Professional Documents
Culture Documents
Homework_1
Homework_1
1.4.1 Dashboards………………………………………………………….6-10
• Burndown ..…………………………………………………….. 6
• Cost Overview……………………………………………………7
• Project Overview ……………………………………………….8
• Upcoming Tasks ………………………………………………...9
• Work Overview …………………………………………………10
• Cash flow…………………………………………………………11
• Cash Overruns ……………………………………………………12
• Earned Value ……………………………………………………..13
• Resource Cost Overview ………………………………………... 14
• Task Cost Review ……………………………………………….. 15
• Critical Tasks ……………………………………………………. 16
• Late Tasks…………………………………………………………17
• Milestone Report…………………………...…………………….. 17
• Resource Overview………………………………………………. 18
1.5 Conclusion……………………………………………………………….19
To prepare the essential construction work schedule for this project, University Technology
Malaysia (UTM), Johor, Malaysia, has chosen to use its existing college block, L22. This
project is being undertaken on behalf of University Technology Malaysia. For the purpose of
this project, however, it is assumed that the structure will be entirely new, with construction
scheduled to begin on July 1, 2024, and finish on July 1, 2025. The L22 project is a two-story
building located in the university's Western area, where most of the campus.
SITE WORK
ZONE A
Out at Zone A
Earthwork at Zone A
ZONE B
Survey and Setting Out at Zone B
Earth work at Zone B
ZONE B
Excavation footing zone B
Lean Concrete at Zone B
Formwork at Zone B
Rebar at Zone B
Pour Concrete at Zone B
Backfill & Compact at Zone B
CLOSE OUT
Site Cleaning
Inspection
Hand Over
1. 4.1 Dashboards
Burndown
Fig-3: Burndown
Cashflow
Milestone Report
Resource Overview
The construction project detailed in this document exemplifies the importance of meticulous
planning and execution in achieving project success. Utilizing Microsoft Project for scheduling
and management, the project covers critical aspects such as task breakdown, cost management,
and resource allocation. The integration of comprehensive dashboards and cost analysis tools
ensures real-time tracking and efficient resource utilization. The detailed Work Breakdown
Structure (WBS) and well-defined timelines demonstrate a strategic approach to meeting
project milestones within the specified period. Overall, this project highlights the effective
application of project management principles and software tools to deliver a construction
project that adheres to the client's requirements and standards, showcasing a robust framework
for future projects.
THANK YOU
SEAA 4113-03 Page | 19