Professional Documents
Culture Documents
ABC Drugs HSE Report
ABC Drugs HSE Report
ABC Drugs HSE Report
Executive Summary
2. Factory Information Sheet
3. HSE Management System
4. Fire Safety Management
5. Plant Site Safety
6. Emergency response & trainings
7. Security Control
8. Miscellaneous Points
9. Risk Rating
10. Graphical Representation
11. Conclusion
1. There is no Hazard Identification study or process specific safety study conducted for
individual processes. The BPR document covers the quality related aspects but does not
cover the hazards associated with the activities. A dedicated Hazard Identification and risk
assessment must be conducted for all the processes and the same must be mapped to
prepare SOPs for individual activities.
2. The fire detection system did not cover all the areas and it is not possible to add further
detectors to the wireless fire detection system. A FRLS wired fire detection system must be
provisioned with an addressable fire alarm panel provided in the security control room. All
the areas mentioned in the report must be covered while planning for detection system.
3. Health and Safety trainings were limited and were covered as part of other trainings. During
the site visit, some workers were unaware of the hazards associated with the chemicals they
were handling. A dedicated HSE training calendar must be prepared covering electrical
safety trainings, chemical handling trainings, hazardous material handling trainings, Static
charge hazards and control measures trainings and BBS trainings (Top to lower
management) as separate.
4. Over storage of chemicals were observed in the Badminton court area and Liquid chemical
storage area. The storage of some chemicals was observed outside directly under sunlight
due to lack of space. Storage of chemicals must be moved to another location or warehouse
with proper detection and suppression system.
5. An emergency response plan was available, however was found to be incomplete and did
not cover all the emergencies’ scenarios in the plant. The emergency response plan must be
updated as mentioned in the ensuing report covering all possible scenarios.
6. Firefighting systems were under capacity and only a jockey pump is available for firefighting.
There are only 4 hydrant points provided covering the complete plant and there are no
internal hydrant points for the plant area. A dedicated main pump and DG pump of
sufficient capacity must be available for firefighting as mentioned in the ensuing report. The
number of hydrant points must also be increased and provision for internal hydrant points
and first aid hose reels for the plant area.
1. HSE Management System
Legal
Sr. Reference/Other
Area/Process Observation Objective Evidence Criticality Recommendation
No. requirement
(If Any)
A basic health and safety 1. The policy statement contains the
policy statement and manual vision of the plant. Specific targets or
has been made commonly for achievements can also be mapped in
both the units. Some of the the policy statement for each year
observations are as follows: and can be updated every year.
1. The health and safety A health and safety policy manual
policy manual are must have the following sub
incomplete and can be segments:
improved. The policy ISO 45001: Health a. Statement of intent mentioning the
manual did not cover the and safety visions and goals of the management
sections for the process Management
towards health and safety, it must be
Health and safety system
1 safety identification and Low counter signed by the top
Policy the hazards associated
IS 18001: Health management for accountability
with the process in the and Safety b. Roles and responsibilities of all the
plant. Management employees must be mentioned in the
2. The health and safety System manual
policy were not displayed
c. Arrangement sections: All the Safe
at prominent locations like
operating procedures including
at the entrance of the
plant and reception area. hazards associated with individual
activities and control measures,
procedure to conduct HIRA, EAIA,
Accident investigation, Management
of change etc. must be mentioned in
the manual
2. The health and safety policy should be
displayed at prominent locations like
at the entrance of the plant and
reception area to show the
management towards health and
safety.
People:
Training must be provided to the selected
members of the health and safety team
on Hazard Identification and risk
assessment.
Awareness to the supervisors and
operators on the identification of risks
associated with their respective activities
like hot work, work at height etc.to be
provided.
Environmental Aspect Impact System:
study has not yet been done 1. An environment aspect impact
for the facility. analysis must be carried out.
2. It must quantify the impact on the
Environmental Environmental
environment due to different
4 aspect impact Low Protection Act,
analysis ISO 14001 activities.
3. Risk rating must be provided both
before and after the application of
control measures.
People:
Training on Accident investigation can be
provided to selected people – to identify
root causes and methodology to device
control measures from why-why analysis.
People:
The concerned HODs with their team
members must be trained on the
developed procedures.
People:
The Emergency response team and
Emergency management team of
individual identified zones must be
briefed about their roles &
responsibilities. Simulation drills to be
planned and conducted for each zones
covering all identified scenarios in the
ERP.
People:
Safety sensitisation training needs to be
provided to the maintenance team on the
importance of firefighting equipment and
maintenance.
People:
The Department In charge needs to make
ensure that the maintenance of fire
extinguisher is based on the following:
Location in designated place
No obstruction to access or visibility
Operating instructions on nameplate
legible and facing outward
Safety seals and tamper indicators
not broken or missing
Fullness determined by weighing or
lifting
Examination for obvious physical
damage, corrosion, leakage, or
clogged nozzle
Pressure gauge reading or indicator
in the operable range or position
Condition of tyres, wheels, carriage,
hose, and nozzle checked (for
wheeled units).
