APPENDIX–B1 - BOQs and Financial offers for ONE SITE - Office Building -Tender: 2024/FNYAR/FNYAR/127032 (036/2024)

unit price
item Describtion unit Qty Total (USD)
USD
General Notes:- FAO contracts are normally LUMP SUMP, the contractor’s financial offers must cover all project expenses
regardless of the actual quantities executed on-site. Thus, the contractors shall take the time to study all the project documents
during the tendering process and must highlight any areas of concern before submitting their final financial offers. In other words,
the actual quantities of individual Works might be lower or higher than originally foreseen in the Bill of Quantities, but FAO’s
financial liability remains the same.
1. The Contractor is responsible for the safety, security, maintenance, and storage of construction materials in the construction
site from the site handover date up until the completion of the contract works.
2. All contractor's personnel must adhere to the highest standards of safety in construction projects including the use of
personal protective equipment, hygiene, health, adoption, and application of the Environmental and Social Management Plan
ESMP provided by FAO.
3. It is the responsibility of the Contractor to ensure the availability of the material as per the contract and plan for its delivery
to the construction site. However, no material should be delivered to the site before the prior approval of the resident engineer.
4. The contractor shall use dust control measures on site, such as spraying water to prevent dust, organizing access to and from
the construction site, coverage of the trucks transporting waste and construction debris, carting away the waste material to
approved disposal areas, preventing burning objects or/and materials in the open air, maintaining machinery and vehicles in good
working conditions to reduce emissions and the- Vehicles and equipment must be serviced and maintained regularly.
5. The contractor must remove all the construction obstacles including the underground concrete foundation, any type of walls,
buildings, steel structures, etc.
6. Upon the site handover and after the site clearance, the Contractor must allocate the benchmarks and start the setting out of
the buildings in accordance with the drawings and specifications.
7. The contractor must obtain all the mandatory clearances and licenses before the start of the construction activities and plan
0.00
the construction timetable accordingly. It is also mandatory to plan for unexpected incidents where the construction may be put in
halts for design review or contract amendments. However, in case such an incident occurs the Contractor should not expect any
monetary compensation from FAO.
Excavation: The excavation either mechanical or manual must be carried on in accordance with the dimensions
specified in the drawings,
The excavation must be protected from sliding and shaped evenly.
The materials used for backfilling must be subbase materials. Nevertheless, it is at the engineering judgment of the resident to allow
the use of the materials resulting from the excavation for backfilling.
Only mechanical compaction is allowed, the size of the compaction machine will be decided by the engineer depending on the
complexity and nature of the area to be compacted.
The costs of soil investigation and mechanical testing of materials should be included in the rate.
All concrete (plain or reinforced) must be made of sulfate-resistant cement only and tested using the 15x15x15 cubes method. The
result after 7 days will be used as an indication of the 28-day result and should not be less than 75% of the required compressive
strength. The cost of sampling testing should be included in the concrete rate.
All concrete must be vibrated using mechanical vibrators, the vibrator diameter should be ¼ of the wall or column thickness
All steel used in the reinforced concrete must be brought from a certified source. However, the contractor must be obliged at the
request of the resident engineer to perform any steel test that is required to confirm the suitability of the steel.Concrete: All design
mix concrete shall be machine-batched
with automatic weigh batcher, machine mixed, and machine
vibrated or Ready Mix Concrete prepared in depot and
transported by transit mixer to the site of work Unless
otherwise stated. All concrete shall be of grade as per
Specifications
Note
Rates for concrete shall include construction joints,
expansion joints or contraction joints as necessary. Including
mockups and finishes. Include MEP Opening and sleeves
according to drawings. Include Formwork (for all necessary
boarding, supports, erecting, framing, cutting angles, cleaning,
apply approved foam oil, and wetting before placing concrete
removal etc.), formwork shop drawings. Concrete materials
(including samples of cement, aggregates, admixtures, curing
materials, other concrete accessories where specified,
accompanied with materials test report from qualified
independent testing agency, materials certificate, and
qualification data for manufacturer), mixture design, placement 1
procedures, compacting, vibrating, curing and making good
The excavation must be protected from sliding and shaped evenly.
The materials used for backfilling must be subbase materials. Nevertheless, it is at the engineering judgment of the resident to allow
the use of the materials resulting from the excavation for backfilling.
Only mechanical compaction is allowed, the size of the compaction machine will be decided by the engineer depending on the
complexity and nature of the area to be compacted.
The costs of soil investigation and mechanical testing of materials should be included in the rate.
All concrete (plain or reinforced) must be made of sulfate-resistant cement only and tested using the 15x15x15 cubes method. The
result after 7 days will be used as an indication of the 28-day result and should not be less than 75% of the required compressive
strength. The cost of sampling testing should be included in the concrete rate.
All concrete must be vibrated using mechanical vibrators, the vibrator diameter should be ¼ of the wall or column thickness
All steel used in the reinforced concrete must be brought from a certified source. However, the contractor must be obliged at the
unit price
item Describtion
request of the resident engineer to perform any steel test that is required to confirm the suitability of the steel.Concrete: All design
unit Qty Total (USD)
mix concrete shall be machine-batched
with automatic weigh batcher, machine mixed, and machine USD
vibrated or Ready Mix Concrete prepared in depot and
transported by transit mixer to the site of work Unless
otherwise stated. All concrete shall be of grade as per
Specifications
Note
Rates for concrete shall include construction joints,
expansion joints or contraction joints as necessary. Including
mockups and finishes. Include MEP Opening and sleeves
according to drawings. Include Formwork (for all necessary
boarding, supports, erecting, framing, cutting angles, cleaning,
apply approved foam oil, and wetting before placing concrete
removal etc.), formwork shop drawings. Concrete materials
(including samples of cement, aggregates, admixtures, curing
materials, other concrete accessories where specified,
accompanied with materials test report from qualified
independent testing agency, materials certificate, and
qualification data for manufacturer), mixture design, placement
procedures, compacting, vibrating, curing and making good
after the removal of formwork, preparation of surfaces,
roughening/chipping, Concrete shall be measured as the net 0.00
area/volume, as shown on the drawings. All according to the
drawings, specifications, any relevant contractual documents
and approval of the Engineer. Reinforcement: (all reinforcement
shall be as per relevant
British Standards having minimum characteristic strength of
460 N/mm2) , rate for reinforcement shall include
supplying, cleaning, cutting, bending, fabricating, binding,
placing in position, binding wires, ties, supporting bars, spaces,
chairs, wastage etc. Steel reinforcement shop drawings.
Reinforcement samples materials and accessories,
accombined with materials test report from qualified
independent testing agency, materials certificate, welding
certificates and qualification data for manufacturer),
Reinforcement shall be measured as the net weight as shown
on the drawings.All according to the drawings, specififications,
any relevent contractual documents and approval of the
Engineer.

