Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

DARoberts, LLC

GEARBOX  FAILURE  INVESTIGATION  


P ORTSMOUTH ,   R HODE   I SLAND   A AER   1 500/77   W IND   TURBINE  

Report  Number:   DAR-­‐EN-­‐20120926  


Principal  Investigator:   Don  Roberts  
Business  Address:   4829  NE  75th  St  
Seattle,  WA  98115  
don@daroberts-­‐llc.com  

For:   Portsmouth,  Rhode  Island  


Contact:   Mr.  Gary  Crosby  
Title:   Acting  Town  Planner  
Business  Address:   2200  E.  Main  Road  
Portsmouth,  RI    02871  

Revision   Description   Date   By  

ø   Final  Release   27  September  2012  

A   Additional  Information   14  October  2012  

CONFIDENTIAL  
This  document  contains  business  and  technical  information  and  data  is  confidential  and  proprietary  to  
Portsmouth,  Rhode  Island.    Any  unauthorized  publication  or  disclosure  of  such  information  to  any  person,  or  
unauthorized  use  of  such  information  without  the  express  written  consent  of  Portsmouth,  Rhode  Island  is  
strictly  prohibited.  
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

TABLE  OF  CONTENTS  


Executive  Summary  ........................................................................................................................................................................  iii  
Introduction  ..........................................................................................................................................................................................3  
Background  ......................................................................................................................................................................................3  
Final  Scope  of  Work  .....................................................................................................................................................................3  
Visual  Inspection......................................................................................................................................................................3  
Gearbox  Inspection  .................................................................................................................................................................3  
SCADA  Data  Review................................................................................................................................................................4  
Generator  Alignment  Check  ...............................................................................................................................................4  
Service  Record  Review  .........................................................................................................................................................4  
Reporting  .....................................................................................................................................................................................4  
Items  Removed  From  Preliminary  Scope  of  Work  .................................................................................................4  
Findings  ..................................................................................................................................................................................................4  
Visual  Inspection......................................................................................................................................................................4  
Gearbox  Inspection  ..............................................................................................................................................................  11  
SCADA  Data  Collection  .......................................................................................................................................................  15  
Generator  Alignment  Check  ............................................................................................................................................  17  
Service  Record  Review  ......................................................................................................................................................  17  
Financial  Considerations  ............................................................................................................................................................  18  
Other  Observations  ........................................................................................................................................................................  20  
Ice  Throw  ..................................................................................................................................................................................  20  
Blades..........................................................................................................................................................................................  20  
Yaw  Errors  ...............................................................................................................................................................................  20  
Conclusion  ..........................................................................................................................................................................................  20  
Appendix  A  Ȃ  Gearbox  borescope  Inspection  Report  ..................................................................................................  22  
Appendix  B  Ȃ  Reference  Documents  .....................................................................................................................................  23  
1.   Dz ‡Š‡††‹‰ƒ† ‡Š”‘™Ȃ  ‹•ƒ†‹–‹‰ƒ–‹‘dzǡƒ˜‹†ƒŠŽǡŠ‹Ž‹’’‡ ‹‰—‡”‡ǡ‹†
Application  Engineering,  GE  Energy,  Greenville,  SC  ................................................................................................  23  
2.   ‹†‡ ‘‡†‡†”ƒ –‹ ‡ǡDzͳ͵Ǥ‹†‡”‰›”‘Œ‡ –•‹‘Ž†Ž‹ƒ–‡•dzǡ†‹–‹‘ʹͲͳͳ
  23  
Appendix  C  Ȃ  Contacts  ..................................................................................................................................................................  24  
   

  ii    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

LIST  OF  FIGURES  


Figure  1  -­‐  Gearbox  Installation  Configuration  ....................................................................................................................5  
Figure  2  -­‐  Blade  Vortex  Generators  ..........................................................................................................................................7  
Figure  3  -­‐  Low  Speed  Shaft  Spark  Gap  (one  of  two  shown)  .........................................................................................8  
Figure  4  -­‐  GasTOPS  Wear  Particle  Monitor  ..........................................................................................................................9  
Figure  5  -­‐  Vibration  Switch  ...........................................................................................................................................................9  
Figure  6  -­‐  Site  of  Portsmouth  Turbine  .................................................................................................................................  10  
Figure  7  -­‐  Water  Tank  Near  Turbine  ....................................................................................................................................  10  
Figure  8  -­‐  Highway  24  cut  Northwest  of  Turbine  ..........................................................................................................  11  
Figure  9  -­‐  Gearbox  Data  Plate  ...................................................................................................................................................  11  
Figure  10  -­‐  Gearbox  Internal  Configuration......................................................................................................................  12  
Figure  11  -­‐  Gearbox  Section  Drawing  ..................................................................................................................................  12  
Figure  12  -­‐  Output  Shaft  Seal  ....................................................................................................................................................  13  
Figure  13  -­‐  Gearbox  Housing  Flange  Holes  .......................................................................................................................  13  
Figure  14  -­‐  First  Planetary  Stage  Ring  Gear  Damage  ...................................................................................................  14  
Figure  15  -­‐  Second  Planetary  Stage  Ring  Gear  Damage  ..............................................................................................  14  
Figure  16  -­‐  Top  Faults  by  Frequency  ....................................................................................................................................  15  
Figure  17  -­‐666,  548,  824,  and  536  Fault  History  ...........................................................................................................  16  
Figure  18  -­‐  Gearbox  Bearing  &  Oil  Tempterature  Trend  ...........................................................................................  17  

  iii  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

EXECUTIVE  SUMMARY  
The  Portsmouth  wind  turbine  gearbox  has  suffered  a  significant,  premature  failure  of  the  first  and  
second  planetary  stages.    The  gearbox  must  be  replaced  in  order  to  return  the  turbine  to  service.  

The  failure  occurred  after  3  years  of  operation  despite  a  design  life  of  20  years.  Total  operating  time  
on  the  turbine  is  approximately  21,000  hours,  and  total  production  in  accordance  with  the  
production  meter  is  9,898  MWh.  Depending  upon  future  gearbox  reliability,  the  cost  of  one  or  more  
replacements  may  exceed  the  potential  future  profit  for  the  life  of  the  turbine.  Therefore,  a  clear  
understanding  of  the  root  cause  of  failure  and  the  reliability  of  the  turbine  moving  forward  is  
critical  to  Portsmouth.    

Due  to  the  extent  of  the  damage,  replacement  is  most  likely  preferable  to  repair,  depending  upon  
repair  vs.  replacement  cost.  

