Professional Documents
Culture Documents
Cpot Ipd Manual
Cpot Ipd Manual
Jan 2023-V3
CPOT –IPD Manual V3
Table of Content
CPOT-IPD Definition.............................................................................................................................................. 3
CPOT-IPD Purpose ................................................................................................................................................ 3
CPOT Parts Requirements ................................................................................................................................... 4
CPOT-IPD Process ................................................................................................................................................ 5
6.1 Deliveries................................................................................................................................................... 8
6.2 Packaging ................................................................................................................................................. 8
6.3 Marking of CPOT-parts ............................................................................................................................. 9
7. C-Builds ....................................................................................................................................................... 9
Contacts ............................................................................................................................................................... 10
Appendix 1 ........................................................................................................................................................... 12
CPOT-IPD Definition
CPOT-IPD Purpose
The CPOT IPD milestone was introduced to ensure a high-quality level of C-released parts,
produced and delivered by our supply partners to the assembly plant. Thereby we are
securing a robust and stable C-truck build, characterized by a minimum of late design
changes, which will lead to a predictable launch of production.
1. To ensure that the serial production tool is capable of producing parts which conform
to drawings and agreed technical specifications at C-release.
2. To ensure that the supply partner verifies the parts out of tool according to the
requirements (i.e: dimension, part feature, part function, etc.) described in the RTS
(Review of Technical Specifications) agreed at C-release.
3. To verify & prepare for serial production in the EDI system and secure assembly
plant readiness by In Plant Delivered CPOT parts.
Fit for V&V testing (representative of serial To be fit for Sales & Marketing activities
parts to be assembled at the C-Builds) (photos, videos.) or need to have serial
visual aspect
Produced with serial production tooling² To be produced with stable serial production
(When specific tooling is needed) process.
TR tests agreed for the CPOT parts to be To have Phase PPAP status
completed and test reports sent in time for
CPOT IPD
¹ Applicable for new parts. (For Carry over/Carry Across Parts, agreement should be made on P release)
² Wiring Harnesses do not require to be produced with serial production assembly boards (To allow for wiring harness fine tuning.) In
addition some components requiring production bonding fixtures (for example hoods) may have to be assembled from soft tools.
³ For some components (applicable for US only), pick-up from tool maker's location can be approved (for example roofs and hoods).
CPOT-IPD Process
Supplier
Award
1. Supplier Award
The price (including packaging / logistics / shipment costs) for CPOT IPD parts should be
agreed and stated in the price agreement between Volvo and the Supply partner, signed at
supply partner award.
For some projects there are specific requirements regarding the reporting of the dimensional
and functional requirements, please refer to the RFQ sent by Volvo.
RTS prior
to
C-release
Please refer to the previous page regarding mandatory requirements for CPOT parts.
C-Release
3. C-Release
The drawings and CAD-module are updated and sent to the supply partner. At C-release the
Supply partner will receive the tool order and the serial production order for the part.
CPOT-
Order
4. CPOT-Order
Volvo will order the CPOT-parts through a specific Quantity Order from the plant. The order
will be placed after C-release, according to plant requirement with the piece price as agreed
at contract signature (including packaging / logistics / shipment costs). Some projects may
have several C-build serie and the Supply partner will then receive one quantity order for
each serie. Any deviations from the normal ordering process will be communicated by
responsible buyer.
The Supply partner is responsible to secure that their EDI system can receive Quantity
Orders without a PPAP approval. Furthermore, the Supply partner is responsible to assure
that the logistic contact is aware of this process.
CPOT
Verification
5. CPOT Verification
In accordance with the quality reference documents (Supply Partner Quality Assurance
Manual, chapter 6.7) to be found on the Volvo Supplier Portal, supply partners are required
to produce and measure parts based on the C-release drawing using the tools intended for
production.
As a minimum, if nothing else is agreed, all of the following records should be sent to Volvo:
- 5 pieces to be fully measured with a complete report on all dimensional
requirements as specified on the drawing or CAD.
- A test report of all TR tests that have been agreed to be completed in time for
CPOT IPD.
- 100% measurement on critical characteristics [2R] & [3R], [SC] / [CC] features for
all parts.
Please write the subject of your email in CAPITAL letters respecting the following format :
1. Project name - PROJECT P1234
2. Part Number & Part Issue PN 1234567 Issue C01
3. Parma Manufacturing Code - 1234
Example: PROJECT P1234 – PN 1234567 Issue C01 – PARMA 1234.
Supply partner must request and get Volvo’s approval before any shipment of
parts with deviation in measurement results.
CPOT In
Plant
Delivered
6.1 Deliveries
As indicated in the order, CPOT-IPD parts must be delivered from the supplier to the Volvo
Group plant or regular pick-up point and dispatched according to delivery instructions
defined in the Volvo Group Trucks Operations “Delivery Manual” available on supplier portal
for each plant or region.
All supply partners for the consignee plant must use ATLAS system to book
the shipments as for serial production
Supply partners are expected to provide a logistics contact person for the deliveries
of CPOT-parts to communicate with Volvo after the order has been sent and before CPOT-
IPD deadline. Any deviation (quality and/or timing) must be communicated as soon as they
are being identified.
6.2 Packaging
Do not mix CPOT-IPD parts with normal production parts on the same
handling unit!
In order to avoid any mix-up of CPOT-IPD parts and production parts the packaging should
have a specific RED A4 label. The label should be weatherproof. For parts shipped in
pallets or combitainers the additional label should be placed next to the Volvo approved
transport label (Odette label). If the part is sent in smallbox the additional label should be
placed next to the standard Odette label for the handling unit (pallet) on V-Emb 153
cardboard label holder.
In addition, Supply partner should physically mark all parts with Part Number and Part
version. The marking should be the same as for prototype procedure. If not possible to
mark the part place the label inside the packaging as close as possible to the part for visual
check by material handler.
C-Build
7. C-Builds
CPOT parts are received by the final assembly plant, using the serial production system EDI,
to detect potential issues between the Volvo and the Suppliers systems, that need to be
resolved prior final serial production.
The plant will use a special production line dedicated to the C-truck builds in order to detect
any issues with the assembly of the part which need to be resolved.
The main purpose of the C-truck builds is verification and validation. The C-trucks are not
intended for use by the end customer,but are crucial for the success of the project.
Contacts
Volvo Contacts
• Supplier Quality Engineer
• Buyer
• Project Material Controller or Project Logistic Handler
• Packaging Engineer
• Product Engineer
If you have any questions regarding the CPOT-IPD process, please contact your buyer.
Appendix 1
CPOT - IPD
CPOT - IPD