Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Liability for Materials Specified in Bills of Quantities

By John B Molloy, LLB (Hons), BSc (Hons), FHKIS, FRICS, ACIArb Managing Director, James R Knowles
(Hong Kong) Limited

Quantity Surveyors often include The experts who gave evidence all agreed
specification of materials in the Bills of that it was generally known by organisations
Quantities. The specification may be such as the Building Research
advised by the Architect of the Engineer or Establishment and slag production
may simply be a standard clause adopted by companies, that steel slag (as opposed to
the particular quantity surveying firm. But other forms of slag) is not an inert material,
who is liable in the event that the specified and was prone to expansion.
materials prove to be unsuitable for the
works in question? Rotherham claimed that the contractors
were liable for the damage caused to the
This is the interesting question that arose in concrete slabs. They argued terms should be
the case of Rotherham Metropolitan implied into the contract at common law by
Borough Council v Frank Haslam Milan & analogy with reason of the Sale of Goods
Co Ltd and Another (1996) 78 BLR 1. Act as follows:
• The material should be reasonable fit for
The plaintiffs (Rotherham) were employers, the purpose for which it was supplied
who employed the defendants (Haslam and and
Gleeson), as contractors for the erection of a • The material should be of merchantable
new 5-storey office building, known as quality.
Norfolk House, to be used as the new civic
office of Rotherham in Northern England. For the 'Fitness for purpose' term to be
The contracts were on JCT 1963 (1977 applicable it must be shown that the
Revision) terms with quantities, which is employer informed the contractor of the
almost identical to the RICS/RIBA Contract purpose and then relied on him to provide
used for the vast majority of private materials to suit that purpose. In this case
developments in Hong Kong. the main point the court addressed was did
the employer trust the judgement of the
The bills of quantities referred to granular contractor or did he rely on his own
hardcore to be placed beneath the ground judgement or the judgement of or his agents
floor slab, and further provided: the architect and the quantity surveyor?

“Granular hardcore shall be graded or In answering this question the court firstly
uncrushed gravel, stone, rock fill, crushed considered the provisions of the contract.
concrete or slag or natural sand or a The contractors 'obligation was clearly 'to
combination of any of these. It shall not carry out and complete the works ...
contain organic material, material described by and referred to in the ...
susceptible to spontaneous combustion, contract documents'. In this respect the job
material in a frozen condition, clays or was to fill hardcore around the foundations.
more than 0.2% of sulphate ions as The material was to be of the quality and
determined by BS 1377.” standard specified in the contract documents.
The description of the material to be
The granular hardcore used by the supplied was (granular) hardcore and the
contractor contained steel slag which specification stipulated that it: ‘Shall be
expanded and caused cracking of the ground graded or unbrushed gravel, stone, rockfill,
floor slab. crushed concrete or slag or natural sand or a
combination of any of these’.
that description. It was sufficient that they
Secondly, the court considered the relative were suitable for one or more purposes.
skill and knowledge of the contractor as Here the description was of (granular)
compared to that of the employer or his hardcore, the purpose was as infill around
agents the architect and quantity surveyor. It the foundations but that was only one of
concluded that in reality the architects and several purposes for which steel-slag was
quantity surveyors assumed the commonly used. In other situations such as
responsibility for the whole design and in bituminous macadam it was entirely
specification of the work. They specified satisfactory. The steel slag was therefore,
hardcore to include steel slag because they commercially saleable; it was, therefore,
assumed that slag was suitable for the of merchantable quality.
purpose. They trusted their own knowledge
and did not need to rely on the contractors’ Accordingly, the court held firstly that
skill and knowledge. although in a building contract it would
often be appropriate to impose on the
Having considered these points the court contractor an implied duty that the materials
held therefore that it was unreasonable to should be reasonably fit for the purpose, in
expect that reliance was being placed on the this case the architect had extensive powers
contractor's skill and judgment and on this over the materials under the express terms
basis a warranty of fitness for purpose of the contract and had himself (or with the
could not be implied. quantity surveyor) determined that the
material was fit for the purpose of fill
With regard to the implied term for material. It was therefore not appropriate to
merchantable quality, the court first imply into the contract any undertaking that
considered whether such a term should be the steel slag should be reasonably fit for
implied into a building construction contract, this purpose.
and concluded that it should be implied.
Secondly whilst it was appropriate to imply
However, they did not consider that in this into the contract a term that the material
case the term had been breached. The court should be of merchantable quality, the
held that in order to comply with the material was in fact of merchantable quality,
requirement of merchantable quality, the since it was reasonably saleable under the
goods did not have to be suitable for every description ‘steel slag’.
purpose within the range of purposes for
which goods were normally brought under (Adopted from the HKIS Newsletter 8(5) May 1999)

You might also like