The  root  cause  of  failure  was  not  determined  during  this  investigation.    Several  potential  causes  
were  ruled  out  as  follows:  

x Structural  damage  to  critical  support  structure  or  looseness  of  components  such  as  blades,  
hub,  tower  foundation,  and  generator  
x Generator  misalignment  
x Blade  exterior  condition  such  as  cracks,  delamination,  or  missing  vortex  generators  
x High  frequency  of  yaw  error  exceeding  10  degrees  (nacelle  direction  vs.  prevailing  wind  
direction  

Possible  root  causes  of  failure  that  cannot  be  confirmed  or  ruled  out  are  categorized  as  follows:  

x High:  Gearbox  manufacturing  error  with  respect  to  assembly  quality  and  choice  of  materials  
and  specificationsȄcomplete  teardown  inspection  is  required  as  well  as  review  of  design  
and  build  records  
x High:  Gearbox  design  error  with  respect  to  structural  stiffness  of  housing-­‐-­‐  analysis  
verification  required  
x Low:  Wind  turbine  support  structural  stiffnessȄanalysis  verification  required  of  unique  
ring  mount  design  
x Low:  Pitch  asymmetry  due  to  incorrect  blade  offsets  
x Low:  Service  quality,  especially  after  May  2011.  However,  failure  to  identify  failure  in  a  
timely  manner  resulted  in  unplanned  failure  and  extensive  gearbox  collateral  internal  
damage.  
x Low:  SitingȄpossible  wind  shear  from  freeway  cut.    Nearby  47  foot-­‐tall  water  tank  is  not  a  
likely  contributor.  

The  gearbox  configuration  is  not  conventional  by  US  industry  standards.    The  make  and  model  of  
gearbox  have  a  poor  track  record,  with  at  least  3  of  5  installed  in  the  US  having  gearbox  failures  

  1    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

within  the  first  3-­‐4  years  of  operation.  Supply  of  replacement  gearboxes  is  likely  to  be  limited,  and  
the  turbine  is  destined  to  become  an  orphan  due  to  bankruptcy  of  the  manufacturer  (AAER)  and  
sluggish  support  from  the  designer  (AMSC/Windtec).    AAER  purchased  a  license  to  build  the  1650  
kW  AMSC/Wintec  design  but  built  a  1500  kW  machine  instead.  

The  AAER  1500/77  60Hz  wind  turbine  or  any  other  AMSC/Windtec  design  with  the  JaKe  PPSC  
1290-­‐  A120  gearbox  never  received  a  Statement  of  Conformity  or  Type  Certificate  from  a  world-­‐
recognized  certification  organization  such  as  Germanischer-­‐Lloyd  or  Det  Norske  Veritas.  Therefore,  
the  turbines  did  not  receive  the  level  of  verification  and  third  party  engineering  review  other  
certified  wind  turbines.  

The  water  tank  to  the  North  may  wake  the  lower  arc  of  the  rotor  creating  asymmetric  rotor  loads,  
and  the  cut  for  Highway  24  may  create  increased  vertical  shear  across  the  rotor  creating  
asymmetric  rotor  loads.    These  conditions  are  dependent  upon  the  frequency  of  operation  and  wind  
speeds  in  the  direction  of  the  features.  The  ATM  site  suitability  report  did  not  provide  a  Wind  Rose  
as  part  of  the  wind  resource  assessment,  nor  did  it  mention  effects  of  tower  or  highway.  

Several  significant  opportunities  to  identify  premature  gearbox  failure  were  missed  from  as  early  as  
June  2011  through  March  2012.      

x Failure  to  monitor  GasTOPS  wear  particle  monitor  data  


x Failure  to  collect  oil  samples  in  Fall  2011  for  analysis,  and,  possibly,  failure  to  replace  gear  
oil  filter  element  and  inspect  housing  for  wear  debris.  
x Failure  to  monitor  SCADA  data  for  key  gearbox  health  trends  such  as  gearbox  bearing   and  
oil  temperatures  

While  early  detection  cannot  prevent  failure,  it  can  provide  an  opportunity  to  delay  the  failure,  plan  
for  replacement  and  reduce  collateral  damage  from  a  single  component  failure.    Collateral  damage  
can  significantly  increase  the  cost  of  gearbox  repair  or  result  in  the  need  to  purchase  a  new  
gearbox.  

Recommendations:  

1. Perform  financial  feasibility  study  for  gearbox  replacement  options,  including  identical  
gearboxes  to  failed  unit,  remediated  but  similar  models,  and  alternative  models  
2. Perform  forensic  teardown  of  failed  gearbox  to  narrow  down  root  cause  of  failure.  
3. Perform  blade  pitch  calibration  and  determine  blade  offsets  as  a  potential  root  cause  
4. Issue  RFQ  for  qualified  service  providers  with  skilled  senior  level  troubleshooters  
5. Obtain  clear  understanding  of  relationships  with  JaKe  and  AMSC/Windtec  with  respect  to  
orphaned  product  support  and  cost.  
6. Inspect  blades  and  determine  repair  costs  prior  to  gearbox  replacement  in  order  to  perform  
complete  financial  analysis  for  return  to  service  of  the  turbine  

   

  2    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

INTRODUCTION  
The  town  of  Portsmouth,  Rhode  Island  (Portsmouth)  commissioned  a  new  AAER  1500-­‐77-­‐65  1.5  
Megawatt  wind  turbine  on  March  24,  2009.    On  May  18,  2012,  significant  amounts  of  metal  were  
found  in  the  gearbox  oil  filter  housing  and  significant  internal  damage  was  observed  with  a  
borescope.    The  filter  element  was  replaced  on  May  25,  and  the  turbine  was  returned  to  service.  
The  turbine  was  removed  from  service  on  June  18,  2012  after  significant  additional  metal  was  
discovered  in  the  filter  housing.  

BACKGROUND  
The  AAER  1500-­‐77  was  manufactured  by  AAER  Wind  Energy  of  Quebec,  Canada.    AAER  declared  
bankruptcy  shortly  after  commissioning,  and  all  service  contracts  and  warranties  through  the  OEM  
were  lost.  AAER  built  the  turbines  under  license  from  AMSC  Windtec  ,  who  has  licensed  similar  
designs  to  several  manufacturers  around  the  world.    According  to  Alexander  Groeber,  Director  of  
Ž‘„ƒŽ‡”˜‹ ‡ˆ‘”ǡDzWe  are  not  100%  sure  what  AAER  has  finally  built  Ȃ  they  have  bought  a  
Ž‹ ‡•‡ˆ‘”ͳ͸ͷͲƒ†Šƒ˜‡„—‹Ž–ƒͳͷͲͲǥ•‘™‡ ƒǯ–„‡•—”‡ƒ„‘—t  the  whole  detailed  turbine  
configuration.dz  

Anecdotal  information  indicates  several  thousand  are  in  operation,  mostly  with  a  different  model  of  
gearbox.      In  2009  and  2010,  five  similar  AAER  1500-­‐77  wind  turbines  with  identical  gearboxes  
were  installed  in  the  United  States1.    Since  then,  at  least  3  of  the  5  turbines  have  experienced  
gearbox  failures  (one  is  operating  at  1000kW  peak  output  due  to  grid  limitations).    The  design  
lifetime  of  the  turbine  is  20  years,  including  the  PPSC  1290-­‐A120  gearbox  manufactured  by  Jahnel  
Kestermann  (JaKe)  of  Germany.      