2
460 N/mm2) , rate for reinforcement shall include
supplying, cleaning, cutting, bending, fabricating, binding,
placing in position, binding wires, ties, supporting bars, spaces,
chairs, wastage etc. Steel reinforcement shop drawings.
Reinforcement samples materials and accessories,
accombined with materials test report from qualified
independent testing agency, materials certificate, welding
certificates and qualification data for manufacturer),
Reinforcement shall be measured as the net weight as shown
on the drawings.All according to the drawings, specififications,
any relevent contractual documents and approval of the unit price
item Engineer. Describtion unit Qty Total (USD)
USD

0.00

1 Excavation, backfilling, site leveling and foundations:


Excavation work for foundations:
In cubic meters: - Digging soil for the foundations for office building and water tank
with dimensions indicated with a height of not less than 0.7 m according to the
1.1 drawings, and the price includes the removal of all construction waste Inside the site m3 72 0.00
and the transfer of all waste to the dump outside the city.

3
unit price
item Describtion unit Qty Total (USD)
USD
Replacement of Foundation soil
This item will only be used in case the bearing capacity of the foundation soil for office
building and water tank is less than the design bearing capacity of 200Kn/m2 The use of
1.2 this item will require prior written approval of the Contract Manager. m3 24 0.00

BackFilling works
1.3 In cubic meters: - Backfill with very clean soil from the site waste about 95% of the m3 73 0.00
laboratory density for office building and water tank .

Total 0.00

4
unit price
item Describtion unit Qty Total (USD)
USD
2.1 Concrete works:-

The contractor must properly serve the concrete as directed by the supervising
engineer and choose a ready-mixed concrete mix that provides excellent aggregate
materials and provides tests for casted samples. The concrete must be shaken
during casting in all concrete works with mechanical vibrators and prices Concrete
includes the following: - 1-
Wooden and reinforcing iron work. 2- Concrete
mixture works and water treatme nt works for the period specified in the drawings,
specifications, and additions required by the drawings of the concrete mixture.
2.1.1 note
3- Testing the cubes according to the engineer’s
request. 4- The contractor shall be responsible for supplying
materials that do not fit to standard specifications.
5- The contractor bears the responsibility to store the materials in a suitable way
that does not expose them to damage, and the contractor should quickly transfer
the damaged materials from the site directly and bear the full responsibility when
using any damaged materials. 6- It is necessary to use sulfur-resistant Portland
cement for all works of concrete and reinforced with foundations and floors.

