LSPA1 - Management Meeting With TPSK (06-Jun-24)
LSPA1 - Management Meeting With TPSK (06-Jun-24)
LSPA1 - Management Meeting With TPSK (06-Jun-24)
MANAGEMENT DISCUSSION
FOR
SUBCONTRACT
06-June-2024
AGENDA
1. AGREED AMOUNT BY PARTIES
APPROVED ACCOUNTING LEDGERS, CRSWO&CRCWO,…
3. DIFFERENT AMOUNT
BOLTING, INLINE INSTUMENT, CRSWOs
Batches 1~2
4. SUMMARY
AGREED + SETTLED DIFFERENT AMOUNT
AGREED VALUE BY
NO DESCRIPTIONS REMARK
TPSK/PTSC
A QUANTITY PERFORMED 2,509,173,425,742 All-in + Direct + Indirect
3
2. EXPENSES OF PTSC & TPSK:
NO DESCRIPTIONS PTSC EXPENSES NO DESCRIPTIONS TPSK EXPENSES
CLAIMS BACKCHARGE
1 225,617,088,319 1 153,927,272,265
(Batch 1~2, excl. 300 Mpw) (Batch 1~6)
300 MANPOWER WE-UD PAID
2 23,231,345,407 2 50,145,244,429
(TPSK deducted) (Direct Amount)
DISCOUNT 25% RENTAL
3 11,468,377,970 3 CGC INCENTIVE 10,088,222,864
SCAFFOLDING
MANPOWER SUPPORT
4 FROM PTSC HEAD 188,007,890,825 4 HOLIDAYS WORKING 1,800,000,000
QUARTER
To reach the Project current success, PTSC spend total actual cost 466,9
billions VND
PTSC assume TPSK spend total 215,9 billion VND for Subcontract related
Backcharge, WE-UD Paid, CGC Incentive and Holidays working paid to PTSC
Parties to find solutions for alignment these two figures
4
3. DIFFERENT AMOUNT:
TPSK AGREED PTSC PROPOSED
NO DESCRIPTIONS REMARK
AMOUNT (*) AMOUNT
TPSK agreed: 40%, but reduce
1330 BOLTING
1 8,874,323,136 13,311,484,704 Backcharge
(Direct + Indirect)
PTSC proposed: 60% to AL approval
TPSK agreed 100%but reduce
2230 INLINE INSTRUMENT
2 2,501,930,471 2,501,930,471 Backcharge
(Direct + Indirect)
PTSC proposed: 100% to AL approval
CRWO-0594 TPSK agreed: 17,5% (=50%*35%)
3 3,001,681,724 8,576,233,498
(Repair Jacketing Damages) PTSC proposed: 50%
CRWO-0771
4 714,619,060 714,619,060 Closed
(Steam Trap)
CRWO-0776
5 998,349,333 2,142,798,568 TPSK removed Tower Scaff.
(Scaffolding for TML)
CRWO-0377 TPSK rejected
6 0 2,554,904,296
(Ceramic Fiber Insulation) PTSC proposed 100% workdone
7 TOTAL 16,090,903,724 29,801,970,596
PTSC is ready to discuss and finalize with TPSK together with Section 2 –
Expenses Amount of each Party
Note (*) TPSK agreed Direct Amount 13,499,022,540 VND. The added Indirect
Amount is calculated as per contractual X/Y Formula for each discipline
5
4. SUMMARY:
NO DESCRIPTIONS TPSK AMOUNT PTSC AMOUNT FINAL AMOUNT (*)
AGREED AMOUNT
1 2,929,470,255,052 2,929,470,255,052 2,929,470,255,052
(See Section 1)
SETTLED DIFFERENT
2 AMOUNT 16,090,903,724 29,801,970,596 TO BE UPDATED
(See Section 3)
3 TOTAL 2,945,561,158,776 2,959,272,225,648 TO BE UPDATED
3 IN USD ($) $126,719,575 $127,309,432
Parties have showed all efforts, full responsibilities for settlement period.
PTSC is willing to settle with TPSK for Project closure on amicable approach
Note (*) upon settlement, Parties shall mutually release and forever
discharge of each other from, any and all claims and howsoever and
6
Thank you