In  order  to  return  the  wind  turbine  to  service,  the  gearbox  must  be  replaced  or  repaired  at  
significant  cost  to  Portsmouth.  The  gearbox  warranty  was  24  months  [from  delivery?],  and  the  
failure  was  discovered  at  approximately  38  months.  The  gearbox  manufacturer  has  offered  
replacement  gearboxes  at  a  significantly  discounted  price  while  supplies  last.  

DA  Roberts,  LLC  (DAR)  performed  a  site  inspection  and  obtained  documents  and  data  for  review  on  
August  28  and  29,  2012  to  confirm  the  condition  of  the  gearbox  and  to  look  for  root  causes  of  
failure.  

FINAL  SCOPE  OF  WORK  

VISUAL   INSPECTION  
The  purpose  of  the  visual  inspection  was  to  become  familiar  with  the  installation  configuration,  
review  blade  pitch  settings,  and  identify  gear  oil  leaks,  loose  hardware,  or  other  indications  as  
possible  factors  in  gearbox  failure.  

GEARBOX  INSPECTION  

                                                                                                                         
1  Barstow,  CA  (1,  operating  at  1000kW  peak  output  due  to  grid  limitations),  Tehachapi,  CA  (2),  Templeton,  

MA  (1)  

  3    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

The  purpose  of  the  borescope  inspection  was  to  inspect  the  internal  condition  of  the  gearbox  and  
obtain  representative  photographs  of  each  gear  and  bearing  that  is  accessible.  

SCADA  DATA  REVIEW  


Ten-­‐minute  SCADA  data  was  requested  for  at  least  5  days  per  month  since  January  2012  in  order  to  
identify  trends  in  turbine  operating  data  that  might  provide  evidence  of  the  onset  of  failure  or  
operating  conditions  that  may  have  contributed  to  gearbox  failure.    The  review  was  limited  to  error  
codes,  gearbox  operating  data,  and  yaw  performance.  

GENERATOR   ALIGNMENT   CHECK  


An  alignment  check  of  generator  relative  to  the  gearbox  was  performed  in  order  to  identify  an  out-­‐
of-­‐alignment  condition  that  might  have  contributed  to  gearbox  failure  due  to  the  interaction  of  the  
high-­‐speed  shaft  connecting  the  output  shaft  of  the  gearbox  to  the  input  shaft  of  the  generator.    

SERVICE   RECORD   REVIEW  


Service  records  since  commissioning  were  reviewed  to  obtain  insight  into  the  quality  of  service  
provided  leading  up  to  and  the  discovery  process  of  the  gearbox  failure.  Records  include  the  
Commissioning  Report,  Turbine  Logbook,  and  service  provider  work  orders.  

REPORTING  
Upon  return  from  site,  a  draft  letter  report  documenting  findings  and  providing  recommendations  
was  expected  to  be  submitted  within  two  weeks.  

ITEMS  REMOVED   FROM  PRELIMINARY   SCOPE  OF  WORK  


The  final  scope  of  work  removes  two  items,  vibration  analysis  and  oil  sample  analysis,  after  
confirmation  of  the  extent  of  gearbox  damage.    Vibration  analysis  equipment  was  shipped  to  the  
site,  but  not  installed  since  DAR  considered  the  risk  of  structural  failure  to  outweigh  the  benefit.    Oil  
analysis  was  not  necessary  since  the  oil  must  be  replaced,  and  there  is  no  diagnostic  beyond  oil  
samples  collected  in  May  by  the  service  provider.  

FINDINGS  
Findings  are  presented  in  accordance  with  the  scope  of  work,  and  attempt  to  narrow  down  
potential  root  causes  of  failure.  

VISUAL   INSPECTION  
The  visual  inspection  focused  on  potential  mechanical  and  environmental  influences  into  to  
gearbox  failure.    

Installation  Configuration  
The  installation  of  the  gearbox  is  structurally  unique  from  t he  more  common  models  of  turbines  in  
operation  in  the  United  States,  and  worth  investigation  as  a  possible  root  cause  of  failure.    While  it  
is  not  possible  within  the  scope  of  this  effort  to  perform  a  structural  evaluation,  a  search  through  
public  documents  for  industry-­‐accepted  design  review  has  provided  some  useful  information.  

  4    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

In  the  AAER  1500,  the  rotor  is  cantilevered  from  the  gearbox,  which,  in  turn,  is  mounted  to  the  
nacelle  frame  as  shown  in  Figure  1.      The  gearbox  housing  incorporates  an  oil-­‐lubricated  main  
bearing  within  the  housing.    The  nose  casing  is  mounted  to  a  ring-­‐type  mount  through  elastomeric  
elements,  and  non-­‐torque  rotor  loads  and  the  torque  reaction  loads  are  transferred  to  the  tower  top  
through  the  ring-­‐shaped  weldment.    

 
Figure  1  -­‐  Gearbox  Installation  Configuration  

Similar  configurations  have  received  statements  of  conformity  or  been  type  certified   by  both  
Germanischer-­‐Lloyd  (GL)  and  Det  Norske  Veritas  (DNV)  on  similar  designs.2,3,4  However,  there  is  no  
published  record  indicating  the  specific  combination  of  the  AAER  1500/77  with  the  JaKe  PPSC  
1290-­‐A120  nor  any  other  make  of  the  AMSC/Windtec  design  with  the  JaKe  PPSC  1290-­‐A120  has  
any  published  record  of  final  GL  conformity  or  any  type  of  final  certification.  DAR  is  concerned  that  
the  Portsmouth  configuration  is  now  an  orphan  design,  and  without  undue  expense,  a  rigorous  
evaluation  to  determine  conformity  with  widely  accepted  industry  standards  will  not  be  
forthcoming.  The  following  configuration  influences  contributing  to  gearbox  failure  cannot  be  ruled  
out:  

x An  increase  in  rotor  loading  and  mass  as  a  result  of  increasing  the  rotor  diameter  from  70  to  
77m,  resulting  in  higher  overhanging  moments  on  the  gearbox  and  potentially  higher  non-­‐
torque  loading  into  the  gearbox  housing  as  a  result  of  increased  transient  aerodynamic  
imbalance.  
x A  change  of  gearbox  internal  tooth  and  bearing  loading  and  life  expectancy  due  to  a  ratio  
change  to  accommodate  60  Hz  from  the  more  common  50  Hz  configuration  