5
unit price
item Describtion unit Qty Total (USD)
USD
2.2 Plain concrete works:
Plain concrete under foundations:
In square meters / supplying and executing ordinary concrete under foundations for
2.2.1 office building and water tank , thickness of 10 cm, m3 7 0.00
And considering that the cement mixture consists of 250 kg of cement per cubic meter.

Plain concrete for slope roof surface:


In square meters/supplying and implementation of plain concrete, the slope of the
2.2.2 m3 1 0.00
surface must be 5 cm, and the strength of the concrete is not less than 150 kg/cm 2, with
the necessary joints being made.
Plain concrete for floors:
In square meters / supplying and executing ordinary concrete for the floors, thickness of
2.2.3 10 cm, under a layer of fracture of a ruh stone of 7-8 cm thickness And considering that m3 3 0.00
the cement mixture consists of 250 kg of cement per cubic meter.

Total 0.00

6
unit price
item Describtion unit Qty Total (USD)
USD
2.3 Rainforced work:-
In cubic meter / supply and cast concrete reinforced with a resistance of (280) kg /
cm2 unless otherwise indicated and according to the sizes and sections indicated in
the executive plans all what is necessary to carry out the work to the fullest extent 0.00
according to the specifications, drawings and instructions of the supervising
engineer. The item :includes the following
Reinforced concrete for the foundations:
In cubic meters: reinforced concrete for thefoundations FOR for water tank using
Portland cement and with a resistance of not less than 280 kg / cm2 and the amount of
2.3.1 cement not less than 350 kg / m3 and it includes (logging, cutting and laying iron, m3 4 0.00
casting, shaking the concrete by vibrating and spraying, and all that is required)
according to the drawings, specifications and instructions of the supervising engineer.

Rainforecd concrete for beams strip footing water tank


In cubic meters : reinforced concrete for beams with a resistance of not less than 250
kg / cm2, and the price includes the necessary tests and examinations for iron and
2.3.2 m3 1 0.00
concrete cubes, the use of mechanical vibrators - spraying concrete - carpentry and
blacksmithing work according to the drawings, specifications, and instructions of the
.supervising engineer

Reinforced concrete for the cloumns:


In cubic meters: reinforced concrete for the cloumns for water tank with a height of 0.5
m using Portland cement and a resistance of not less than 300 kg / cm2 and the amount
2.3.3 m3 0 0.00
of cement not less than 400 kg / m3 and includes (logging, cutting and laying iron,
casting, shaking the concrete by vibrating and spraying, and all necessary) According to
.the drawings, specifications, and instructions of the supervising engineer

Rainforecd concrete for grund beams:


In cubic meters / reinforced concrete for beams with a resistance of not less than 250
kg / cm2, and the price includes the necessary tests and examinations for iron and
2.3.4 m3 4 0.00
concrete cubes, the use of mechanical vibrators - spraying concrete - carpentry and
blacksmithing work according to the drawings, specifications, and instructions of the
supervising engineer.

7
unit price
item Describtion unit Qty Total (USD)
USD
Rainforecd concrete for beams:
In cubic meters / reinforced concrete for beams with a resistance of not less than 250
kg / cm2, and the price includes the necessary tests and examinations for iron and
2.3.5 m3 2 0.00
concrete cubes, the use of mechanical vibrators - spraying concrete - carpentry and
blacksmithing work according to the drawings, specifications, and instructions of the
supervising engineer.
Rainforced conctrete for roof:
In cubic meter / reinforced concrete for roof (5 diameters 12 per meter in both
directions) 10 cm thick, with a resistance of not less than 250 kg/cm 2, and the price
2.3.6 m3 4 0.00
includes the necessary tests and examinations for iron and concrete cubes, the use of
mechanical vibrators - spraying concrete - carpentry and blacksmithing work according
to the drawings, specifications, and instructions of the engineer admin.
Supply and implementation of windows and doors reinforced concrete lintels with a
thickness of 20 cm, with steel reinforcement (3Ø14 top and 3Ø14 bottom, and
2.3.7 ties/stirrups 1Ø8 @15 cm). according the above specification, workmanship and m3 0.45 0.00
instruction of supervising engineer.

