.5+0.5+4.5+0.80+0.35-0.05=7.6*3.28=24.928
A1= 4Ø3/8*24.928*0.376*1.10=41.240lb
A2= 4Ø1*24.928*2.67*1.10=292.854
Acero trasversal
4.8/0.20+1=25
L Ester=4(0.5-0.05) +2(0.15) =2.1*3.28=6.888pies
A3= 25Ø3/8*6.888*0.376*1.10=71.221
L Est int=4(0.25-0.025) +4(0.25-0.025) +2(0.15)
Pol= (0.9,0.9) +0.30=1.572*3.28pie=5.156pies
A4=25 Ø3/8*5.156*0.376lb*1.10=53.313
Σ=41.240+292.854+71.221+53.313=458.628/100=4.586qq
V.H= (0.5*0.5*0.45) =1.125m3

P=4.586qq/1.125m3=4.076*2=alambre=8.152lbs
Despiece
4Ø3/8 *24.928/20=4.985=5Ø3/8@20
4Ø1*24.928/20=4.985=5 Ø1@20
25*6.888/20=8.61=9 Ø3/8@20
25*5.156/20=6.445=7 Ø3/8@20
Alambre= 1.125m3*8.152lbs=9.171lbs
Acero horizontal: Est Ø3/8@ 0.15
Acero Vertical 12 Ø1
L= 1.5+0.80+4.0+0.35+0.8-0.025=7.425*3.28=24.354pies
A1= 12 Ø1*24.354*2.67lb*1.10=858.332lb
Acero trasversal
4.325/0.15+1=29.833=30
L=3.14*(0.60-0.06) +2(0.15) =1.996*3.28pie=6.548pies
A2=30 Ø 3/8*6.548*0.376*1.10=81.247lb
Est interior #30
L= 4(0.6-0.06) +4(0.15) =2.76*3.28pies=9.052pies
A3=30 Ø 3/8*9.052*0.376lb*1.10=112.317lb
Σ=858.332+81.247+112.317=1051.896/100=10.518qq
V.H=3.14(0.60¿2/4*4=1.130m3
P=10.518qq/1.130m3=9.307*2= alambre=18.614lbs
Despiece
12 Ø1*24.354/20=14.612=15 Ø1@20
30 Ø3/8*6.548/20=9.822=10 Ø3/8@20
30 Ø3/8*9.052/20=13.578=14 Ø3/8@20
Alambre: 18.614lbs*1.130m3=24.198lbs
Acero Vertical 7Ø 3/4+ 5Ø ½
Acero Trasver: EstØ3/8@0.15
L= 1.5+0.6+3.3+0.35+0.8-0.05=6.5*3.28=21.32
A1= 7Ø 3/4*21.32*1.502*1.10=246.574lb
A2=5Ø1/2 * 21.32*0.668lb*1.10=78.329lb
Acero trasversal
#3.6/0.15+1=25
Estibo exterior
L=4(0.60-0.05) +4(0.30-0.05) +4(0.15) =3.8*3.28pies=12.464pies
A3= 25 Ø3/8*12.464*0.376*1.10=128.877
Estribó interior #25
L= 4(0.60-0.05) +4(0.30-0.05) +4(0.15)
Pol= (2.2,1) +4(0.15) =3.016*3.28=9.892pies
A4= 25 Ø3/8*9.892pies*0.376 lb *1.10 =102.283pies
Σ= 246.574+78.329+128.877+102.283=556.063/100=5.560qq

V.H= (0.60*0.30) +(0.30*0.30) *0.35=0.18+0.09*03.3=0.891m 3

P=5.560qq/0.891m 3=6.240*2=alambre=12.48lbs

Despiece
7Ø 3/4*21.32/20=7.462=8 Ø 3/4@20
5Ø1/2*21.32/20=5.33=6 Ø1/2@20
25 Ø3/8*12.464/20=15.58=16 Ø3/8@20
25 Ø3/8*9.892/20=12.365=13 Ø3/8@20

Alambre=12.48lbs*0.891m 3=11.119lbs
Acero Vertical=3/4@0.20
Acero Horizontal = 1/2@0.25
Re gral= 0.025
Acero vertical #=14.95+2(7.325) +2(5) +2(8.35-0.05) /.20+1=281=282
#= (15+6+8.35/.20) +1=147.75*2=295.5=296
L= 4.50+0.35+0.35+0.30-0.05-0.025=5.425*3.28=17.794pies
A1= 296 Ø3/4*17.794pies*1.502lb*1.10=8702.177lbs
Acero horizontal #= (4.8/0.25) +1=20.2=21
L= 2(15-0.05) +2(6.70-0.05) +2(8.35-0.05) =59.8*3.28=196.144pies
A2= 21 Ø1/2*196.144pies*0.668lb*1.10=3026.658lbs
Σ=8702.177+3026.658=11728.835/100=117.288qq
V.H= (29.35*4.50*0.35) =46.226m3
P= 117.288qq/46.226m3=2.537m3*2=alambre=5.074lbs
Despiece
296 Ø3/4*17.794/20=263.351=264 Ø3/4@20
21 Ø1/2*196.144/20=205.951=206Ø1/2@20
Alambre= 5.074lbs*46.226m3=234.550lbs
Acero vertical Ø1/2@0.15
Acero horizontal Ø 1/2 @0.20
Acero Vertical
#= π*(3.60-0.06) + π (3.0-0.05) =139
(π*3.54) /0.15+1) =76+ (π*2.95) /0.15+1=63=139
10/3.28=3.048
L=3.048+0.35+0.35+0.20-0.03-0.05=3.868*3.28=12.687
A1= 139Ø1/2*12.687*0.668*1.10=1295.814lbs
Acero Horizontal
3.34/0.20+1=17.7=18
L= π*3.54 + π* 2.94= 11.121+9.236=20.35*3.28=66.770
A2= 18 Ø3/8*66.770*0.376*1.10=497.089lbs
Σ= 1792.903/100=17.929qq
V.H= π (3.6¿2/4=10.178- π (3) = 9.424=0.754*3.04=2.292m3
P= 17.92/2.292=7.818*2=alambre = 15.636lbs
Despiece
139 Ø1/2*12.687/20=88.174=89 Ø1/2@20
18 Ø3/8*66.770/20=60.093=61 Ø3/8@20
Alambre= 15.636*2.292=35.83lbs