                                                                                                                         
2  AMSC  WT  1650  60  Hz,  GL  Statement  of  Conformity,  DAA-­‐GL-­‐025-­‐2010,  15  September  2009  
3  Hyundai  HQ  1650,  DNV,  Type  Certificate,  IEC  TC222301-­‐0,  23  September  2011  
4  Fuhrlander  FL  1500/77,  GL  (1999),  Statement  of  Conformity  WT-­‐00-­‐022A-­‐2004,  July  14,  2004  

  5    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

Additional  insight  into  the  gearbox  design  process  was  obtained  by  Portsmouth  in  an  interview  
with  Martin  Venne,  a  former  Technical  Director  for  AAER  and  responsible  for  the  due  diligence  on  
the  1290  gearbox.    At  the  time  Portsmouth  was  procuring  the  turbine,  he  was  in  Germany  at  the  
JaKe  factory.  He  was  not  convinced  JaKe  had  solved  the  bending  problem  in  their  gearbox  to  his  
satisfaction.    He  was  aware  of  two  1281  (first  generation)  gearboxes  that  had  failed  within  one  year  
which  prompted  JaKe  to  reinforce  the  second  generation  (1290)  and  provide  finite  element  analysis  
data  to  demonstrate  they  had  solved  the  problem.  He  was  skeptical  that  they  had  made  the  case,  
called  into  question  some  of  the  assumptions  in  their  study,  and  quite  pointedly  stated  his  
conviction  that  the  root  cause  of  our  gearbox  failure  was  lack  of  reinforcement  in  the  gearbox  to  
accommodate  high  bending  loads.            

No  other  significant  configuration  differences  in  the  Portsmouth  turbine  were  noted  that  could  
potentially  contribute  to  gearbox  failure.    

Blade  pitch  s ettings  


Wind  turbine  blades  are  airfoils  that  generate  varying  lift  depending  upon  the  angle  of  the  blade  
chord  line  relative  to  the  wind.    Ideally,  all  blades  are  installed  and  collectively  pitched  to  operate  at  
identical  angles.    Transient  conditions  within  the  design  envelope  do  exist  where  each  blade  may  
create  different  lift  forces,  resulting  in  asymmetric  loading  of  the  rotor:  these  are  considered  
normal  loads  with  the  exception  of  extreme  site  conditions  that  exceed  the  IEC  wind  class  the  
turbine  was  designed  to.      

Asymmetric  load  can  impart  bending  moments  into  the  low  speed  shaft,  and  in  the  case  of  the  PPSC  
1290  design,  into  the  gearbox.    Shaft  bending  can  result  in  uneven  load  distribution  on  bearings  and  
gear  teeth  in  the  1st  planetary  stage  of  the  gearbox  as  a  result  of  bearing  clearances,  and  may  cause  
structural  deflections  that  also  affect  bearing  and  gear  load  sharing.    While  verification  of  design  
loading  against  operating  loads  is  well  beyond  the  scope  of  this  investigation,  one  potential  cause  
for  constant  asymmetrical  loading  is  incorrect  blade  indexing.    When  the  blades  are  initially  
installed,  the  pitch  system  must  be  calibrated  by  measuring  blade  offsets  from  zero  using  pitch  
index  plates  on  the  blades  and  entering  the  offsets  into  the  controller.    A  visual  check  of  the  current  
pitch  settings  was  made  and  recorded  as  shown  in  Table  1.  From  the  data,  it  appears  there  may  be  a  
pitch  imbalance;  however,  upon  review  of  commissioning  documents,  a  very  specific  procedure  is  
outlined  in  section  110.2  (page  36)  of  the  Installation  Commissioning  document  provided  to  
Portsmouth  during  commissioning.  DAR  recommends  Portsmouth  authorize  and  witness  an  
experienced  service  team  to  execute  the  pitch  calibration  procedure  per  the  instructions  and  note  
the  new  offset  values.    Allowable  offset  variances  should  be  obtained  from  AMSC/Windtec.    As  a  
result  of  the  pitch  inspection,  pitch  asymmetry  due  to  pitch  differences  between  b lades  cannot  be  
ruled  out  as  a  potential  influence  into  gearbox  failure.      

Table  1  -­‐  Pitch  Index  Check  

Blade   Commissioning   Blade  Index  check  29  Aug  12   Pitch  difference     Blade  position  
Offset  April   29  Aug   29  Aug  
2008  
1   -­‐1.6   .25  left  (CW  rotation)  of  mark   -­‐   Up  left  looking  
s/n  156   forward  

  6    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

2   -­‐2.7   .4  left  (CW  rotation)  of  mark   +  .15     Up  right  looking  


s/n  160   left  of  1   forward  
3   -­‐2   1.0  left  (CW  rotation)  of  mark   +  .75     down  
s/n  158   left  of  1  
 
Blade  Condition  
The  blades  were  photographed  from  the  ground  using  a  Canon  50D  digital  SLR  with  a  17-­‐50mm  
zoom  lens.    Images  were  reviewed,  and  no  significant  defects  such  as  lightning  strikes,  
delamination,  or  missing  vortex  generators  ( Figure  2)  were  noted.  The  surface  condition  of  the  low  
pressure  shell  aft  of  the  vortex  generators  and  the  trailing  edges  is  very  rough.    While  beyond  the  
scope  of  this  report,  DAR  strongly  encourages  a  thorough  blade  inspection  from  the  manufacturer  
(LM  Glasfiber)  or  a  qualified  service  provider.  

 
Figure  2  -­‐  Blade  Vortex  Generators  

Mechanical  Looseness  
Inspection  of  the  following  hardware  indicated  periodic  partial  torque  tests  were  performed,  and  
no  loose  or  missing  hardware  that  could  induce  abnormal  vibration  into  the  drivetrain  was  found.  

1. Blade  attach  bolts  


2. Hub  attach  bolts  
3. Tower  foundation  
4. Generator  footings  

Lightning  Protection  System  


An  inspection  of  the  lightning  protection  system  protecting  the  gearbox  from  high-­‐voltage  arcing  
indicates  the  turbine  is  equipped  with  a  robust  spark  gap  system  containing  two  spark  gaps  
grounding  the  rotor  to  the  nacelle  frame.    There  is  no  indication  of  lightning  damage  on  the  blades.  
Therefore,  lightning  damage  has  been  ruled  out  as  a  potential  root  cause  of  gearbox  failure.  

  7    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  3  -­‐  Low  Speed  Shaft  Spark  Gap  (one  of  two  shown)  

Gearbox  Lubrication  and  Filtration  System  


The  lubrication  system  is  an  industry  standard  Hydac  NF  series  pump  and  filter  and  Hydac  fan-­‐
cooled  heat  exchanger.    Hose  condition  and  bend  radii  are  acceptable.  The  desiccant  breather  is  
partially  used,  and  indicates  adequate  absorption  of  incoming  moisture  due  to  the  blue  coloration  
of  the  desiccant  particles  at  the  top  of  the  filter.  