Total 0.00
3 Building works: -
All types of buildings are implemented according to the drawings, specifications,
and instructions of the supervising engineer. The contractor must approve a sample
of all types of stones and blocks used prior to delivery - with written approval -, 0.00
and the cement mortar used in the construction will be at a mixing rate of 300 kg of
cement per cubic meter sand .
Basis workers
In cubic meters: Building a support stone for the foundations with a height of 50 cm and,
3.1 provided that the concrete is not less than 25% of the volume with a good abundance m3 13 0.00
and spraying, according to the drawings, specifications and instructions of the
supervising engineer.

8
unit price
item Describtion unit Qty Total (USD)
USD
The stone buildings works:
In cubic meters: the implementation of buildings of black stone (basalt) with a thickness
3.2 m3 30 0.00
of 60 cm and a height of 1.75 m, according to what is shown by the executive drawings.
According to the specifications, drawings and instructions of the supervising engineer.

Stairs And landing area for building entrances


Construct staircase and landing area for the building entrance, build black "Basalt" stone
squared on a plain concrete 10cm thick under ground level in 50cm deep to the ground
floor level with 40cm thickness, backfill inside landing area and under stairs with good
3.3 L.s 1 0.00
soil with compacting then crush stones layer 10cm and finally cast reinforced concrete
with steel reinforcement 5Ø8/m for both ways for landing area (at level of floor) and
under staircases, work shall include all necessaries to complete the work and according
to drawings and the specification and instruction of supervising engineer.

Supply and installation of mosic granulated anti-skid tiles for building entrance
(Landing area and staircase), in the required color and approved form. The price also
3.4 includes install skirts sand and cement mortar for installation and settlement works by m2 8 0.00
mixing cement mortar ratio 1: 3 with the implementation of all necessary to complete
the work as per specification and direction by the supervising engineer.

9
unit price
item Describtion unit Qty Total (USD)
USD
Total 0.00
4 Concrete cladding works: -

1) All whitewashing works, cement roughing for all walls, internal ceilings, external
awnings, stairs, and stairs with a mortar of 300 kg cement / m3 nice, with holes,
tendons, edges, and grouting after roughing.
2) The quantities listed in the table deducted the openings for (windows, doors and
qamarieat).
3) The Contractor shall hand over the core and string works to the engineer before
commencing the cladding works.
4) The contractor shall implement a coarse cement splash layer (450 kg cement / m3)
with spraying for three days for all walls, internal ceilings, windows, and facades. 0.00
5) Making an iron grille in the places where the walls meet with the reinforced
concrete and above the places of the electricity pipes, then splashing on it.
6) The finishing of all paneling works in the correct manner, with the necessity of
finishing the internal and external corners resulting from the walls meeting each other
or with other elements in a good way and taking special care of the finishing of these
facings, taking into account that the ceilings facing the walls work in a circular manner
(a quarter of a circle Radius 5 cm) and at the edges of the columns and walls, bevels of
1 cm.

10
unit price
item Describtion unit Qty Total (USD)
USD
Interior cement plaster for roof :
In square meters: - Supplying and implementing cement cement for internal roofs using
4.1 Portland cement and includes cement splashes and the basic layer of cement mortar, m2 26 0.00
with spraying (3) times per day, according to the drawings, specifications, and
instructions of the supervising engineer.

Interior cement plaster:


In square meters: - Supplying and implementing cement cement for internal walls and
4.2 walls using Portland cement and includes cement splashes and the basic layer of m2 124 0.00
cement mortar, with spraying (3) times per day, according to the drawings,
specifications, and instructions of the supervising engineer.

Moisture insulating layer for the roof:


In square meters: Supplying and installing a moisture-insulating layer three faces of
4.3 bitumen heated on two layers of flats and has inserts around the wall to the height of m2 28 0.00
50 cm a with the introduction of its horizontal ends as much as 3 cm inside the
buildings.
External cement plaster:
In square meters: - Supplying and executing plastering of the external, walls using
4.4 Portland cement, which includes cement splashes and the basic layer of cement mortar m2 119 0.00
and serving well and with the same specifications as the previous item.