Any observation identified must be
immediately reported to the safety
department
4 Smoke detectors Information: System:
and Fire Alarm Currently, the premise is To avoid such issues there are two
Control panel equipped with the wireless methods:
type detection system 1. It is recommended to replace the
wireless detection unit system with a
Observation: FRLS cable wired fire detection
There are many cons of these
system integrated with a fire alarm
wireless detection units:
control panel that must be placed in
Additional number of
the security room (Emergency
detectors cannot be added
Control Room) for 24 x 7 monitoring
to the loop, in case of an
expansion and repeater panel at the reception.
2. An addressable panel is
Battery Run out issues in recommended considering the
the detection unit number of detectors required.
Intermixing of detection Manual call points, Smoke detectors
unit with the base and can be connected to the same panel
resulting in wrong and hooters.
indication in the panel
IS 2189: 2009
Wireless alarm range
Selection,
restriction and Power Installation and
backup Maintenance of
Monitoring of detection High Automatic Fire·
units Detection and
1. There is no detection Alarm System-
system provisioned in the Code of Practice
electrical panel rooms,
servo room, office areas,
record rooms, UPS &
Battery storage rooms, 3. The fire alarm panel must be
Raw Material storage connected with the fire dampers in
room 1 & 3.
the ducts, access control doors &
2. AHU unit in plant area is
AHU supplying multiple floors. In case
not connected to fire
of an emergency, the fire dampers
detection system
must be in closed position and AHUs
3. Heat detectors were not
provisioned in the liquid eeshould be turned off to prevent the
chemical storage area. spread of smoke.
4. Manual call point was not 4. Access control doors must be free to
installed in the storage open for easy evacuation during an
room in block 58. emergency
(Badminton Court) 5. Heat Detectors are suitable for clean
5. The existing fire alarm burning fires, such as those involving
panel is not integrated
with the access control certain flammable liquids. Areas
doors in the plant areas subject to smoke, steam, dust or dirt
and the fire dampers or during normal use, fire that evolves
the AHU. heat and flame rapidly, suitable for
6. A log register is not rooms where heat producing
maintained at the security equipment like DG Area, class A
room to record the alarms
chemical storage, storage containing
and false alarms.
any flammable chemicals,
kitchen/pantry.
6. Smoke detectors can be provisioned
in the electrical panel rooms, record
rooms, UPS & battery storage rooms
and office areas.
7. Manual call points must be
provisioned in all the building blocks
such as QC building & storage
building in block number 58.
(Badminton court)
8. The fire alarm panel must be
connected with the access control
doors in the plant area and the Air
Handling units. As soon as the fire is
detected, the access control doors
must disengage, and the air handling
units must turn OFF automatically to
prevent smoke from travelling to
different floors.
9. A log register must be available to
record all the alarms, to identify
areas with maximum false alarms. It
will help in providing permanent
solutions to the false alarm.
Weekly Inspection
a. Once a week, at least one trigger
device or end of line switch on one
zone circuit should be operated to
test the ability of the control, further
indicating equipment to receive a
signal and to sound the alarm and
operate other warning devices.
b. A visual examination of the battery
and connection should be made to
ensure that they are in good
condition.
c. Any defect noticed should be
recorded in the logbook and reported
to the responsible person, and action
should be taken to correct it.
Manual Call Points and Alarms
Every floor area must be provisioned with
Manual call points and fire alarms
installed near the exits and staircases.
These must be integrated to a common
fire alarm panel which can be installed in
the security control room at main gate.
5 Exit Doors and 1. Only a single exit is Medium System:
Evacuation available from the QC & 1. Provision for alternative exit route
Office building blocks from QC building
2. The emergency exit from 2. The exit route from the second floor,
the second floor in plant 2 (plant-2) must have sufficient width
was observed to be for the movement of people to the
obstructed due to AHU exit staircase.
ducts and other utilities. 3. All the exit to be identified with
NBC 2016, Part 4
3. Photoluminescent floor Fire and Life photoluminescent type exit marks and
marking not available for Safety kept unobstructed. The routes to the
exit routes.
exits can be provided with photo
4. Photoluminescent
luminescent floor markings too.
evacuation maps were not
displayed anywhere at
prominent locations in the
plant.
People:
The Department In-charge should be
made responsible to ensure that all the
exits are kept unobstructed and
unlocked.
People:
The firefighting team must be trained in
the use of SCBA set.
3. Plant Site Safety
People:
Training on handling chemicals and
dozing chemicals must be provided based
on the MSDS. Training on hazards
associated with the chemicals must also
be known to the ETP operators.
People:
Personnel responsible for CCTV must be
trained on emergency/security related
importance of CCTV like- relevance of
probing any incident by visualising CCTV
footage, reporting the CCTV breakdown
etc.