GasTOPS  Wear  Particle  Monitor  


The  GasTOPS  wear  particle  monitor  installation  is  conventionally  located  upstream  of  the  gear  oil  
pump  as  shown  in  Figure  4.  However,  there  is  no  indication  in  the  records  or  the  data  that  the  
monitor  was  detecting  and/or  sending  particle  warnings  to  the  SCADA  system  or  to  Portsmouth.    The  
O&M  service  provider  should  have  been  aware  of  this  monitor  and  should  have  been  monitoring  the  
signal.    Some  installations  of  GasTOPS  monitors  require  logging  into  a  website  published  by  the  
data  collector,  or  data  monitoring  directly  by  GasTOPS.    This  piece  of  equipment  has  a  proven  track  
record  of  failure  detection,  and  could  have  been  extremely  valuable  in  early  detection  of  a  gearbox  
failure  in  progress.  While  the  GasTOPS  system  could  not  have  prevented  a  gearbox  failure,  early  
detection  could  have  provided  sufficient  warning  for  pro-­‐active  investigation  potentially  leading  to  
far  less  internal  gearbox  damage  and  possibly  an  extended  operation  at  reduced  power  until  a  
replacement  gearbox  could  be  secured.    

  8    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  4  -­‐  GasTOPS  Wear  Particle  Monitor  

Vibration  S witch  
The  vibration  switch  is  installed  in  the  turbine  protection  system  to  detect  large  vibrations  in  the  
nacelle  that  could  lead  to  significant  damage  to  the  turbine.    Due  to  the  acceptable  visual  condition  
and  positioning  of  the  switch,  undetected,  extremely  high  vibration  leading  to  gearbox  failure  is  
ruled  out  as  a  potential  influence  in  gearbox  failure.  

 
Figure  5  -­‐  Vibration  Switch  

Turbine  Siting  
Most  wind  farms  are  installed  subsequent  to  a  wind  resource  assessment  and  site  suitability  
analysis.  Site  selection  was  based  upon  a  report  titled  Town  of  Portsmouth,  RI  Wind  Resource  and  
Economic  Assessment  prepared  in  2007  by  Advanced  Technology  and  Management  (ATM).    The  
report  was  summarized  by  the  Portsmouth  Economic  Development  Council  (PEDC)  report   Wind  
Project  for  the  High  School  and  Middle  School  -­‐  A  Feasibility  Study.    According  to  the  Portsmouth  
Economic  Development  Council  (PEDC),  ATM  provided  Dza  detailed  wind  resource  analysis,  a  
detailed  energy  use  analysis,  an  electrical  interconnection  assessment,  and  a  financial  analysisdzˆ‘”
the  final  site  (the  High  School).   ‘”†‹‰–‘–Š‡•—ƒ”›‘ˆ–Š‡”‡’‘”–ǡDzWithin  the  scope  of  

  9    
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

ǯ••–—†›ǡ‘ˆƒ–ƒŽˆŽƒ™•™‡”‡‹†‡–‹ˆ‹‡†–Šƒ–™‘—Ž†’”‡˜‡––Š‡†‡˜‡Ž‘’ment  of  a  wind  turbine  


’”‘Œ‡ –Ǥdz  

Figure  7  shows  the  physical  location  of  the  turbine  relative  to  its  surrounds.  

 
Figure  6  -­‐  Site  of  Portsmouth  Turbine  

While  they  were  not  considered  fatal  flaws  for  a  site  evaluation,  two  noticeable  features  stand  out  
that  cannot  be  ruled  out  as  potential  causes  of  wind  shear  and  subsequent  asymmetrical  rotor  
loading.  

A  water  tower,  shown  in  Figure  7,  is  located  within  600  feet  North  of  the  turbine  base.  The  lower  
arc  of  the  rotor  is  27.5  meters  (90  ft.)  above  the  ground.    The  height  of  the  tower  is  46  feet.  Tower  
waking  can  most  likely  be  ruled  out  as  a  contributing  factor  to  gearbox  failure.      

 
Figure  7  -­‐  Water  Tank  Near  Turbine  

A  freeway  cut  with  a  steep  embankment  is  located  approximately  600  ft  to  the  Northwest  of  the  
turbine.    The  cut  may  induce  wind  shear  into  the  rotor  during  inflow  angles  perpendicular  to  the  
cut.  

  10  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  8  -­‐  Highway  24  cut  Northwest  of  Turbine  

The  ATM  report  does  not  provide  a  wind  direction  frequency  (Wind  Rose).    In  the  course  of  future  
wind  turbine  operation,  additional  wind  resource  assessment  of  the  site  should  be  performed  to  
investigate  shear  influences  on  the  turbine,  and  to  determine  the  need  for  curtailment  in  the  event  
the  geography  adversely  affects  rotor  loading.  

GEARBOX  INSPECTION  
A  detailed  gearbox  inspection  report  is  provided  in  Appendix  A .    This  section  summarizes  the  
findings.      

 
Figure  9  -­‐  Gearbox  Data  Plate  

The  gearbox  is  a  three-­‐stage  planetary  design  with  two  planetary  and  one  parallel  stage  which  is  
offset  to  the  right  looking  towards  the  rotor.  In  total,  there  are  twelve  gears  and  twenty-­‐two  
bearings  producing  an  increase  ratio  of  120:1  to  convert  the  17  RPM  speed  of  the  rotor  to  the  
nominal  generator  speed  of  2000  RPM.  The  oil  capacity  of  the  gearbox  is  685  liters  (181  gallon).    
Figure  10  and  Figure  11  show  the  internal  arrangements.  

  11  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  10  -­‐  Gearbox  Internal  Configuration  

 
Figure  11  -­‐  Gearbox  Section  Drawing  

External  Inspection  
The  external  inspection  did  not  reveal  any  damaged,  loose  or  missing  structural  components.    Oil  
leaks  were  noted  at  the  output  shaft  seal,  and  oil  residue  is  evident  as  far  away  as  the  yaw  deck.    
The  seal  is  partially  dislodged  from  the  shaft  as  shown  in  Figure  12.  According  to  the  service  
technician,  the  seals  slip  out  of  their  seats  despite  repeated  reseating.  

  12  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  12  -­‐  Output  Shaft  Seal  

The  gearbox  housing  has  a  radial  pattern  of  unused  holes.    This  appears  to  be  by  design,  and  
perhaps  the  holes  are  used  in  a  different  installation  configuration,  such  as  a  different  turbine  make.    
Examination  of  the  mounting  configuration  revealed  the  gearbox  is  held  in  the  housing  using  a  
clamping  arrangement  rather  than  the  through-­‐holes  on  the  casing.    The  flange  appears  to  be  solid,  
and  there  is  no  possibility  of  fretting  or  breathing  of  the  structure  within  the  flange  that  would  be  
associated  with  mating  flanges.  