Total 0.00

11
unit price
item Describtion unit Qty Total (USD)
USD
5 Painting works:-
In square meter / matte oil paint of good quality and approved according to the color
specified in the specifications for the walls and interior walls, and wherever necessary
for similar works. The price includes:
- Good sanding of the cladding face using sandpaper and stone, and making a
foundation face of lime before making the putty.
- Good restoration with putty of cracks, letters, corners, voids, around doors and
windows (frames), electrical and sanitary works.
Apply a good quality putty on both sides, with the necessity of smoothing well using
5.1 sandpaper between each side until the surface becomes smooth, polished and m2 124 0.00
homogeneous, free of bumps or kinks and so on.
- Applying oil paint (three sides) of good quality and approved in advance by the
engineer, with the required color and with the appropriate calibration, provided that
samples are made on the walls to be received and approved by the engineer.

In square meters / the same as the previous item, but with white Amilshn (watery)
5.2 paint for the ceilings on the base and three sides with putty and sanding according to m2 27 0.00
the specifications, drawings, and instructions of the supervising engineer.

12
unit price
item Describtion unit Qty Total (USD)
USD

In square meters / the same as the previous item. Amilshn paint for external, walls
5.3 (water-based) is resistant to weather conditions and the inner wall of the real estate m2 124 0.00
from three sides with putty and sanding.

Total 0.00
6 Isolation works: -
An insulating layer for the surfaces of the stone chair:
Per square meter: Coating surfaces and materials with three layers of hot bitumen
6.1 m2 132 0.00
to protect against moisture or any insulating material according to the
specifications and instructions of the supervising engineer.
Moisture insulating layer for bathroom floors:
In square meters: Supplying and installing a moisture-insulating layer for bathroom
floors from three faces of bitumen heated on two layers of flats and has inserts
around the wall to the height of 50 cm above the reinforced tiles with the
introduction of its horizontal ends as much as 3 cm inside the buildings and ordinary
6.2 concrete thickness of 10 cm installed on the insulating layer of moisture and size m2 6 0.00
according to The horizontal projection without a premium for the sole and the
succession.

Total 0.00

13
unit price
item Describtion unit Qty Total (USD)
USD
7 Metal works:
“Metal columns and bridges IPE 3
In linear metres: Supply and implementation of metal columns and bridges of IPE with
a total length of 39 m for the water tank. The price includes all installation work,
7.1 formwork, metal connections and everything necessary to implement the item L.M 39 0.00
according to the drawings and directions of the supervising engineer.”

14
unit price
item Describtion unit Qty Total (USD)
USD
Iron protection net:
In square meters: Supplying and installing an iron protection net according to the
approval and directives of the supervising engineer. The price includes an angle of 50
7.2 x 50 mm, installation at an angle of iron in the marble. The price also includes a m2 5 0.00
primer and two-sided paint in the approved color and as directed by the supervising
engineer.

Metal Compact Doors:D1, D2


In square meters: T doors, galvanized stacking, for door, service accessories with
shalman, 2 "(circled on the door completely), and the work of the shutters, from iron
grates (1 inch x 2 hens.), good artistic work with the work of three hinges, including
7.3 anti-rust paint after emery and good grinding of traces. Soldering with ultrashild gloss No 2 0.00
finish with primer. Three coatings for the door and throat are wide. Stacking not less
than 20 cm. The closures are provided that the solutions are executed before the
dressing works, and it is fixed with 3 Holvasses from each side with a length of 20 cm
according to the instructions and instructions of the supervising engineer.

Total 0.00
8 Aluminum works:
Supply and installation of aluminum doors for bathrooms with dimensions of 0.7 * 2.0
8.1 (D3) with a thickness of not less than 2 mm. No 2 0.00

Supply and installation of aluminum windows (W1) for the guard room with sash and
shank grilles, and installation of protection posts for the windows with 6 mm thick
8.2 glass in the specified color. With all supplies and handles, Lexus Taiwan, 4*4 cm m2 4 0.00
frame, 6.5 cm partitions, and external corners, according to the drawings and
instructions of the supervising engineer, and do everything necessary.

