ITEM DESCRIPTION UNIT QTY RATE AMOUNT


1.00 MATERIAL-ONLY COST - PREFABS:
WALLING:

1.01 2500x600x90mm thick wall panels:

Precast 90mm thick panels No 279 1875 523,125.00

BEAMS AND BLOCKS:

1.02 T-beams
5mm pre-stressed Lm 744 1200 892,800.00

1.03 Blocks
400x200x150mm No 3345 100 334,500.00

1.04 50mm thick floor bed (class 15):


Sika fibre, 900g No 22 1350 29,700.00

Sand Tons 14 1900 26,600.00

Aggregate (coarse) Tons 20 1700 34,000.00

Cement Bags 81 700 56,700.00

TOTAL MATERIAL-ONLY COST 1,897,425.00

Add 30% Labor Costs: 569,227.50

Add 12% delivery costs: 227,691.00

GRAND TOTAL FOR MATERIAL + LABOR FOR PREFAB WORKS 2,694,343.50

1 of 3
ITEM DESCRIPTION UNIT QTY ADJ QTY RATE TOTAL

2.00 RC SUPERSTRUCTURES

CONCRETE WORKS

2.01 RC CONCRETE

Beams
Class 25 (1:1.5:3) CM 12 12.00
Cement Bags 84.00 750.00 63,000.00
Sand Tons 7.00 1500.00 10,500.00
Ballast Tons 7.00 1500.00 10,500.00

Columns
Class 25 (1:1.5:3) CM 6 6.00
Cement Bags 42.00 750.00 31,500.00
Sand Tons 4.00 1500.00 6,000.00
Ballast Tons 4.00 1500.00 6,000.00

Staircase and landings


Class 25 (1:1.5:3) CM 1 1.00
Cement Bags 7.00 750.00 5,250.00
Sand Tons 1.00 1500.00 1,500.00
Ballast Tons 1.00 1500.00 1,500.00

2.02 REINFORCEMENT

High yield square twisted reinforcements


bars to B.S 4461 (Assorted and
provisional)

Assorted KGS 2714 2714.00 115.00 312,110.00


BARS
447,860.00

Add 30% labor costs 134,358.00

TOTAL FOR SUPERSTRUCTURE CARRIED TO SUMMARY 582,218.00

2
DESCRIPTION AMOUNT

3.00 TENTATIVE GRAND SUMMARY

Total for prefarb works brought forward 2,694,343.50

Total for RC superstructure brought forward 582,218.00

GRAND TOTAL 3,276,561.50