 
Figure  13  -­‐  Gearbox  Housing  Flange  Holes  

Internal  Inspection  
The  gearbox  internal  components  that  could  be  inspected  without  draining  oil  were  viewed  with  a  
GE  XLGo+  borescope  with  a  6.1mm  insertion  tube  with  no  lens  or  a  120  deg,  standard  focus  tip  for  
close-­‐in  imaging.  Inspection  access  was  limited  to  one  access  cover  on  top  of  the  second  planetary  
stage,  and  the  desiccant  breather  fitting  on  the  nose  casing.  

The  inspection  revealed  severe  abrasion  and  deformation  of  the  first  stage  planetary  ring  gear  and  
severe  Hertzian  fatigue  and  debris  damage  to  second  stage  planetary  ring  gear.    The  ring  gears  are  
the  largest  gears  in  the  gearbox.    Failure  of  either  gear  requires  removal  of  the  gearbox  from  the  
turbine.    It  is  possible  the  damage  observed  is  a  secondary  failure  mode,  with  the  primary  failure  

  13  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

mode  a  planet  bearing  failure.    The  appearance  of  the  damage  on  the  ring  gear  indicates  extreme  
structural  deformation  of  the  housing  due  to  overload,  or  cocking  of  one  or  more  planet  gears  after  
complete  failure  of  a  planet  bearing  or  bearings.  

 
Figure  14  -­‐  First  Planetary  Stage  Ring  Gear  Damage  

The  second  stage  ring  gear  appears  to  have  Hertzian  fatigue  damage  as  indicated  by  macropitting  
and  spalling  in  the  lower  portion  of  the  tooth  flank.    The  teeth  also  show  significant  debris  damage  
from  hard  particles  entrained  in  the  gear  mesh.  

 
Figure  15  -­‐  Second  Planetary  Stage  Ring  Gear  Damage  

The  gearbox  is  not  serviceable  in  this  condition,  and  further  operation  of  the  turbine  is  not  
recommended  due  to  the  certainty  of  additional  d amage  to  the  gearbox  and  risk  of  gearbox  housing  
structural  failure.  

  14  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

Typical  causes  of  premature  bearing  failure  in  wind  turbines  are  due  to  poor  lubrication  or  uneven  
load  distribution.  A  forensic  teardown  of  the  gearbox  will  provide  a  much  greater  opportunity  to  
investigate  the  primary  failure  mode  of  the  gearbox.    

SCADA  DATA  COLLECTION  


Several  days  of  10  minute  data  in  2012,  and  an  error  list  since  October  2011  were  reviewed.  

Error  List  
Š‡Ž‡ƒ†‹‰‡””‘” ‘†‡™ƒ•‡””‘”͸͸͸ǡDz ‡ƒ”„‘šŠ‹‰Š•’‡‡†’—’‘’”‡••—”‡dzǡ™Š‹ Šindicates  low  
oil  pressure  after  the  pump  is  switched  to  high  speed  (for  better  cooling).    This  error  causes  the  
turbine  to  shut  down  using  Fast  Stop  mode  (no  mechanical  brake).      

 
Figure  16  -­‐  Top  Faults  by  Frequency  

A  time  trace  of  fault  666  shown  in  Figure  17  indicates  faults  occurring  as  early  as  October,  but  
significantly  increasing  in  February,  2012.    Service  records  and  the  service  provider  (Solaya)  report  
titled  Portsmouth  Rhode  Island  Wind  Turbine  Maintenance  Gearbox  Analysis  (undated,  unsigned)  
indicate  technicians  suspected  and  searched  for  a  faulty  sensor,  ultimately  finding  significant  metal  
in  the  gear  oil  filter  clogging  indicator.    The  filter  housing  was  cleaned,  the  sensor  changed,  and  the  
fault  frequency  decreased  in  late  May  2012.    It  peaked  again  in  early  June.     In  all  likelihood,  the  666  
fault  increase  was  due  to  large  amounts  of  metal  in  the  gear  oil  pump  and  filter  housing,  resulting  in  
a  restricted  supply  pressure  downstream  of  the  pump.  

  15  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  17  -­‐666,  548,  824,  and  536  Fault  History  

Figure  16  and  Figure  17  show  a  high  incidence  of  error  824,  which  is  a  yaw  nuisance  fault,  and  has  
no  bearing  on  the  gearbox  failure.  However,  it  does  prevent  the  turbine  from  yawing  into  the  
prevailing  wind  during  the  extended  downtime  associated  with  the  gearbox  failure.  The  yaw  fault  
should  be  corrected  in  order  to  limit  blade  flapwise  loading,  which  could  cause  blade  damage  in  
high  winds.      

””‘”ͷͶͺǡDz-­‐Ͷ”ƒ‡–‘”ƒ‰‡‡Žƒ›•dzǡ”‡•—Ž–•‹ƒ”ƒ‡Šƒ‹–‘’ǡ‡aning  the  high-­‐speed  


mechanical  brake  is  applied  as  well  as  a  fast  pitching  of  the  blades.    If  the   generator  is  turning  at  
high  speed  when  this  fault  occurs,  application  of  the  mechanical  brake  against  the  interia  of  the  
rotor  could  result  in  significant  internal  loads  in  the  gearbox.    At  least  nine  events  were  recorded  
between  October  3,  2011  and  May  9,  2012.    An  initial  investigation  of  the  10  minute  data  indicates  
most  occurances  happened  at  low  speed  in  low  wind.    Additionally,  the  most  likely  damage  from  a  
high-­‐speed  brake  engagement  is  to  the  high  speed  gear  mesh,  and  the  high  speed  gears  do  not  show  
signs  of  overload.  

10-­‐Minute  SCADA  
This  section  is  limited  to  a  review  of  eight  days  of  data  with  at  least  one  hour  of  winds  6  m/s  or  
higher.  

Key  tags  indicating  gearbox  health  were  reviewed  for  days  operating  at  or  near  rated  power  in  the  
provided  data  set  with  wind  speeds  in  excess  of  12  m/s,  were  December  11,  2011  and  March  27,  
2012  only  data  to  date,  with  the  following  results:  

x Gearbox  bearing  temperature  average  rose  from  69.8  °C  to  81.5°C  
x Gearbox  oil  temperature  average  rose  from  69.3  °C  t o  71.6  °C  
x Ambient  temperatures  for  December  11  were  15  °C  and  March  27  near  0°C  

In  a  trend  analysis  of  eight  days  of  data  with  power  output  greater  than  350  kW,   gearbox  bearing  
temperature  was  providing  predictive  data  indicating  gearbox  health  issues  as  early  as  January,  
well  in  advance  of  the  severe  failure  finally  noted  in  May  and  June.  