15
unit price
item Describtion unit Qty Total (USD)
USD
Supplying and installing aluminum windows for bathrooms (W2)(0.6*0.6) with glass
with a thickness of 6 mm in the specified color.With all supplies and knobs and the
8.3 throat 4 * 4 cm and cutouts 6.5 cm and the corners are external according to the No 3 0.00
drawings and the instructions of the supervising engineer and do all the necessar

Total 0.00
9 Tiling works

16
unit price
item Describtion unit Qty Total (USD)
USD
In Square meter / Mosaic tiles 20 x 20 x 2.5 cm, automatic, with broken marble and
white cement, provided that the thickness of the white cement is half the thickness of
the tiles, with the implementation of its sole with a height of 10 cm. The price
includes:
- Spread a layer of small Aggregate and a layer of cement and sand supplies at a ratio
of (1:3).
- Make a layer of cement and sand mortar with a thickness of not less than 2.5 cm for
gluing and fixing the tiles.
- Installing the tiles so that the joints of the tiles are in the form of regular straight
lines as they should be
Cut the tiles automatically when cutting is needed, and the excess mortar is cleaned
after stacking.
- To cut the tiles automatically when cutting is needed, and the excess mortar is
cleaned after stacking.
- A wooden mallet is used to knock the tiles during installation, with the necessity to
ensure that the surface is flat
9.1 - Clean the joints from cement residues with a wire brush, at a depth of 4 cm. m2 28 0.00
Fill joints with white cement mortar and grout.
- Spraying with abundant water daily and for an appropriate period - Scouring,
polishing, and mechanical smoothing.
- Finishing, cleaning, and removing residues. The price also includes all that is
necessary to finish and deliver the work to the fullest
Faced with the specifications, drawings, and instructions of the supervising engineer.

17
unit price
item Describtion unit Qty Total (USD)
USD
Supply and installation of mosaic tiles for Skirting , ministries, approved by the
supervising and certified engineer. The price also includes the reclamation work,
mortar for installation, and grouting work with a cement mortar mixing ratio of 1:3,
along with making channels, manholes, and a 10-inch high-pressure pipe network to
drain water into the sea, along with implementing everything necessary to complete
the work according to the directives of the supervising engineer. . L.M 28 0.00

In square meters / supply and installation of ceramic tiles (30 cm x 30 cm x 8 mm) for
2 bathroom floors, and the ceramic should be soaked with water before m2 6 0.00
implementation.

In square meters / supply and installation of ceramic tiles (30 cm x 30 cm x 8 mm) for
2 bathroom floors, for 2m hight, and the ceramic should be soaked with water before m2 24 0.00
implementation.
Total 0.00
10 Plumbing works

Supply and installation of toilet, original type, good in required color, with ejection
10.1 box, and all water and sewage connections to the connection point in the outer wall. No 2 0.00

Supply and installation of chrome faucets with a diameter of 1/2 ", and includes all
10.2 necessary connections, hardware and all necessary, according to specifications. No 2 0.00

18
unit price
item Describtion unit Qty Total (USD)
USD
Supply and installation of wash pond 40 cm balloon required with column, mixer and
10.3 wiring for the hot and cold Install and install on pipes with all water connections from No 2 0.00
the outer wall, drainage to the ground machine

Supply, installation and connection of plastic pipes of diameter 4'' with all sewage
connections from the wall of the external bathrooms to the manholes, passing to the
10.4 site of the cesspool, in accordance with the drawings, specifications and instructions L.M 25 0.00
of the supervising engineer.

Supply and installation of a ground plastic siphon with all sewage connections to the
10.5 point of connection in the outer wall, according to the drawings, specifications, and No 2 0.00
instructions of the supervising engineer.

supply and installation of galvanized pipes r 3/4 "


Supply and installation of galvanized steel water pipes, (medium pressure) according
10.6 to British standard BS-1387 and threaded according to British standard BS_21 and L.M 30 0.00
includes fixation, with all connections.

Supply and installation of galvanized pipes, 1/2 "diameter


Supply and installation of galvanized steel water pipes, (medium pressure) according
10.7 to British standard BS-1387 and threaded according to British standard BS_21 and L.M 16 0.00
includes fixation, with all connections.

19
unit price
item Describtion unit Qty Total (USD)
USD

Sanitation chambers
Sanitation chambers with an internal size of 60X 60 x 80 cm, built from deaf silks with
10.8 a concrete base of 15 cm thickness, worn inside with cement-resistant salt, with No 3 0.00
regard to inclination, and covered with reinforced concrete and iron, according to the
drawings, specifications, and instructions of the supervising engineer.

Construct sewage collection pit.


