1.5 MOS
1.5 MOS
REV 0 - 2023.11
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE 00
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 00
CONTRACTOR REV.
XE CẨU 40T
XE CẨU 40T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE XE CẨU 40T
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 01
CONTRACTOR REV.
XE CẨU 250T
XE CẨU 250T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE XE CẨU 250T
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 02
CONTRACTOR REV.
XE CẨU 250T
XE CẨU 250T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE XE CẨU 250T
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 03
CONTRACTOR REV.
XE CẨU 800T
XE CẨU 800T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE XE CẨU 800T
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 04
CONTRACTOR REV.
Xe cẩu 40 T GHI CHÚ CHUNG LẮP DỰNG THÁP 28.0 m
+ Sử dụng xe cẩu 40T hạ hàng và tổ hợp tháp thang trên mặt đất
+ Tháp thang được tổ hợp nằm trên mặt đất , kê bằng gỗ kê
+ Sử dụng giàn giáo để công nhân di chuyển lên lắp bu lông liên kết
+ Nghiệm thu lực siết bu lông trên nền
+ Sử dụng xe cẩu 250T đỡ đầu , xe cẩu 110T đỡ đuôi
+ Nâng tổ hợp theo phương ngang sau đó từ từ nâng đầu cáp xe cẩu 250T lên cao
, đến khi tổ hợp thẳng đứng thì thả tự do cáp xe cẩu 110T
+ Xe cẩu 250 T từ từ đưa tổ hợp vào vị trí
+ Công nhân trên nền thi công bu lông liên kết
+ Sau khi hoàn tất bu lông liên kết , tiến hành lắp thủ công hoàn thiện các vị trí lan
can trên đầu tháp.
Recommended torque ( for Guidane only) / Đề xuất trực tiếp ( chỉ để hướng dẫn)
Bolt size
No kích
STT thước N.m Ft.I.b N.m Ft.I.b N.m Ft.I.b N.m Ft.I.b
bulong ( Newton- ( Foot- ( Newton- ( Foot- ( Newton- ( Foot- ( Newton- ( Foot-
Meter) Pounds) Meter) Pounds) Meter) Pounds) Meter) Pounds)
Grade
4.6 5.6 8.8 10.9
Cấp độ
1 M12 32 24 40 29 86 63 120 88
2 M16 79 58 98 72 210 154 295 217
3 M20 155 114 190 140 410 302 580 427
4 M24 265 195 330 243 710 523 1000 737
5 M27 390 287 490 361 1050 774 1500 1105
6 M30 530 391 660 486 1450 1069 2000 1474
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE TỔ HỢP THANG TRÊN NỀN
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 08
CONTRACTOR REV.
Xe cẩu 40 T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE TỔ HỢP THANG TRÊN NỀN
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 09
CONTRACTOR REV.
TỔ HỢP THÁP TRÊN NỀN
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE TỔ HỢP THANG TRÊN NỀN
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 10
CONTRACTOR REV.
TỔ HỢP THÁP TRÊN NỀN
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE TỔ HỢP THANG TRÊN NỀN
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 11
CONTRACTOR REV.
XE CẨU 250T
Rmin : 14 M
R : 20 M
XE VẬN CHUYỂN
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE MẶT BẰNG DI CHUYỂN TỔ HỢP
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 11
CONTRACTOR REV.
Thu cáp 3.0 M
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE DI CHUYỂN TỔ HỢP VÀO VỊ
ISSUED FOR WIND FARM 2204 TRÍ LẮP DỰNG
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 12
CONTRACTOR REV.
Hook 2
Hook 1
60 60
60 60
Hook 1
90
30 60
2143 2008
2000 2015 2836 2799 2760 2740
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE Page 26
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 12
CONTRACTOR REV.
Xe cẩu 800T
Xe cẩu 250T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE NÂNG TỔ HỢP VÀO VỊ TRÍ
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 13
CONTRACTOR REV.
Vị trí lắp đặt
Xe cẩu 800T
R: 20 M
Rmin : 14 M
R:40 M
Rmin: 9 M
Xe cẩu 250T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE MẶT BẰNG LẮP DỰNG
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 13
CONTRACTOR REV.
Boom
length
: 93.0
m
Boo
m le
ngth
: 45
.0 m
MẶT CẮT
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE NÂNG TỔ HỢP VÀO VỊ TRÍ
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 14
CONTRACTOR REV.
Thông số maní thép
( Tham khảo chi tiết thuyết minh tính toán )
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE THÔNG SỐ TAI MÓC CẨU VÀ
ISSUED FOR WIND FARM 2204 MANÍ
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 16
CONTRACTOR REV.
Góc nhìn 3d móc cáp cẩu Mặt đứng móc cáp cẩu Mặt đứng móc cáp cẩu
Góc ngiêng 15 o Góc ngiêng 45 o Hoàn tất quy trình lật cấu kiện
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE CHI TIẾT MÓC CÁP ĐẦU THANG
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 17
CONTRACTOR REV.
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE NÂNG TỔ HỢP VÀO VỊ TRÍ S1
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 17
CONTRACTOR REV.
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE NÂNG TỔ HỢP VÀO VỊ TRÍ S2
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 18
CONTRACTOR REV.
Modul tháp thang:
Chiều dài : 28.0 M
Khối lượng : 50 T
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE NÂNG TỔ HỢP VÀO VỊ TRÍ S3
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE 19
CONTRACTOR REV.
CHI TIẾT ĐỈNH CỘT
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING MOS- 23
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE
CONTRACTOR REV.
- Sau thi thả cáp Pa-lăng thì
xe cẩu 250T đưa tổ hợp vào
vị trí thi công
- Công nhân đứng từ trong
thang ra thi công bu lông liên
kết , ( đảm bảo trong suốt
quá trình thi công công nhân
móc cáp cứu sinh vào lan
can.
- Sau khi thi công bu lông
liên kết phía trên
- Công nhân trên thang tiến
hành thả từ từ cáp palăng ,
công nhân phía dưới hỗ trợ
căn chỉnh đưa giằng vào vị
trí thi công
- Công nhân phía dưới tiến
hành khóa chốt chống giằng.
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING MOS- 24
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE
CONTRACTOR REV.
- Sau thi thả cáp Pa-lăng thì
xe cẩu 250T đưa tổ hợp vào
vị trí thi công
- Công nhân đứng từ trong
thang ra thi công bu lông liên
kết , ( đảm bảo trong suốt
quá trình thi công công nhân
móc cáp cứu sinh vào lan
can.
- Sau khi thi công bu lông
liên kết phía trên
- Công nhân trên thang tiến
hành thả từ từ cáp palăng ,
công nhân phía dưới hỗ trợ
căn chỉnh đưa giằng vào vị
trí thi công
- Công nhân phía dưới tiến
hành khóa chốt chống giằng.
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING MOS- 25
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE
CONTRACTOR REV.
THI CÔNG GIẰNG NGANG
REV. DATE REV. NO REVISION CONTENT REV. DATE REV. REVISION CONTENT PROJECT LEAD DESIGNED
Quotation No. DRAWING TITLE ENGINEER DRAWN BY CHECK BY DWG NO.
BY
Q23- GREATER CHANGHUA OFFSHORE
ISSUED FOR WIND FARM 2204
PROPOSAL DRAWING MOS- 26
BUILDING No. CONSULTANT: DATE: 2023/11 SCALE
CONTRACTOR REV.