  16  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

 
Figure  18  -­‐  Gearbox  Bearing  &  Oil  Tempterature  Trend  

Turbine  operating  conditions  affecting  drivetrain  loads  could  include  yaw  error,  or  the  difference  
between  the  nacelle  direction  and  the  prevailing  wind.    A  review  of  several  days  of  data  indicates  
yaw  error  rarely  exceeds  6  degrees.    In  addition,  there  is  no  clear  correlation  of  increased  tower  
vibration  or  drivetrain  swinging  error  that  correlates  with  yaw   error  in  the  limited  data  set.    It  is  
unlikely  that  the  frequency  of  operation  at  yaw  errors  of  less  than  10  degrees  introduce  loads  that  
exceed  the  design  load  spectrum.  

GENERATOR   ALIGNMENT   CHECK  


A  severely  misaligned  high-­‐speed  shaft  could  potentially  input  bending  loads  into  the  gearbox  
output  shaft,  causing  high  gear  and  bearing  loading.    A  generator  alignment  check  was  performed  
by  a  technician  from  a  different  wind  site  hired  by  the  service  provider  using  an  Easy  Laser  
alignment  tool.  DAR  witnessed  the  alignment  process.    Three  sequential  measurements  were  taken  
during  light  wind  conditions,  and  it  was  determined  by  the  technician  that  the  shaft  was  within  
alignment  tolerances.  

SERVICE   RECORD   REVIEW  


Service  records  for  the  turbine  include  turbine  logbook  entries,  work  orders,  oil  analysis  reports,  
and  special  reports.  It  is  apparent  from  the  records  reviewed  that  the  turbine  received  frequent  
troubleshooting  and  support  from  May  2009  through  May  2010.    From  that  point  on,  records  are  
much  less  frequent.    The  latest  service  provider,  Lumus  Construction,  spent  a  large  amount  of  time  
troubleshooting  666  and  824  error  codes.    The  (Solaya)  report  titled   Portsmouth  Rhode  Island  Wind  
Turbine  Maintenance  Gearbox  Analysis  indicates  scheduled  maintenance  was  provided  in  the  Fall  of  
2011,  and  more  frequent  troubleshooting  began  in  February  2012.    Oil  analysis  reports  for  June  21,  
2011  and  May  17,  2012  indicate  a  significant  change  in  ferrous  content,  per  the  PQ  Index,  and  a  
drop  in  oil  viscosity.    There  should  have  been  a  sample  report  from  Fall  2011,  which  could  have  
indicated  an  increase  in  PQ  Index  well  in  advance  of  the  severe  failure  events.  

Logbook  entries  show  repeated  events  of  error  526,  Gearbox  Oil  Filter  at  High  Speed.    This  error  
cannot  be  found  in  the  current  error  listing,  but  it  may  relate  to  the  666  errors  observed  throughout  
late  2011  and  2012.    If  so,    

  17  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

An  emergency  stop  at  5  m/s  was  conducted  for  training  purposes  on  September  10,  2009.    This  
stop  activates  the  high  speed  brake  and  fast  pitches  the  rotor.  At  5  m/s  the  generator  is  rotating  at  
approximately  1250  RPM.  The  likelihood  that  this  event  resulted  in  gearbox  damage  is  low.  

FINANCIAL  CONSIDERATIONS  
In  order  to  determine  the  profitability  of  continued  turbine  operation  subsequent  to  a  gearbox  
replacement,  two  scenarios  are  considered,  a  three-­‐year  and  a  ten-­‐year  gearbox  life.  The  three-­‐year  
life  estimate  assumes  a  larger  maintenance  reserve  based  upon  current  replacement  costs  divided  
by  three  years.    The  ten-­‐year  estimate  divides  replacement  costs  by  10  years.    Based  upon  the  high  
potential  for  curtailment  of  future  operations  to  protect  the  gearbox  under  potentially  damaging  
conditions,  and  to  protect  the  surrounds  from  potential  ice  throw,  an  availability  estimate  of  92%  is  
used.  No  additional  major  corrective  events  are  factored  in.  At  current  power  purchase  prices,  
annual  revenue  estimate  of  $160,000  is  grossly  insufficient  to  cover  the  costs  of  operation  in  either  
case.  

  18  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

Table  2  Ȃ  Income  (Loss)  Estimate,  3  and  10  year  Gearbox  Life  

Gearbox  Replacement  Costs


One-­‐time  costs  (for  life  of  replacement  gearbox)
Gearbox  (2) $203,000
Removal  and  Installation $407,000
7  days  Crane  stand-­‐by  time  estimate  during  swap-­‐out  of  some  gearbox  parts  to  
new  gearbox  (2  days  =  $1,150) $32,200
Shipping  of  (2)  gearboxes  from  Germany $30,000
shipping  gearbox  to  West  Virginia  and  back $4,000 ??
JaKe  technicians  and  or  support  during  commissioning  (note:  $43,400  already  
included  in  Lumus  quotation  SDOC  6965) $0
Technical  tear  down  of  failed  gearbox  (2-­‐3  days)  with  Gary  Duke  to  witness $6,000
Vibration  System  plus  installation $8,000
CCJ  Off-­‐line  filtration  plus  installation  (or  increased  capacity  Hydac  on-­‐line  filter) $5,000
Subtotal,  gearbox  replacement  cost  (non-­‐recurring) $695,200

Recurring  additional  costs  (annual)


Vibration  monitoring  (with  integrated  GasTOPS  wear  particle  monitoring) $1,200
Borescope  inspection  (includes  scope  rental) $1,300
Oil  filtration $500
Lost  production  for  curtailment  (reduced  power,  ice,  water  tower  sector  mgmt
Indoor  storage  of  spare  Gearbox  with  monthly  rotation $3,600
Independent  Engineering  Support  (i.e.,  DNV  or  GL  Project  monitoring) $8,000
Subtotal,  recurring  additional  annual  costs $14,600

Annual  Revenue  Estimate


Income
Rated  Power 1.5 MW
Capacity  Factor 22%
Availability  Estimate  (includes  curtailment  such  as  reduced  power,  ice,  water  tower  
sector  mgmt) 92%
Production  Hours 1773 h
Gross  Annual  Energy  Production 2660 MWh
Energy  Consumption  (rough  estimate  from  10  minute  SCADA  using  7.2  kWh  avg  
consumption  per  day) -­‐2.63 MWh
Net  Annual  Energy  Production 2662 MWh
Power  Purchase  Price $60 $/MWh
Renewable  Energy  Credit $0 $/MWh
Annual  Production  Revenue $159,730

10  Yr.  Gbx   3  Yr.  Gbx  


Operating  Cost   Life Life
O&M  Service  Contract  (sched  maint.  &  light  correctives) $40,000 $40,000
Unschedule  Maintenance  Reserve  ($10/kWh) $49,220 $164,067
Additional  Gearbox  recurring  O&M  costs $14,600 $14,600
Initial  Loan  Payment  (10  yr.,  $3.1mil,  4%,  Principal  +  Interest) $372,000 $372,000
2nd  Gearbox  Loan  Payment  (10  yr,  $700,000,  4%,  P+I) $85,200 $85,200
Depreciation ? ?
Major  Component  Failure  Insurance ? ?
Total  Annual  Operating  Cost $561,020 $675,867

Net  Revenue ($401,290) ($516,137)


 

  19  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

OTHER  OBSERVATIONS  
ICE  THROW    
The  initial  site  assessment  did  not  adequately  address  the  potential  for  ice  throw,  which  presents  a  
significant  risk  to  inhabited  areas  surrounding  the  turbine.  