Supplying and executing a sewage collection plant/pit for the internal dimensions of
net 3 m diameter and a depth of not less than (3 m) and no more than 5 meter the
price includes the following works:
1- Digging in any type of soil or rock and removing the waste to a suitable place
outside the health unit.
2- The supply and implementation of black squared stone basalt buildings or of the
region's stones for the baking with a thickness of 40 cm.
3- Supplying, implementing and casting reinforced concrete for the roof of the pit
consisting of a circular slab with dimensions of 3.8 meters diameter and a thickness
of 15 cm and reinforcement (6ɸ12 mm / m) in both directions (brushes and lids) and
provided that the cement percentage not be less than (350 kg / m³) and mixing ratio
10.9 (1: 1.5: 2.5) (Cement: Sand: gravel) The mixing is done using a mechanical mixer, and No 1 0.00
the price includes the supply, implementation and casting of the cover of the plant
from reinforced concrete with dimensions (80 * 80 * 10) cm.
4- use of salt resistant cement.
5- construct the pit cover of the reinforced concrete size 80 * 80 * 10 cm and
reinforcement (5ɸ8 mm / m) for both direction.

20
unit price
item Describtion unit Qty Total (USD)
USD

Supply and installation of UPVC plastic pipes with drilling and backfilling, diameter
100 mm, high pressure
11 In linear meters: the supply and installation of plastic pipes (UPVC 6 bar), and includes L.M 35 0.00
drilling and backfilling and all fittings - with fixing the sides of the drilling if necessary,
according to the drawings, specifications and instructions of the supervising engineer.

Supply and installation of a high-quality galvanized iron water tank with a capacity of
10 cubic meters,or 10000 liters with a float, a filter hole, and valves. It will be installed
11.1 over metal bridges on concrete foundations at a height of 300 cm from the ground, in No 1 0.00
accordance with the drawings, specifications, and instructions of the supervising
engineer.
By linear meter/supplying and installing (UPVC Class4) 3-inch pipes for water drainage
Rainfall as well as vertical drainage pipes, and the price includes connections, cutting,
and fixing by Brackets of galvanized iron fixed to the walls at distances not exceeding
11.2 2 m, according to drawings, and specifications, and instructions of the supervising L.M 11 0.00
engineer.

Total 0.00

21
unit price
item Describtion unit Qty Total (USD)
USD
11 Electrical works:-
Supply, deliver, install, test and commission new main distribution board (SDB), with
- Main input breaker 3P 32 A MCB, 6 way.
- Outgoing breakers one pole 2 of 10A MCB , and 2of 16A MCB
- The panel should be of type dipped in wall.
All the breakers should be LEGRAND-brand or Equivalent, including busbars. Work
11.1 also include Set 1 0.00
- The electrical wiring connection by 4x16 mm2 copper and earthing 6 mm2
equivalent from the main board in the processing machine building the connection
should be through PVC pipes 25 mm dia.
- Carrying out all the necessary civil works such as cutting, chipping, repairing,
finishing, and painting of wall work required to accomplish the work.
Power socket
Supply, install, test and commission complete electrical sockets 3P+E 13A, 230V, BS
1363, IP 40 this also include:
-Installing new wires from the distribution board as shown in the drawings of 4 mm2
copper cable and 4 mm2 for earthing in recessed pipes 25mm dia PVC.
11.2 - Carrying out all the necessary civil works such as cutting, chipping, repairing, No 5 0.00
finishing, and painting of wall work required to accomplish the work.
Note: All electrical equipment must be approved by supervision engineer before being
supplied.

Economical outdoor LED lamp works (40 watt):


Supply and installation of an economical lighting unit (40watt) motion sensor with
wiring, warterproof with the work of the necessary electrical switches, extension of
plastic pipes (PVC) and the withdrawal of the isolated pure copper wires, box,
connection to the distribution panel, and the work of the experiment and doing all
11.3 necessary according to the drawings, specifications and instructions of the supervising No 6 0.00
engineer.
The contractor is obligated to take all safety standards to avoid an electrical shock
accident

22
unit price
item Describtion unit Qty Total (USD)
USD
Economical LED lamp works (15 watt):
Supply and installation of an economical lighting unit (15 watt) motion sensor with
wiring, with the work of the necessary electrical switches, extension of plastic pipes
(PVC) and the withdrawal of the isolated pure copper wires, box, connection to the
distribution panel, and the work of the experiment and doing all necessary according
11.4 to the drawings, specifications and instructions of the supervising engineer. No 4 0.00
The contractor is obligated to take all safety standards to avoid an electrical shock
acciden

Supply, install, test and commission complete lighting point Ceiling Recessed 40 W,
including all supports, connections, with (4000)K CCT, minimum 30000 hr. working
lifetime, (110 - 120)lm/W luminous efficiency, RI>80% :
- Installing new wires from the distribution board as shown in the drawings of 2.5
mm2 copper cable and 2.5 mm2 for earthing of Standard qulity in recessed pipes
11.5 25mm dia PVC. No 4 0.00
- Carrying out all the necessary civil works such as cutting, chipping, repairing,
finishing, and painting of wall work required to accomplish the work.
Note: All electrical equipment must be approved by supervising engineer before being
supplied.