Š‡ ”‹–‡”‹ƒˆ‘”‹ ‡–Š”‘™‹•„ƒ•‡†—’‘ƒ ‡‡”ƒŽŽ‡ –”‹ ”‡ ‘‡†ƒ–‹‘–‹–Ž‡†ǡDz ‡Š‡††‹‰


and  Ice  Throw  Ȃ  ‹•ƒ†‹–‹‰ƒ–‹‘dzǡ™Š‹ Š‹•‹ Ž—†‡†‹’’‡†‹šǤ  This  recommendation  takes  
into  consideration  the  ice  thrown  from  the  blades  as  a  result  of  rotation.      

The  recommended  ice  throw  calculation,  1.5  *  (hub  height  +  rotor  diameter),  indicates  a  minimum  
safe  distance  of  213  meters  (699  feet).    Per  Figure  6,  Highway  24,  portions  of  the  High  School  and  
several  houses  fall  within  this  distance.      

BLADES  
The  LM  34.5  blades  are  identical  to  blades  used  on  other  1.5  MW  wind  turbines,  which  have  had  a  
history  of  manufacturing  defects  and  remediation  for  limited  portions  of  the  production  run  
approximately  around  the  time  the  Portsmouth  blades  were  manufactured.    Portsmouth  should  
contact  LM  as  soon  as  practical  for  a  blade  inspection  and  serial  number  check  against  blade  serial  
numbers  with  known  manufacturing  errors.  

YAW  ERRORS  
The  824  yaw  fault  should  be  corrected  immediately  in  order  to  allow  the  turbine  to  align  with  the  
wind.    High  winds  acting  on  the  blades  in  a  flapwise  direction  could  result  in  blade  structural  
damage.    In  discussions  with  Windland  technicians,  the  fault  frequency  can  be  reduced  significantly  
by  increasing  yaw  pad  pressure  on  the  slewing  ring  until  Yaw  Power  is  5-­‐6  kW  (or  exceeds  the  
alarm  threshold  in  the  controller  software).    One  other  operator,  Templeton  Municipal  Light  and  
Water,  reports  AMSC  changed  the  parameter  settings  in  the  software.  

CONCLUSION  
The  following  conclusions  should  be  taken  into  consideration  during  discussions  involving  
continued  operation  of  the  turbine:  

1. The  AAER  1500/77-­‐65m  turbine  is  an  orphan  turbine  with  very  few  operating  in  North  
America,  limited  engineering  and  spares  support,  and  a  history  of  gearbox  failures  (3  of  5  
installed).  
2. The  AAER  1500/77-­‐65m  design  never  received  certification  by  any  recognized  certification  
organization,  though  similar  designs  licensed  from  AMSC/Windtec  have  been  certified  by  
GL  and  DNV.  

  20  
 
DAR-­‐EN-­‐20120926-­‐revA   Portsmouth  Gearbox  Failure  Investigation   14  October  2012  

3. The  gearbox  design  may  be  defective,  specifically  having  insufficient  structural  stiffness  
resulting  in  uneven  1st  stage  planet  bearing  load  distribution  and  premature  failure,  or  
having  defective  bearings.  
4. A  similar  make  and  model  turbines  based  upon  the  AMSC  Windtec  design,  the  Fuhrländer  in  
Princeton,  NJ,  has  had  a  similar  gearbox  failure,  though  the  gear  ratios  are  slightly  different.  
5. Subsequent  similar  turbine  models  licensed  by  AMSC  Windtec,  the  AMSC  wt1650df  and  the  
Hyundai  HQ  1650  appear  to  have  nearly  identical  nacelles,  but  may  incorporate  an  
improved  gearbox.    Retrofit  options  should  be  considered.    Attempts  to  obtain  confirmation  
of  compatibility  via  AMSC  Windtec  or  Hyundai  to  date  have  been  difficult.  
6. Based  upon  a  preliminary  profit/loss  estimate,  it  does  not  appear  the  turbine  can  be  
operated  profitably,  even  if  the  gearbox  is  replaced  and  operates  without  failure  for  at  least  
10  years.    A  detailed  10-­‐15  year  pro  forma  with  anticipated  operating  costs,  debt  servicing,  
revenues,  energy  credits,  maintenance  reserves,  and  insurance  should  be  developed  with  
assistance  from  a  recognized  authority  such  as  DNV-­‐Kema  or  GL  Garrad  Hassan.  
7. Due  to  limited  service  experience  in  the  region,  a  collaborative  users   group  should  be  
developed.  Potential  collaborators  are  Windland  (operates  3  AAER  1500  in  California),  
Templeton  Municipal,  and  Princeton.  
8. A  procedure  to  prevent  operation  of  the  turbine  with  ice  on  the  blades  should  be  
implemented,  and  a  study  of  anticipated  loss  of  energy  production  due  to  curtailment  
should  be  commissioned.  
9. The  blades  should  be  inspected  by  LM  Glasfiber,  and  specifically  checked  for  manufacturing  
defects  by  serial  number.  
10. In  the  absence  of  a  highly  experience  service  provider,  an  Independent  Engineer  with  
intimate  knowledge  of  wind  project  operations  should  be  contracted  to  perform  annual  
project  monitoring.    
11. The  GasTOPS  wear  particle  monitor  should  be  returned  to  service.  This  monitor  will  
provide  sufficient  advance  warning  of  a  similar  failure  to  plan  for  repair  or  replacement  at  
lower  cost  and  less  downtime  than  the  current  event.    
12. A  24/7  vibration  monitoring  system  should  be  installed.    Bachmann  Electronics  is  highly  
recommended  for  the  turbine  due  to  the  Bachmann  controller  used  in  the  turbine.  
13. Turbine  SCADA  gearbox  bearing  temperature  should  be  more  closely  monitored  for  
opportunities  to  obtain  advance  warning  of  bearing  failure.  
14. The  blade  pitch  system  calibration  should  be  verified  by  a  qualified  technician,  and  existing  
offsets  should  be  recorded  to  determine  whether  the  blade  pitch  is  properly  set.    Incorrect  
calibration  may  have  been  a  contributing  factor  to  gearbox  failure.    
15. Portsmouth  should  enroll  in  the  free  National  Renewable  Energy  Collaborative  (NREL)  
Reliability  Collaborative  to  keep  up  to  date  on  most  pressing  reliability  issues,  learn  
methods  to  improve  reliability,    and  network  with  other  owners.  

  21  
 

You might also like