Supply, install, test and commission complete electrical lighting switches two gangs,
10A, 230V, IP 21, BS 3676 this also include:
- Installing new wires from the distribution board as shown in the drawings of 2.5
mm2 copper cable and 2.5 mm2 for earthing of Saudi or equivalent in recessed pipes
11.6 25mm dia PVC. No 1 0.00
- Carrying out all the necessary civil works such as cutting, chipping, repairing,
finishing, and painting of wall work required to accomplish the work.
Note: All electrical equipment must be approved by supervision engineer before being
supplied.

23
unit price
item Describtion unit Qty Total (USD)
USD
Supply, install, test and commission complete electrical lighting switches one gangs,
10A, 230V, IP 21, BS 3676 this also include:
- Installing new wires from the distribution board as shown in the drawings of 2.5
mm2 copper cable and 2.5 mm2 for earthing of Saudi or equivalent in recessed pipes
11.7 25mm dia PVC. No 2 0.00
- Carrying out all the necessary civil works such as cutting, chipping, repairing,
finishing, and painting of wall work required to accomplish the work.
Note: All electrical equipment must be approved by supervision engineer before being
supplied.

Economical outdoor LED lamp works (40 watt):


Supply and installation of an economical lighting unit (40watt) motion sensor with
wiring, warterproof with the work of the necessary electrical switches, extension of
plastic pipes (PVC) and the withdrawal of the isolated pure copper wires, box,
11.8 connection to the distribution panel, and the work of the experiment and doing all No 5 0.00
necessary according to the drawings, specifications and instructions of the supervising
engineer.
The contractor is obligated to take all safety standards to avoid an electrical shock
accident

Ceiling fan Supply and installation


ceiling fans with high quality or
equivalent economically powered with the regulator, key and price inclusive of all
necessary to complete the work to the fullest and according to the supervising
engineer’s- Installing new wires from the distribution board of 2.5 mm2 copper cable
11.9 and 2.5 mm2 for earthing of Standard qulity in recessed pipes 25mm dia PVC No 2 0.00
instructions, engineering drawings and specifications.

24
unit price
item Describtion unit Qty Total (USD)
USD
Supply, install, test and commission complete electrical lighting switches three gangs,
10A, 230V, IP 21, BS 3676 this also include:
- Installing new wires from the distribution board as shown in the drawings of 2.5
mm2 copper cable and 2.5 mm2 for earthing of Saudi or equivalent in recessed pipes
12 25mm dia PVC. No 1 0.00
- Carrying out all the necessary civil works such as cutting, chipping, repairing,
finishing, and painting of wall work required to accomplish the work.
Note: All electrical equipment must be approved by supervision engineer before being
supplied.

Mounting Structure
Supply and install steel structure mountain as per drawings, specification and
as per the following details:
1- Supply and installation Cold-formed galvanized steel
2- Beam And Bracing Structure Mounting
12.1 3- Supply and installation Cold-formed galvanized steel LS 1 0.00
4- Sag Rod
The work include establishing all the solar panels on that mounting structure and
finish the job perfectly.

Supply, install, testing and commissioning of complete earthing system including but
not limited to earthing conductors, earth rodes, plates, earth pits, clamps, bonding,
terminations and for earthing all electrical installations and equipontential bonding of
all exposed and extraneous conductive parts, mechanical services including water
Pumps, HVAC equipments,etc.
The item includes all related accessories to complete the installation in accordance
12.2 with the IEE Wiring regulations, BS 7671 and as per technical specifications, drawings Set 1 0.00
and instruction of the site engineer.Earthing system for all electrical installations
main/sub-main and final distribution boars and equipontential bonding for the three
buildings
Earth resistance should be tested in presence of the FAO representative by calibrated
earth tester, the earth resistance should not be more than 5Ohm.

25
unit price
item Describtion unit Qty Total (USD)
USD
Total for Electric Work 0.00

26